A30 Temple to Higher Carblake Improvement Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 6 February 2014

Caeodd yr archwiliad ar 6 August 2014

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

6 Chwefror 2014 - Preliminary Meeting

Caeedig

Preliminary Meeting

24 Chwefror 2014 - Deadline 1

Caeedig

Issue by ExA of:

• Examination timetable • ExA first written questions

3 Mawrth 2014 - Deadline 2

Caeedig

Deadline I Deadline for receipt by ExA of:

• Comments by interested parties on other environmental information provided by the applicant on 8 January 2014 and published to the A30 Temple to Higher Carblake Improvement project webpage on 14 January 2014 • Request for receipt of written notification by statutory parties of a wish to be considered as an interested party • Request for receipt of notification (using the prescribed form) by persons with certain categories of interest in the land of wish to become an interested party

4 Mawrth 2014 - Deadline 3

Caeedig

Issue by ExA of:

• Notification of issue specific hearing on 7 April 2014 • Notification of accompanied site inspection on 8 APril 2013 • Corrected examination timetable

19 Mawrth 2014 - Deadline 4

Caeedig

Deadline II Deadline for receipt by ExA of:

• Any comments by interested parties on the comments received at Deadline I in relation to the other environmental information • Comments by interested parties on relevant representations (RRs) • Summaries of RRs by interested parties whose RRs exceeded 1500 words • Written representations (WRs) by interested parties • Summaries of WRs by interested parties whose WRs exceeded 1500 words • Local Impact Report(s) from local authorities defined under s56A of the Planning Act 2008 (as amended) • Statements of Common Ground requested by ExA • Responses to ExA’s first written questions • Notification by interested parties of wish to speak at a compulsory acquisition hearing • Notification by interested parties of a wish to make oral representations at the issue specific hearing on the draft Development Consent Order (DCO) on 7 April 2014 • Notification by interested parties of a wish to speak at an open-floor hearing • Notification by interested parties of wish to attend accompanied site inspection on 8 April 2014 • Recommendations from interested parties on suitable itinerary items for the accompanied site inspection on 8 April 2014

7 Ebrill 2014 - Issue Specific Hearing 1

Caeedig

Issue specific hearing on the draft Development Consent Order

8 Ebrill 2014 - Site Visit (Accompanied) 1

Caeedig

Site inspection in the company of interested parties

15 Ebrill 2014 - Deadline 5

Caeedig

Deadline III Deadline for receipt by ExA of:

• Post-hearing documents including any written summary of an oral case put at the issue specific hearings on the draft DCO and any documents/amendments requested orally by the ExA • Comments by interested parties on WRs and responses to comments on RRs • Comments by interested parties on Local Impact Reports • Comments by interested parties on responses to ExA’s first written questions • Applicant’s revised draft DCO • Applicant’s updated Book of Reference • Applicant’s mitigation schedule • Applicant’s schedule of private agreements

30 Ebrill 2014 - Deadline 6

Caeedig

Issue by ExA of:

• Second written questions

21 Mai 2014 - Deadline 7

Caeedig

Deadline IV Deadline for receipt by ExA of:

• Responses by interested parties to ExA’s second written questions

23 Mai 2014 - Deadline 8

Caeedig

Issue by ExA of:

• Notification of issue specific hearings on 23 and 25 June 2014, and 21 and 22 July 2014 • Notification of compulsory acquisition hearings on 26 June 2014 • Notification of open floor hearing on 27 June 2014 • Notification of second accompanied site inspection on 24 June 2014 • Request for further information

6 Mehefin 2014 - Deadline 9

Caeedig

Deadline for receipt by ExA of:

• Applicant's progressed draft Landscape Ecological Management Plan • Applicant's progressed draft Construction Environmental Management Plan • Applicant's draft DCO Requirement securing mitigation measures for dormice • Suggestions from interested parties on features/sites to be viewed at second accompanied site inspection to be held on 24 June 2014

11 Mehefin 2014 - Deadline 10

Caeedig

Deadline V Deadline for receipt by ExA of:

• Comments by interested parties on responses to ExA's second written questions • Notification by interested parties of wish to attend/speak at June hearings and/or to attend second accompanied site inspection

23 Mehefin 2014 - Issue Specific Hearing 2

Caeedig

Issue specific hearing including issues relating to mitigation measures (am)

23 Mehefin 2014 - Issue Specific Hearing 3

Caeedig

Issue specific hearing including issues relating to the draft Development Consent Order (pm)

24 Mehefin 2014 - Site Visit (Accompanied) 2

Caeedig

Second site inspection in the company of interested parties.

25 Mehefin 2014 - Issue Specific Hearing 4

Caeedig

Issue specific hearing including issues relating to landscape and visual impact (am)

25 Mehefin 2014 - Issue Specific Hearing 5

Caeedig

Issue specific hearing including issues relating to highway design (pm)

26 Mehefin 2014 - Compulsory Acquisition Hearing 1

Caeedig

Compulsory acquisition hearing including issues relating to compulsory acquisition of common land (am)

26 Mehefin 2014 - Compulsory Acquisition Hearing 2

Caeedig

Compulsory acquisition hearing including issues relating to general compulsory acquisition matters (pm)

27 Mehefin 2014 - Open Floor Hearing

Caeedig

Open floor hearing

3 Gorffennaf 2014 - Deadline 11

Caeedig

Deadline VI Deadline for receipt by ExA of:

• Post-hearing documents including any written summary of an oral case put at the issue specific; open-floor; and compulsory acquisition hearings held between 23 and 27 June 2014 and any documents/amendments requested orally by the ExA

4 Gorffennaf 2014 - Deadline 12

Caeedig

Deadline for receipt by ExA of:

• Any comments by interested parties on Cornwall Council's Technical Note assessing alternative access arrangements at Higher Carblake; and • Any comments by interested parties on the draft National Networks National Policy Statement

14 Gorffennaf 2014 - Deadline 13

Caeedig

Deadline for receipt by ExA of:

• Notification by interested parties of wish to attend/speak at hearing on 22 July 2014 dealing with matters relating to highway design and compulsory acquisition at Higher Carblake

22 Gorffennaf 2014 - Compulsory Acquisition Hearing 3

Caeedig

Hearing dealing with compulsory acquisition matters relating to Higher Carblake

29 Gorffennaf 2014 - Deadline 14

Caeedig

Deadline VII Deadline for receipt by ExA of:

• Post-hearing documents including any written summary of an oral case put at the Higher Carblake hearing on 22 July 2014, any documents/amendments requested orally by the ExA and the applicant’s final draft DCO

1 Awst 2014 - Deadline 15

Caeedig

Deadline for receipt by ExA of:

• Responses from interested parties in relation to proposed change to the application comprising the substitution of replacement common land