Thorpe Marsh Gas Pipeline Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 22 April 2015

The examination closed on 7 September 2015

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

22 April 2015 - Preliminary Meeting

Closed

A procedural meeting for discussion about how the application is to be examined.

29 April 2015 - Deadline 1

Closed

Issue by ExA of:

• Examination timetable (including notifications of the dates, times and venues for an Accompanied Site Inspection (ASI) and for Issue Specific (IS), Compulsory Acquisition (CA) and Open Floor (OF) Hearings if required)

• ExA first written questions

20 May 2015 - Deadline 2

Closed

DEADLINE 1

Deadline for receipt of:

• Comments on relevant representations (RRs)

• Summaries of all RRs exceeding 1500 words

• Written representations (WRs) by all interested parties

• Summaries of all WRs exceeding 1500 words

• Local Impact Report from any local authorities

• Draft Statements of Common Ground (SoCGs) requested by ExA (see Annex G) or update on progress on SoCGs

• Responses to ExA’s first written questions

• Notification of wish to speak at a Compulsory Acquisition hearing

• Notification of wish to make oral representations at the issue specific hearing on the draft DCO

• Notification of wish to speak at an open floor hearing

• Notification by statutory parties that they wish to become interested parties

• Any comments on submissions made at, or following, the Preliminary Meeting – see Annex C

• Representations relating to the locations from which the ExA can or should view the works areas or surrounding areas where there is no other opportunity to gain public access (the ExA has already undertaken an unaccompanied site visit to the extent possible using publically accessible land)

10 June 2015 - Deadline 3

Closed

DEADLINE 2

Deadline for receipt by the ExA of:

• Comments on WRs and responses to comments on RRs

• Comments on Local Impact Reports (LIRs)

• Comments on responses to ExA’s first written questions

16 June 2015 - Deadline 4

Closed

Accompanied site inspection (if required)

16 June 2015 - Deadline 5

Closed

Date reserved for open floor hearing (if requested)

• At the close of the accompanied site inspection, and not before 6.00pm (with seating available from 5.30pm)

• Venue: Mansion House, High Street, Doncaster, South Yorkshire, DN1 1BN

17 June 2015 - Deadline 6

Closed

Issue specific hearing on draft DCO

• 10.00am (with seating available from 9.30am)

• Venue: Earl of Doncaster, Bennetthorpe, Doncaster, South Yorkshire, DN2 6AD

17 June 2015 - Deadline 7

Closed

Dates reserved for possible Compulsory Acquisition hearing (including, if requested or required, s.127 and s.138 of the Planning Act 2008 issues)

• At the close of the issue specific hearing on the draft DCO, and not before 2.00pm (with seating available from 1.30pm)

• Venue: Earl of Doncaster, Bennetthorpe, Doncaster, South Yorkshire, DN2 6AD

17 June 2015 - Issue Specific Hearing

Closed

Issues realting to the Development Consent Order

17 June 2015 - Compulsory Acquisition Hearing

Closed

Issues relating to CA powers

26 June 2015 - Deadline 8

Closed

DEADLINE 3

Deadline for receipt of:

• Post hearings documents, including any written summary of an oral case put at any hearing and any documents/amendments requested by the ExA

• Any revised draft DCO from applicant

• Responses to any requests under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 (as amended)

3 July 2015 - Deadline 9

Closed

Issue by ExA of:

• The ExA’s draft DCO

· Second written questions (if required)

· Notification of any issue specific and/or CA hearings (if required)

24 July 2015 - Deadline 10

Closed

DEADLINE 4

Deadline for receipt of:

• Comments on the ExA’s draft DCO

• Comments on Post Hearing Documents

• Responses to ExA’s second written questions (if issued)

• Final agreed SoCGs

• Responses to any requests under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 (as amended)

21 August 2015 - Deadline 11

Closed

DEADLINE 5

Deadline for receipt of:

• Comments on responses to ExA’s second written questions (if issued)

• Responses to any requests under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 (as amended)

28 August 2015 - Deadline 12

Closed

DEADLINE 6

Deadline for receipt of:

• Comments on responses to request under Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010 issued on 6 August 2015.

4 September 2015 - Deadline 13

Closed

Date on which the Examination is anticipated to close