A14 Cambridge to Huntingdon Improvement Scheme Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 13 May 2015

The examination closed on 13 November 2015

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

12 May 2015 - Site Visit (Unaccompanied)

Closed

Unaccompanied

13 May 2015 - Preliminary Meeting

Closed

Preliminary Meeting

1 June 2015 - Deadline 1

Closed

Deadline 1 - 12 noon Deadline for receipt of: · Comments on relevant representations · Suggested locations and justifications for the accompanied site visit · Report on status of negotiations with affected persons in respect of compulsory acquisition for each plot

15 June 2015 - Deadline 2

Closed

Deadline 2 - 12 noon Deadline for receipt of: · Written representations (WRs) by all interested parties · Joint Local Impact Report (LIR) from local authorities · Responses to ExA’s first written questions · A Traffic Modelling Update Report to include: an environmental impact general topic review; detailed air quality and noise modelling work and data analysis; the effect of the November 2014 and March 2015 DfT economic data and road traffic forecasts; and revised operational tables for the Transport Assessment · A revised business case in accordance with the Traffic Modelling Update Report Comments on: i) Revised application documents following s51 advice from Planning Inspectorate. Published on the Planning Portal on 15 April 2015. ii) Errata sheet and revised application documents. Published on the Planning Portal on 12 May 2015. iii) Update to the Case for the Scheme. Published on the Planning Portal on 14 May 2015. · Notification of wish to make oral representations at the issue specific hearing on the draft Development Consent Order (DCO) · Notification of wish to speak at the open floor hearings, providing details of the date and time of the open floor hearing which you wish to attend · Notification of wish to attend an accompanied site visit · Notification by statutory parties of wish to be considered an interested party · Any further information requested by the ExA

26 June 2015 - Deadline 3

Closed

Deadline 3 - 12 noon Deadline for receipt of: · Statements of Common Ground requested by ExA · Revised joint LIR which must clearly show (in track changes) any alterations to the previous joint LIR submission. Local authorities to make clear that this supersedes the former version. · Revised WRs from local authorities which must clearly show (in track changes) any alterations to the previous WR submission. Local authorities to make clear that this supersedes the former version.

7 July 2015 - Deadline 4

Closed

Deadline 4 - 12 noon Deadline for receipt by the ExA of: · Comments on WRs · Comments on LIRs · Comments on responses to ExA’s first written questions · Comments on the Traffic Modelling Update Report · Report on status of negotiations with affected persons in respect of compulsory acquisition foreach plot · Applicant’s revised draft DCO · Applicant’s completed matrices on Screening and Implications for the integrity of European sites

13 July 2015 - Open Floor Hearing 1

Closed

Open floor hearing (6.30pm Hilton)

14 July 2015 - Open Floor Hearing 2

Closed

Open floor hearings 9.30am Bar Hill

14 July 2015 - Open Floor Hearing 3

Closed

Open floor hearing 2pm Bar Hill

14 July 2015 - Open Floor Hearing 4

Closed

Open floor hearing (7pm Brampton)

15 July 2015 - Issue Specific Hearing 1

Closed

Issue specific hearing on the draft DCO

16 July 2015 - Site Visit (Accompanied) 1

Closed

Accompanied site visit

17 July 2015 - Site Visit (Accompanied) 2

Closed

Accompanied site visit

22 July 2015 - Deadline 5

Closed

Deadline 5 - 12 noon Deadline for receipt of: · Summary of oral submissions put at hearings · Post-hearing documents · Any further information requested by the ExA

29 July 2015 - Deadline 6

Closed

Publication of Second Written Questions by the ExA

3 August 2015 - Deadline 7

Closed

Deadline 6 - 12 noon Deadline for receipt of: · Applicant’s report on local traffic impacts outside those in the Transport Assessment and Traffic Modelling Update Report

