Examination timetable
The examination timetable shows the dates of events and deadlines for submissions.
If you have registered to have your say, you can do this in the examination stage.
The examination stage
The examination opened on 15 January 2014
The examination closed on 15 July 2014
15 January 2014 - Preliminary Meeting
ClosedPreliminary Meeting
22 January 2014 - Deadline 1
ClosedIssue by ExA of: -Examination timetable -ExA first written questions
26 February 2014 - Deadline 2
ClosedDeadline for receipt by the ExA of:
- Comments on relevant representations (RRs)
- Summaries of all RRs exceeding 1500 words
- Written Representations(WRs) by all interested parties
- Summaries of all WRs exceeding 1500 words
- Local impact Report from any local authorities
- Statement of common ground requested by ExA
- Responses to ExA first written questions
- Notification of wish to speak at a Compulsory Acquisition hearing
- Notification of wish to make oral reperesentations at the issue specific hearing on the draft Development consent Order (DCO)
- Requests for any issue specific hearings, Cumpulsory Aquisition or open floor hearings
19 March 2014 - Deadline 3
ClosedDeadline for receipt by the ExA of:
- Comments on WRs and responses to comments on RRs
- Comments on Local Impact Reports
- Comments on responses to ExA's first written questions
- Revised draft DCO
27 March 2014 - Site Visit (Accompanied)
ClosedAn accompanied site visit, as described in the ExA's letter of 11 March 2014
3 April 2014 - Deadline 4
ClosedResponses to the questions in the ExA's letter of 20 March 2014
8 April 2014 - Issue Specific Hearing 1
ClosedDraft Development Consent Order, Requirements and associated matters
8 April 2014 - Issue Specific Hearing 2
ClosedThe provision that would be made for non-motorised users
9 April 2014 - Deadline 5
ClosedPeriod reserved for possible issue specific hearings, Compulsory Aquisition hearings and open floor hearings
9 April 2014 - Open Floor Hearing
ClosedRepresentations by interested parties
9 April 2014 - Compulsory Acquisition Hearing
ClosedThe proposed compulsory acquisition of land or of interests in or rights over land for the scheme
11 April 2014 - Deadline 6
ClosedComments on responses to the questions in the ExA's letter of 20 March 2014
16 April 2014 - Deadline 7
ClosedIssue of ExA of: -Second written questions
9 May 2014 - Deadline 8
ClosedDeadline for receipt of:
- Responses to ExA's second written questions
30 May 2014 - Deadline 9
ClosedDeadline for receipt of:
- Comments on responses to ExA's second written questions
5 June 2014 - Deadline 10
ClosedDeadline for receipt of:
- Comments on the applicant's submissions of 13 May 2014
10 June 2014 - Deadline 11
ClosedDeadline for receipt of:
- Applicant's final draft DCO
26 June 2014 - Deadline 12
ClosedDeadline for receipt of: -Responses to requests for information made on 5 and 6 June 2014
8 July 2014 - Issue Specific Hearing 3
ClosedDraft Development Consent Order, Requirements and associated matters.
12 July 2014 - Deadline 13
ClosedDeadline for receipt of: -Comments on the responses to to requests for information made on 5 and 6 June 2014 -Comments on any responses to requests for information that may be sent to specific parties -Any outstanding comments on submissions made to the examination before that date.