A19 / A184 Testos Junction Improvement Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 14 November 2017

The examination closed on 26 March 2018

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

14 November 2017 - Preliminary Meeting

Closed

PM

15 November 2017 - Issue Specific Hearing 1 on draft DCO

Closed

Issue Specific Hearing 1 on draft DCO

22 November 2017 - Rule 8

Closed

Issue by ExA of:

• Examination timetable • ExA’s Written Questions (ExQ1)

28 November 2017 - Deadline 1

Closed

DEADLINE 1

Deadline for receipt of:

• Comments on any updates to Application Documents submitted by the Applicant before or at the PM • Comments on Relevant Representations (RRs) • Summaries of all RRs exceeding 1500 words • Written Representations (WRs) by all Interested Parties (IPs) • Summaries of all WRs exceeding 1500 words • Statements of Common Ground (SoCG) requested by ExA – see Annex G • Response to any further information requested by the ExA for this deadline • Post-hearing submissions including written submissions of oral cases • Notification by Statutory Parties of their wish to be considered as an IP by the ExA • Notification of wish to speak at any subsequent Issue Specific Hearings (ISH) • Notification of wish to speak at a Compulsory Acquisition Hearing (CAH) • Notification of wish to speak at an Open Floor Hearing (OFH) • Provision of suggested locations and justifications for site inspections for consideration by the ExA • Notification of wish to attend an Accompanied Site Inspection (ASI) • Notification of wish to have future correspondence received electronically

18 December 2017 - Deadline 2

Closed

DEADLINE 2

Deadline for receipt of:

• Comments on WRs • Comments on any SoCGs • Local Impact Reports (LIR) from any Local Authorities • Responses to ExA’s Written Questions (ExQ1) • Comments on any additional information/submissions received by D1 • Responses to any further information requested by the ExA for this deadline

16 January 2018 - Accompanied Site Inspection

Closed

Accompanied Site Inspection

16 January 2018 - Open Floor Hearing

Closed

Open Floor Hearing (evening)

17 January 2018 - Issue Specific Hearing 2 on Environmental Issues

Closed

Issue Specific Hearing 2 on the Interrelationship of major proposals in the Area, Environmental & Landscape/Visual Issues and any Legal matters.

18 January 2018 - Compulsory Acquisition Hearing

Closed

Compulsory Acquisition Hearing

19 January 2018 - Issue Specific Hearing 3 on draft DCO

Closed

Issue Specific Hearing 3 on draft DCO

25 January 2018 - Deadline 3

Closed

DEADLINE 3

Deadline for receipt by the ExA of:

• Post-hearing submissions including written submissions of oral cases • Comments on LIRs • Comments on responses to ExA’s Written Questions (ExQ1) • Any revised/updated SoCGs (if any) • The Applicants revised dDCO • Comments on any additional information/submissions received by D2 • Responses to any further information requested by the ExA for this deadline

6 February 2018 - Deadline 4

Closed

DEADLINE 4

Deadline for receipt by the ExA of:

• Comments on the Applicant’s revised dDCO • Comments on any revised/updated SoCGs (if any) • Comments on any additional information/submissions received by D3 • Responses to any further information requested by the ExA for this deadline

15 February 2018 - Procedural Decision

Closed

Publication by ExA of:

• Further Written Questions (ExQ2) (if required) • ExA’s consultation on the dDCO or dDCO commentary (if required) • Report on the Implications for European Sites (RIES) (if required)

28 February 2018 - Issue Specific Hearing 4 on any Outstanding Issues

Closed

Issue Specific Hearing 4 on any Outstanding Issues

1 March 2018 - Issue Specific Hearing 5 on draft DCO (if required)

Closed

Issue Specific Hearing 5 on draft DCO

8 March 2018 - Deadline 5

Closed

DEADLINE 5

Deadline for receipt by the ExA of:

• Post-hearing submissions including written submissions of oral cases • Any revised/ updated SoCGs • Response to the ExA’s Written Questions (ExQ2) (if required) • Comments on the ExA’s consultation on the dDCO or dDCO commentary (if required) • Comments on the ExA’s RIES (if required) • Comments on any additional information/ submissions received by D4 • Responses to any further information requested by the ExA for this deadline

15 March 2018 - Deadline 6

Closed

DEADLINE 6

Deadline for receipt by the ExA of:

• Comments on any revised/ updated SoCGs • Comments on responses to ExA’s Written Questions (ExQ2) (if required) • The Applicant’s Final Preferred DCO in the SI template validation report • Comments on any additional information/ submissions received by D5 • Responses to any further information requested by the ExA for this deadline

26 March 2018 - Deadline 7

Closed

DEADLINE 7

Deadline for receipt by the ExA of:

• Comments on the Applicant’s Final Preferred DCO • Comments on any additional information/submissions received by D6 • Responses to any further information requested by the ExA for this deadline