16 July 2020

The Secretary of State has granted development consent for this application. For further information please refer to the following decision documentation:

Planning Inspectorate Notification of Decision Letter
Secretary of State Decision Letter
Development Consent Order as made by the Secretary of State
Examining Authority’s Recommendation Report
Regulation 23 Notice

16 July 2020

Decision made by the Secretary of State

17 April 2020

Recommendations given by the Planning Inspectorate

20 January 2020

The Examination closed at 23.59 on 17 January 2020.

Notification of completion of the Examination has been issued and the Examination Library has been updated.

15 January 2020

The Deadline 9 submissions have been published.

7 January 2020

The Deadline 8 submissions have been published.

20 December 2019

16 December 2019

The Deadline 7 submissions have been published.

6 December 2019

The Deadline 6 submissions have been published.

29 November 2019

The Deadline 5 Submissions have been published.

8 November 2019

The Deadline 4 Submissions have been published.

31 October 2019

The Deadline 3 Submissions have been published.

8 October 2019

2 October 2019

The Accompanied Site Inspection (ASI) Notification letter has been published. The ASI is taking place on Tuesday 15 October 2019.

11 September 2019

The Deadline 2 Submissions have been published.

29 August 2019

The Deadline 1 Submissions have been published.

21 August 2019

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.

Procedural decision following Preliminary Meeting.

13 August 2019

Preliminary Meeting takes place

13 August 2019

Examination begins

12 July 2019

The notification of Preliminary Meeting (Rule 6 letter) has been sent.

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

28 June 2019

Registration of interested parties closes

28 June 2019

Relevant representations published on the website

28 May 2019

The applicant has sent us a letter explaining a number of persons were not provided with section 56 notifications in error. The applicant has sent notifications to those parties and has allowed time for them to make their representations by Friday 28 June 2019.

If you have received a notification and wish to make a representation, please either use the online form or contact us at A19DownhillLaneJunction@planninginspectorate.gov.uk.

28 May 2019

Registration of interested parties begins

22 February 2019

The application has been accepted for examination

28 January 2019

This application was received by the Planning Inspectorate on 25 January 2019.

The applicant has agreed that all application documents can be published as
soon as practicable to help everyone become familiar with the detail of what
is being proposed in this application. The Planning Inspectorate will therefore
make the application documents available as soon as practicable.

This provision is solely for the purpose of allowing more time to all those who
wish to become familiar with the detail of what is being proposed ahead of
the relevant representation period without lengthening the overall time
required for the application process. There will be no opportunity at this
stage to make comments on the application. However, if the application is
accepted anyone interested in the application will be able to register and
express their views during the relevant representation stage and the
subsequent examination.

25 January 2019

Application received by the Planning Inspectorate