Agorodd yr archwiliad ar 9 October 2019

Caeodd yr archwiliad ar 9 April 2020

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

9 Hydref 2019 - Preliminary Meeting

Caeedig

Preliminary Meeting

16 Hydref 2019 - Issue by the ExA

Caeedig

Issue by the ExA of:

• Examination Timetable;

Publication of:

• The ExA’s Written Questions

24 Hydref 2019 - Deadline 1

Caeedig

Deadline 1

Deadline for receipt by the ExA of:

• Notification of wish to speak at a Compulsory Acquisition Hearing (CAH); • Notification of wish to speak at an Open Floor Hearing (OFH); • Notification of wish to attend the Accompanied Site Inspection (ASI); • Submission of suggested locations/sites for the ExA to include as part of the ASI including the issues to be observed there, information on whether the site can be accessed on public land and reasoning for each nominated site; • Applicant’s draft itinerary for the ASI; • Responses to Relevant Representations; • Response from the Ministry of Defence to Written Question SS.1.4; • Comments on the Applicant’s response to the Planning Inspectorate’s s51 advice; • Local Impact Reports (LIR) from Local Authorities.

28 Hydref 2019 - Issue by the ExA of

Caeedig

Issue by the ExA of:

• Notification of Hearings to be held during the weeks commencing 25 November and 2 December 2019

14 Tachwedd 2019 - Deadline 2

Caeedig

Deadline 2

Deadline for receipt by the ExA of:

• Responses to the ExA’s Written Questions; • Written Representations (WRs); • Summaries of all WRs exceeding 1500 words; • Comments on LIR(s); • Initial Statements of Common Ground (SoCG) requested by the ExA (see Annex B); • A Statement of Commonality of Statements of Common Ground; • An updated Guide to the Application; • Compulsory Acquisition Schedule; • An updated version of the draft Development Consent Order (dDCO) in clean, tracked and word versions; • Any further information requested by the ExA under Rule 17 of the Examination Rules .

25 Tachwedd 2019 - Open Floor Hearing

Caeedig

Open Floor Hearing Evening

26 Tachwedd 2019 - Accompanied Site Inspection

Caeedig

Accompanied Site Inspection

27 Tachwedd 2019 - Issue Specific Hearing (ISH1)

Caeedig

Issue Specific Hearing AM on the dDCO

27 Tachwedd 2019 - Compulsary Aquisition Hearing (CAH1)

Caeedig

Compulsory Acquisition Hearing PM

3 Rhagfyr 2019 - Issue Specific Hearing (ISH2)

Caeedig

Issue Specific Hearing on Environmental Matters

4 Rhagfyr 2019 - Issue Specific Hearing (ISH3)

Caeedig

Issue Specific Hearing on Environmental Matters

18 Rhagfyr 2019 - Deadline 3

Caeedig

Deadline 3

Deadline for receipt by the ExA of:

• Written summaries of oral submissions put at any Hearings held during the weeks commencing 25 November and 2 December 2019; • Comments on Written Representations; • An updated Guide to the Application; • An updated version of the dDCO in clean, tracked and word versions; • An updated Compulsory Acquisition Schedule; • Comments on responses to the ExA’s Written Questions; • Comments on responses submitted for Deadline 2; • Progressed Statements of Common Ground and an updated Statement of Commonality of Statements of Common Ground; • Any further information requested by the ExA under Rule 17 of the Examination Rules.

13 Ionawr 2020 - Publication of FWQ and Issue by the ExA of;

Caeedig

Publication of:

• The ExA’s Further Written Questions (FWQ) (if required). Issue by the ExA of:

• Notification of Hearings to be held during the week commencing 24 February 2020 (if required).

30 Ionawr 2020 - Deadline 4

Caeedig

Deadline 4

Deadline for receipt by the ExA of:

• Responses to the ExA’s FWQ (if published); • An updated Guide to the Application; • An updated version of the dDCO in clean, tracked and word versions; • An updated Compulsory Acquisition Schedule; • Comments on responses submitted for Deadline 3; • Progressed Statements of Common Ground and an updated Statement of Commonality of Statements of Common Ground; • Any further information requested by the ExA under Rule 17 of the Examination Rules.

13 Chwefror 2020 - Deadline 5

Caeedig

Deadline 5

Deadline for receipt by the ExA of:

• Comments on responses to the ExA’s FWQ (if published); • An updated Guide to the Application; • An updated version of the dDCO in clean, tracked and word versions; • An updated Compulsory Acquisition Schedule; • Comments on responses submitted for Deadline 4; • Progressed Statements of Common Ground and an updated Statement of Commonality of Statements of Common Ground; • Draft planning obligations (if applicable) • Any further information requested by the ExA under Rule 17 of the Examination Rules.

24 Chwefror 2020 - Compulsory Acquistion Hearing (CAH2)

Caeedig

Compulsory Acquisition Hearing PM

25 Chwefror 2020 - Issue Specific Hearing (ISH4)

Caeedig

Issue Specific Hearing on the draft Development Consent Order

26 Chwefror 2020 - Issue Specific Hearing (ISH5)

Caeedig

Issue Specific Hearing on Environmental Matters (day 1 of 2)

27 Chwefror 2020 - Issue Specific Hearing (ISH5)

Caeedig

Issue Specific Hearing on Environmental Matters (day 2 of 2)

5 Mawrth 2020 - Deadline 6

Caeedig

Deadline 6

Deadline for receipt by the ExA of:

• Written summaries of oral submissions put at any Hearings held during the week commencing 17 February 2020; • An updated Guide to the Application; • An updated version of the dDCO in clean, tracked and word versions; • An updated Compulsory Acquisition Schedule; • Comments on responses submitted for Deadline 5; • Finalised Statements of Common Ground; • Any further information requested by the ExA under Rule 17 of the Examination Rules.

12 Mawrth 2020 - Issue by the ExA of;

Caeedig

Issue by the ExA of:

• The Report on the Implications for European Sites (RIES) (if required); • The ExA’s dDCO (if required); • Any requests for information under Rule 17 of the Examination Rules (if required).

19 Mawrth 2020 - Accompanied Site Inspection 2

Caeedig

ASI2

19 Mawrth 2020 - Deadline 6a

Caeedig

Deadline 6a

Deadline for receipt by the ExA of:

• Natural England’s response to the ExA’s request for information dated 9 March 2020.

2 Ebrill 2020 - Deadline 7

Caeedig

Deadline 7

Deadline for receipt by the ExA of:

• Comments on the RIES (if required); • Comments on the ExA’s dDCO (if required) and/or an updated version of the dDCO in clean, tracked and word versions as required; • Any further information requested by the ExA under Rule 17 of the Examination Rules (if required); • An updated Guide to the Application; • An updated Compulsory Acquisition Schedule; • Signed and dated planning obligations (if required); • Comments on responses submitted for Deadline 6.

9 Ebrill 2020 - End Of Examination

Caeedig

The ExA is under a duty to complete the Examination of the application by the end of the period of 6 months.