26 Hydref 2020
The Secretary of State has made a Correction Order (PDF, 55 KB) affecting The Lake Lothing (Lowestoft) Third Crossing Order 2020. A Correction Notice (PDF, 141 KB) was issued on 21 October 2020. The corrections to the Order are applied following a request from the Applicant dated 11 June 2020 (PDF, 3MB).
30 Ebrill 2020
The Secretary of State has granted development consent for this application. For further information please refer to the following decision documentation:
Planning Inspectorate Notification of Decision Letter
Secretary of State Decision Letter
Development Consent Order as made by the Secretary of State
Examining Authority’s Recommendation Report
Post-Examination Submissions
Regulation 23 Notice
Planning Inspectorate Notification of Decision Letter
Secretary of State Decision Letter
Development Consent Order as made by the Secretary of State
Examining Authority’s Recommendation Report
Post-Examination Submissions
Regulation 23 Notice
30 Ebrill 2020
Decision made by the Secretary of State
29 Ebrill 2020
A Statement has been laid in Parliament by the Secretary of State announcing a new deadline of 5 May 2020 for the decision.
IMPORTANT: As a result of ongoing Government guidance relating to COVID-19 the Planning Inspectorate is seeking to ensure that all Parties are notified of key developments on projects, in a timely manner. In order to help achieve this, and to minimise any delays which could arise if the postal service is affected, it would be extremely helpful if registered Parties that have not already done so could supply us with a contact e-mail address as soon as possible (details in the contact information heading of the project page).
Please be assured that this information will be managed in line with our Privacy Notice.
IMPORTANT: As a result of ongoing Government guidance relating to COVID-19 the Planning Inspectorate is seeking to ensure that all Parties are notified of key developments on projects, in a timely manner. In order to help achieve this, and to minimise any delays which could arise if the postal service is affected, it would be extremely helpful if registered Parties that have not already done so could supply us with a contact e-mail address as soon as possible (details in the contact information heading of the project page).
Please be assured that this information will be managed in line with our Privacy Notice.
6 Ionawr 2020
The Applicant’s response to the Secretary of State’s consultation dated 10 December 2019 has now been published.
11 Rhagfyr 2019
The Department for Transport has asked for comments from the Applicant by 3 January 2020.
15 Tachwedd 2019
In light of the general election, the original decision date of 5 December 2019 for the Lake Lothing Development Consent Order application will now be postponed until a new Government is appointed. A Statement to Parliament setting a new deadline for a decision will be made once Parliament is in session.
The Examining Authority issued a Recommendation Report to the Secretary of State on 05 September 2019. The decision letter and Recommendation Report will be published on this project page once a decision has been made.
The Examining Authority issued a Recommendation Report to the Secretary of State on 05 September 2019. The decision letter and Recommendation Report will be published on this project page once a decision has been made.
14 Hydref 2019
Responses from the Applicant and Associated British Ports to the Secretary of State's consultation have now been published.
10 Hydref 2019
27 Medi 2019
The Department for Transport has asked for comments from the Applicant and Associated British Ports by 11 October 2019.
5 Medi 2019
Recommendations given by the Planning Inspectorate
6 Mehefin 2019
The Examination closed at 23:59 on 5 June 2019.
Submissions to Deadline 11 have now been published.
Additional Submissions, accepted at the discretion of the Examining Authority, have also been published.
Submissions to Deadline 11 have now been published.
Additional Submissions, accepted at the discretion of the Examining Authority, have also been published.
29 Mai 2019
All submissions to Deadline 10 have now been published.
The Examining Authority’s draft Development Consent Order has been published.
The Examining Authority’s draft Development Consent Order has been published.
14 Mai 2019
Updated documents have been submitted by the Applicant reflecting the inclusion of eight non-material changes within the application. These documents were requested by the Examining Authority to Deadline 10 and have been published early in order to facilitate the Examination. All other submissions to Deadline 10 will be published as soon as practicable after 24 May 2019.
29 Ebrill 2019
Submissions to Deadline 9 have now been published.
15 Ebrill 2019
Please note that in the light of the content of this letter from the Applicant dated 12 April 2019, the Examining Authority has decided to defer its Procedural Decision in respect of the proposed changes to the application from 15 April 2019 to a later date.
Submissions to Deadline 8 have now been published.
Submissions to Deadline 8 have now been published.
11 Ebrill 2019
Interested Parties have been notified of further hearings and a second Accompanied Site Inspection.
25 Mawrth 2019
The Examining Authority's second suite of Written Questions has now been published.
6 Mawrth 2019
Submissions to Deadline 6 have now been published.
28 Chwefror 2019
27 Chwefror 2019
Deadline 5 Submissions have been published and added to the Examination Library.
7 Chwefror 2019
4 Chwefror 2019
Interested Parties and others have been notified of changes to the Examination Timetable and of the date, time and place of rescheduled hearings.
24 Ionawr 2019
Interested Parties and others have been notified of a change to the Examining Authority and about the postponement of Issue Specific Hearing 2 (Environment) on 14 February 2019 and Open Floor Hearing 2 on 15 February 2019.
17 Rhagfyr 2018
The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.
Procedural decision following Preliminary Meeting.
5 Rhagfyr 2018
Preliminary Meeting takes place
5 Rhagfyr 2018
Examination begins
6 Tachwedd 2018
The notification of Preliminary Meeting (Rule 6 letter) has been sent.
The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.
10 Hydref 2018
Relevant representations published on the website
24 Medi 2018
Registration of interested parties closes
17 Awst 2018
Registration of interested parties begins
9 Awst 2018
The application has been accepted for examination. View the acceptance letter.
9 Awst 2018
The application has been accepted for examination
13 Gorffennaf 2018
This application was received by the Planning Inspectorate on 13 July 2018.
The application documents will be made available if the application is accepted for examination.
It is for the Applicant to decide whether or not application documents can be published upon submission (see government guidance).
The application documents will be made available if the application is accepted for examination.
It is for the Applicant to decide whether or not application documents can be published upon submission (see government guidance).
13 Gorffennaf 2018
Application received by the Planning Inspectorate