Skip to main content
Dod o hyd i Brosiect Seilwaith Cenedlaethol

Gwasanaeth beta yw hwn - bydd eich adborth yn ein helpu i'w wella.

River Humber Gas Pipeline Replacement Project Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 9 September 2015

Caeodd yr archwiliad ar 7 March 2016

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

28 Gorffennaf 2015 - Site Visit (Unaccompanied)

Caeedig

Unaccompanied site visit

9 Medi 2015 - Preliminary Meeting

Caeedig

Preliminary Meeting

23 Medi 2015 - Deadline 1

Caeedig

Deadline 1 Deadline for the reciept of: • Statements of Common Ground (Drafts) and summary schedule • Updated plans • Updated Schedule of Mitigation Measures • Updated Schedule of Progress of Voluntary negotiations • In-combination assessment evidence for Humber Estuary SAC; survey data summary table; and updated Habitats Regulations Assessment (HRA) screening and integrity matrices

12 Hydref 2015 - Deadline 2

Caeedig

Deadline 2 Deadline for receipt by the ExA of: • Comments on relevant representations (RRs) • Summaries of all RRs exceeding 1500 words • Written Representations (WRs) by all interested parties. • Summaries of all WRs exceeding 1500 words • Local Impact Reports (LIRs) from any local authorities • Responses to ExA’s first written questions (ExQ1) • Updated ES chapters • Comments on Statements of Common Ground (Drafts) from Deadline 1 • Notification of wish to speak at a Compulsory Acquisition hearing • Notification of wish to speak at the Issue Specific Hearing on the draft Development Consent Order (DCO) • Notification of wish to speak at any other Issue Specific Hearing • Notification of wish to speak at an Open Floor Hearing • Notification from statutory parties, or a local authority without direct responsibility in the proposed development area, of a wish to be considered an interested party • Nominations of locations to be inspected during unaccompanied site inspections, the features to be observed there, with reasons for each nomination; and • Nominations of locations to be inspected during accompanied site inspections, the features to be observed there, with reasons for each nomination. • Any other information requested by the ExA

27 Hydref 2015 - Deadline 3

Caeedig

Issue by ExA of notification of date, time and place for hearings and accompanied site visit(s)

2 Tachwedd 2015 - Deadline 4

Caeedig

Deadline 3 Deadline for receipt by the ExA of: • Comments on WRs and responses to comments on RRs • Comments on Local Impact Reports • Comments on responses to ExA’s first written questions • Progress report on draft SOCGs and updated summary schedule • Comments on any other documents submitted at Deadline 1 • Any other information requested by the ExA

17 Tachwedd 2015 - Issue Specific Hearing 1

Caeedig

Date reserved for Issue Specific Hearing relating to:

  • Construction - how the project will be planned and executed and its effects;
  • Flood Risk and drainage
  • Hydro-geology
  • Biodiversity, Ecology and Natural Environment impacts
  • Noise impacts
  • Transportation and Traffic impacts
  • Debris, Waste and Contamination impacts
  • Historic Environment
  • Navigation
  • Landscape and Visual Impact
  • Socio Economic Effects
  • Any other matter requested by the ExA

18 Tachwedd 2015 - Issue Specific Hearing 2

Caeedig

Date reserved for Issue Specific Hearing relating to:

  • The draft application DCO - a high level review of the certified documents and plans
  • any other matters relevant to achieve efficient progress of the examination, including any matters not fully discussed in previous days hearing

18 Tachwedd 2015 - Compulsory Acquisition Hearing

Caeedig

Date reserved for Issue Specific Hearing relating to:

  • Compulsory acquisition issues

18 Tachwedd 2015 - Open Floor Hearing

Caeedig

Date reserved for Open Floor Hearing (if required, this will only be held if any requests are recieved by Deadline 2. If there are no requests, the hearing will be cancelled and interested parties will be notified through the banner on the project webpage.)

  • Evening Session

19 Tachwedd 2015 - Site Visit (Accompanied)

Caeedig

Date reserved for Accompanied Site Inspection

27 Tachwedd 2015 - Deadline 5

Caeedig

Deadline 4 Deadline for receipt by the ExA of: • Post-hearing documents including written summaries of oral cases, of any evidence or documents presented, or amendments requested by the ExA • Revised draft DCO from the applicant taking into account all issues raised at hearings and in RRs/WRs (including both clean and track-change versions) • Response to comments from documents received at Deadline 3 • Updated SoCGs and summary schedule • Any further information requested by the ExA for this deadline

8 Rhagfyr 2015 - Deadline 6

Caeedig

Publication by the ExA of second written questions (if required)

22 Rhagfyr 2015 - Deadline 7

Caeedig

Deadline 5 Deadline for receipt by the ExA of: • Responses to second written questions (if applicable)

5 Ionawr 2016 - Issue Specific Hearing 3

Caeedig

Date reserved for Issue Specific Hearing on DCO and other outstanding matters

6 Ionawr 2016 - Issue Specific Hearing 4

Caeedig

Date reserved for Issue Specific Hearings on DCO

13 Ionawr 2016 - Deadline 8

Caeedig

Deadline 6 Deadline for receipt by the ExA of: • Applicant’s revised draft DCO taking account of issues and comments raised, clean and track-change • Updated SOCGs (where progress has been made since Deadline 4) and summary schedule • Comments on responses to the second round of questions (if issued) ExQ2 • Any further information requested by the ExA for this deadline

15 Ionawr 2016 - Deadline 9

Caeedig

Issue by ExA of Rule 17 request

22 Ionawr 2016 - Deadline 10

Caeedig

Deadline 6a Deadline for receipt by the ExA of: • Responses to Rule 17 request dated 15 January 2016

29 Ionawr 2016 - Deadline 11

Caeedig

Deadline 6b Deadline for receipt by the ExA of: • Comments on responses to Rule 17 request dated 15 January 2016

1 Chwefror 2016 - Deadline 12

Caeedig

Publication by the ExA of:

  • Report on Implications for European Sites (RIES)
  • ExA's Draft DCO

17 Chwefror 2016 - Deadline 13

Caeedig

Deadline 7 Deadline for receipt by the ExA of: • Comments on Report on Implications for European Sites (RIES) • Comments on ExA’s draft DCO • Comments on SOCG where updated • Executed final version SOCGs (If these contain remaining points of contention then final position statements for each signatory required for ExA judgement) • Comments on any other information submitted at Deadline 6 • Revised Book of Reference taking into account all issues raised at hearings and in RRs/WRs (including both clean and track-change versions) • Any other information requested by the ExA

24 Chwefror 2016 - Deadline 14

Caeedig

Deadline 8 • Comments on the responses to the RIES • Comments on the responses to the ExA Draft DCO • Comments on the executed final version SOCG from parties who are not signatories, or from the parties if document is not executed • Responses to revised Book of Reference

26 Chwefror 2016 - Deadline 15

Caeedig

Time period reserved for issue by the ExA of; • Any further information requests under Rule 17 (if required)

4 Mawrth 2016 - Deadline 16

Caeedig

Deadline 9 • Responses to any further information requested as required at item 20 (if required) • comments on responses to revised Book of Reference