The examination opened on 2 June 2014

The examination closed on 2 December 2014

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

2 June 2014 - Preliminary Meeting

Closed

Preliminary Meeting

5 June 2014 - Deadline 1

Closed

Deadline 1 Deadline for receipt from applicant of: • Report on status of negotiations with affected persons in respect of compulsory acquisition for each plot

25 June 2014 - Deadline 2

Closed

Issue by Examining Authority (ExA) of: • ExA’s first written questions

30 June 2014 - Deadline 3

Closed

Deadline 2 Deadline for receipt of: • Comments on revisions to application documents • Written representations (WRs) by all interested parties • Local impact report (LIR) from any local authorities

14 July 2014 - Deadline 4

Closed

Deadline 3 Deadline for receipt of: • Comments on relevant representations (RRs) • Notification of wish to speak at the open floor hearings on Tuesday 22 and Wednesday 23 July 2014 • Notification of wish to participate in the accompanied site visit on Wednesday 23 July 2014 • Notification of wish to make oral representations at the issue specific hearing on Thursday 24 July 2014

21 July 2014 - Deadline 5

Closed

Deadline 4 Deadline for receipt of: • Responses to ExA’s first written questions • Statements of common ground (SoCG) • Comments on WRs • Comments on LIRs • Comments on report on status of negotiations with affected persons in respect of compulsory acquisition • Revised draft Development Consent Order (DCO) from applicant • Notifications from statutory parties of a wish to be considered as interested parties • Requests to cross examine at issue specific hearings

22 July 2014 - Open Floor Hearing 1

Closed

Daytime open floor in Norwich city centre

22 July 2014 - Open Floor Hearing 2

Closed

Evening open floor hearing in Thorpe Saint Andrew

23 July 2014 - Open Floor Hearing 3

Closed

Evening open floor hearing in Drayton

23 July 2014 - Site Visit (Accompanied) 1

Closed

Accompanied site visit to include the approximate proposed route, nearby villages and the Wensum Valley

24 July 2014 - Issue Specific Hearing 1

Closed

Draft Development Consent Order

4 August 2014 - Deadline 6

Closed

Deadline 5 Deadline for receipt of: • Comments on responses to ExA’s first written questions • Responses to comments on RRs • Post-hearing documents including any written summary of an oral case put at any hearing • Any further information requested by the ExA • Updates to SoCGs • Responses to requests to cross examine at issue specific hearings

15 August 2014 - Deadline 7

Closed

Issue by ExA of: • Second written questions • Procedural decision regarding cross examination at issue specific hearings

8 September 2014 - Deadline 8

Closed

Deadline 6 Deadline for receipt of: • Responses to ExA’s second written questions • Applicant’s revised draft DCO • Notification of wish to make oral representations at the issue specific hearings on Tuesday 16 - Friday 19 September 2014 • Notification of wish to make oral representations at the compulsory acquisition hearings on Tuesday 30 September - Friday 3 October 2014

16 September 2014 - Issue Specific Hearing 2

Closed

Need; traffic forecasts; value for money

17 September 2014 - Issue Specific Hearing 3

Closed

Alternative options and alignments; impacts

18 September 2014 - Issue Specific Hearing 4

Closed

Western termination; minor changes

19 September 2014 - Issue Specific Hearing 5

Closed

Draft Development Consent Order

30 September 2014 - Compulsory Acquisition Hearing 1

Closed

General considerations and regarding specific plots to be agreed with Affected Persons

1 October 2014 - Compulsory Acquisition Hearing 2

Closed

Plots to be agreed with Affected Persons

2 October 2014 - Compulsory Acquisition Hearing 3

Closed

Plots to be agreed with Affected Persons

3 October 2014 - Compulsory Acquisition Hearing 4

Closed

Plots to be agreed with Affected Persons

9 October 2014 - Deadline 9

Closed

Deadline 8 Deadline for receipt of: • Post-hearing documents including any written summary of an oral case put at any hearing • Any further information requested by the ExA

10 October 2014 - Deadline 10

Closed

Publication by ExA of: • Report on the Implications for European Sites (RIES)

3 November 2014 - Deadline 11

Closed

Deadline 9 Deadline for receipt of: • Comments on proposed changes to the scheme • Comments on proposed provision for compulsory acquisition of additional land • Comments on the applicant's draft DCO • Comments on post-hearing documents • Comments on the RIES • Any further information requested by the ExA

5 November 2014 - Deadline 12

Closed

Publication by ExA of: • Draft DCO

20 November 2014 - Deadline 13

Closed

Deadline 10 Deadline for receipt of: • Comments on the ExA's draft DCO • Comments on relevant representations • Information requested from the applicant • Notification to make oral representations at the hearings on Friday 28 November 2014 • Any further information requested by the ExA

27 November 2014 - Deadline 14

Closed

Deadline 11 Deadline for receipt of: • Written representations regarding the proposed provision for the compulsory acquisition of additional land • Comment on information provided by the applicant

28 November 2014 - Issue Specific Hearing 6

Closed

Unresolved matters and draft DCO

28 November 2014 - Open Floor Hearing 4

Closed

Proposed provision for the compulsory acquisition of additional land only

28 November 2014 - Compulsory Acquisition Hearing 5

Closed

Proposed provision for the compulsory acquisition of additional land and outstanding matters

28 November 2014 - Site Visit (Accompanied) 2

Closed

To follow discussions of the compulsory acquisition hearing if required

2 December 2014 - Deadline 15

Closed

Deadline 12 Deadline for receipt of: • Post-hearing documents including any written summary of an oral case put at a hearing • Comments on written representations • Any further information requested by the ExA