There are no deadlines and events
Examination timetable
The examination timetable shows the dates of events and deadlines for submissions.
If you have registered to have your say, you can do this in the examination stage.
The examination stage
The examination opened on 24 April 2014
The examination closed on 4 September 2014
24 April 2014 - Preliminary Meeting
ClosedPreliminary Meeting to discuss the examination procedure.
8 May 2014 - Deadline 1
ClosedDeadline 1 Deadline for receipt of: • Statements of Common Ground (SoCG) • Local Impact Reports (LIR) • Information from the applicant relating to s127, s135 and s138 PA 2008
27 May 2014 - Deadline 2
ClosedDeadline 2 Deadline for receipt of: • Comments on relevant representations (RRs) • Summaries of all RRs exceeding 1500 words • Written representations (WRs) by all interested parties • Summaries of all WRs exceeding 1500 words • Responses to ExA’s first written questions • Notification by affected persons of wish to request a compulsory acquisition hearing • Notification by interested parties of wish to make oral representations at an issue specific hearing on the draft Development Consent Order (DCO) • Notification by interested parties of wish to request an open floor hearing • Representations from interested parties recommending itinerary items for the accompanied site visit
3 June 2014 - Deadline 3
ClosedIssue of final notification by the ExA of date, time and place for: • Any open floor hearings • The issue specific hearing relating to the draft DCO • Any compulsory acquisition hearing • Any other issue specific hearings • Accompanied site visit
24 June 2014 - Deadline 4
ClosedDeadline 3 Deadline for receipt by the ExA of: • Comments on WRs and responses to comments on RRs • Comments on LIRs • Comments on responses to ExA’s first written questions • Any revised draft DCO from applicant • Any further information requested by the ExA
15 July 2014 - Deadline 5
ClosedSite inspection (accompanied)
15 July 2014 - Open Floor Hearing
ClosedOpen Floor Hearing
16 July 2014 - Deadline 6
ClosedIssue specific hearing on draft DCO
16 July 2014 - Issue Specific Hearing
ClosedDraft Development Consent Order
17 July 2014 - Deadline 7
ClosedIssued specific hearing on compulsory acquisition
17 July 2014 - Compulsory Acquisition Hearing
ClosedCompulsory Aquisition Hearing
28 July 2014 - Deadline 8
ClosedIssue by the ExA of the Report on Implications for European Sites (RIES)
31 July 2014 - Deadline 9
ClosedDeadline 4 Deadline for receipt of: • Applicant’s final preferred draft DCO • Updated SoCGs • Any information requested at hearings • Written summaries of oral cases put at hearings • Any further information requested by the ExA
12 August 2014 - Deadline 10
ClosedDeadline 5 Deadline for receipt of: • Comments on applicants final preferred draft DCO • Comments on RIES • Any further information requested by the ExA
22 August 2014 - Deadline 11
ClosedDeadline 6 Deadline for the receipt of: • Responses to ExA’s Rule 17 request for further information
24 October 2014 - Deadline 12
ClosedThe ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.