19 August 2015 - Deadline 8

Closed

Deadline 7 - 12 noon Deadline for receipt of: · Responses to ExA’s second written questions · Applicant's proposed changes to the scheme · Comments on the Applicant’s report on local traffic impacts outside those in the Transport Traffic Modelling Update Report · Applicant’s revised draft DCO · Notification of wish to speak at a compulsory acquisition hearing

1 September 2015 - Compulsory Acquisition Hearing 1

Closed

Compulsory acquisition hearing

2 September 2015 - Deadline 9

Closed

Deadline 8 - 12 noon Deadline for receipt by the ExA of: · Comments on responses to ExA’s second written questions · Any supplementary documents to update the joint LIR from local authorities. Any local authority that submits a supplementary document to the joint LIR to make clear its relationship to that joint LIR. · Notification of wish to make oral representations at the issue specific hearings · Any further information requested by the ExA

2 September 2015 - Compulsory Acquisition Hearing 2

Closed

Compulsory acquisition hearings

3 September 2015 - Compulsory Acquisition Hearing 3

Closed

Compulsory acquisition hearings

4 September 2015 - Issue Specific Hearing 2

Closed

Issue specific hearing on the draft DCO

10 September 2015 - Deadline 10

Closed

Deadline 9 - 11.59pm Deadline for receipt by the ExA of: · Comments on changes to the scheme · Comments on the proposed provision for compulsory acquisition of additional land

15 September 2015 - Issue Specific Hearing 3

Closed

Noise and air quality

16 September 2015 - Issue Specific Hearing 4

Closed

Traffic and transportation

17 September 2015 - Issue Specific Hearing 5

Closed

Detailed design

18 September 2015 - Issue Specific Hearing 6

Closed

Miscellaneous matters

28 September 2015 - Deadline 11

Closed

Deadline 10 - 12 noon Deadline for receipt of: · Summary of oral submissions put at hearings · Post-hearing documents · Comments on any supplementary joint LIR · Applicant’s revised draft DCO and Explanatory Memorandum · Any further information requested by the ExA

9 October 2015 - Deadline 12

Closed

Publication of the ExA’s Report on the Implications for European Sites

13 October 2015 - Deadline 13

Closed

Publication of the ExA’s draft DCO

14 October 2015 - Deadline 14

Closed

Deadline 11 - 12 noon Deadline for receipt of: · Notification of wish to make oral representations at the October hearings · Any further information requested by the ExA

21 October 2015 - Issue Specific Hearing 7

Closed

Reserved hearing date

21 October 2015 - Compulsory Acquisition Hearing 4

Closed

Compulsory acquisition hearing into the proposed provision for the compulsory acquisition of additional land

21 October 2015 - Open Floor Hearing 5

Closed

Matters related to the proposed provision for the compulsory acquisition of additional land and any other matters relating to the scheme changes

21 October 2015 - Compulsory Acquisition Hearing 5

Closed

Compulsory acquisition hearing on general matters

21 October 2015 - Site Visit (Accompanied) 3

Closed

Reserved for accompanied site visit only if required from compulsory acquisition hearing

22 October 2015 - Deadline 15

Closed

Deadline 12 - 12 noon Deadline for receipt of: · Written representations regarding the proposed provision for the compulsory acquisition of additional land · Comments on changes to the scheme

22 October 2015 - Issue Specific Hearing 8

Closed

Issue specific hearing on the draft DCO

30 October 2015 - Deadline 16

Closed

Deadline 13 - 12 noon Deadline for receipt of: · Comments on ExA’s draft DCO · Comments on Report on the Implications for European Sites · Post hearing documents · Any further information requested by the ExA

6 November 2015 - Deadline 17

Closed

Deadline 14 - 12 noon Deadline for receipt of: · Comments on written representations regarding the proposed provision for the compulsory acquisition of additional land · Responses to comments on ExA’s draft DCO · Any further information requested by the ExA

11 November 2015 - Deadline 18

Closed

Deadline 15 - 12 noon Deadline for receipt of: · All final written responses