28 October 2020

The Secretary of State has made a Correction Order (PDF, 127 KB) affecting the A63 (Castle Street Improvement, Hull) Development

Consent Order 2020. A Correction Notice (PDF, 122 KB) was issued on 28 October 2020. The corrections to the Order are applied following a request from the Applicant dated 16 June 2020 (PDF, 140 KB).

28 May 2020

Decision made by the Secretary of State

29 April 2020

A Statement has been laid in Parliament setting a new deadline of 31 May 2020 to enable further work to be carried out before the application is determined by the Secretary of State.

 IMPORTANT: As a result of ongoing Government guidance relating to COVID-19 the Planning Inspectorate is seeking to ensure that all Parties are notified of key developments on projects, in a timely manner. In order to help achieve this, and to minimise any delays which could arise if the postal service is affected, it would be extremely helpful if registered Parties that have not already done so could supply us with a contact e-mail address as soon as possible (details in the contact information heading of the project page).

Please be assured that this information will be managed in line with our Privacy Notice.

23 March 2020

The A63 Castle Street Improvement - Hull Development Consent Order application remains with the Secretary of State for consideration.

11 March 2020

Responses to the Secretary of State’s consultation of 27 February 2020 have been published.

27 February 2020

The Secretary of State for Transport has asked for further clarification and information in relation to a range of matters by 10 March 2020

24 December 2019

Recommendations given by the Planning Inspectorate

26 September 2019

The examination closed at 23:59 on Thursday 26 September 2019.

11 July 2019

The Examining Authority has published the Report on the Implications for European Sites (RIES) and issued the Agenda’s for ISH5 and CAH2, Schedule of Proposed Changes to the draft Development Consent Order and Further Written Questions and Requests for Information. The deadline for responses to the Further Written Questions is D5: 5 August 2019

19 June 2019

The Examining Authority has issued notice of hearings.

1 April 2019

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.

Procedural decision following Preliminary Meeting.

26 March 2019

Preliminary Meeting takes place

26 March 2019

Examination begins

22 February 2019

The notification of Preliminary Meeting (Rule 6 letter) has been sent.

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

27 December 2018

Relevant representations published on the website

20 December 2018

Registration of interested parties closes

7 November 2018

Registration of interested parties begins

18 October 2018

The application has been accepted for examination

20 September 2018

This application was received by the Planning Inspectorate on 20 September 2018.

The applicant has agreed that all application documents can be published as
soon as practicable to help everyone become familiar with the detail of what
is being proposed in this application. The Planning Inspectorate will therefore
make the application documents available as soon as practicable.
This provision is solely for the purpose of allowing more time to all those who
wish to become familiar with the detail of what is being proposed ahead of
the relevant representation period without lengthening the overall time
required for the application process. There will be no opportunity at this
stage to make comments on the application. However, if the application is
accepted anyone interested in the application will be able to register and
express their views during the relevant representation stage and the
subsequent examination.

20 September 2018

Application received by the Planning Inspectorate