M42 Junction 6 Improvement Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 21 May 2019

Caeodd yr archwiliad ar 21 November 2019

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

21 Mai 2019 - Preliminary Meeting

Caeedig

Preliminary Meeting

21 Mai 2019 - Open Floor Hearing

Caeedig

Open Floor Hearing

22 Mai 2019 - USI 1 22 May 2019

Caeedig

Unaccompanied site visit

22 Mai 2019 - Issue Specific Hearing 1

Caeedig

Issue Specific Hearing (DCO) Content of the draft Development Consent Order (DCO 1)

3 Mehefin 2019 - Deadline 1 (D1)

Caeedig

Deadline 1 Deadline for the receipt of:

• Notification of wish to speak at a Compulsory Acquisition Hearing • Request to hold a further Open Floor Hearing • Notification of wish to speak at an Issue Specific Hearing • Notification of suggested locations, and their justifications, for the Accompanied Site Inspection (ASI) on 3 and 4 July and any comments on the current draft ASI –which was submitted prior to the PM where 2 days for the ASI was agreed • Notification by statutory parties of wish to be considered as an Interested Party • Notification of wish to have future correspondence electronically • Comments on Relevant Representations (RRs) • Written Representations (WRs) and summaries of all WRs which exceed 1500 words • Any further information requested by the Panel for this Deadline

24 Mehefin 2019 - Deadline 2 (D2)

Caeedig

Deadline 2 Deadline for the receipt of:

• Local Impact Reports (LIRs) from local authorities • Statements of Common Ground (SoCGs) requested by the Panel – see Annex B • Responses to the Panel’s First Written Questions • Applicant to provide a final ASI itinerary based on requests received at D1 and discussions with Case Team • Post hearing submissions including written submissions of oral case, arising from hearings held on 21 or 22 May • Comments on any additional information and submissions received for D1 • Comments on any further information requested by the Panel for Deadline 1

2 Gorffennaf 2019 - Issue Specific Hearing 2

Caeedig

Issue Specific Hearing (DCO) Content of the draft Development Consent Order (DCO 2)

2 Gorffennaf 2019 - Issue Specific Hearing 3

Caeedig

Issue Specific Hearing Need for improvements at junction 6 on the M42

3 Gorffennaf 2019 - Accompanied Site Inspection

Caeedig

Accompanied Site Inspection Day 1 - Full itinerary will be published in due course.

4 Gorffennaf 2019 - Accompanied Site Inspection

Caeedig

Accompanied Site Inspection Day 2 - Full itinerary will be published in due course.

15 Gorffennaf 2019 - Deadline 3 (D3)

Caeedig

Deadline 3 Deadline for the receipt of:

• Comments on WRs which were received at D2 • Any responses to comments on RRs which were received at D1 • Comments on LIRs which were received at D2 • Comments on responses received at D2 to the Panel’s First Written Questions • Post hearing submissions including written submissions of oral cases, arising from Hearings on 2 July 2019 • Updates to Statements of Common Ground • Responses to any further information requested by the Panel • Comments on any additional information or submissions received for the previous deadline

5 Awst 2019 - Issue of the Panel’s Second Written Questions (if required)

Caeedig

Issue of the Panel’s Second Written Questions (if required)

12 Awst 2019 - Deadline 3A

Caeedig

Deadline 3A Deadline for the receipt of:

• Updated Guide to the Application • Outline Management Plan for Main Site Compound • Consideration of Alternative Locations for the M42 Junction 6 Main Site Compound • Response to CPRE Letter dated 15 July 2019 • Transport Modelling Hierarchy

20 Awst 2019 - Compulsory Acquisition Hearing

Caeedig

Compulsory Acquisition (CA) and Temporary Possession (TP)

21 Awst 2019 - Issue Specific Hearing 4

Caeedig

Issue Specific Hearing (DCO) Content of the draft Development Consent Order (DCO 3)

22 Awst 2019 - Open Floor Hearing

Caeedig

Open Floor Hearing

2 Medi 2019 - Deadline 4 (D4)

Caeedig

Deadline 4 Deadline for the receipt of:

• Responses to the Panel’s Second Written Questions (if required) • Responses to any further information requested by the Panel • Updates to Statements of Common Ground (SoCG) requested by the Panel • Comments on any additional information or submissions received by previous deadline

16 Medi 2019 - Deadline 5 (D5)

Caeedig

Deadline 5 Deadline for the receipt of:

• Applicant’s revised draft DCO • Responses to further information requested by the Panel • Post hearing submissions including written submissions of oral cases, arising from Hearings on 20-22 August 2019 • Comments on any additional information or submissions received by previous deadline

23 Medi 2019 - Publication of the Panel’s further Written Questions (if required)

Caeedig

Publication by the Panel of: • further Written Questions (ExQ3)

1 Hydref 2019 - Issue Specific Hearing 5

Caeedig

Issue Specific Hearing on: Living conditions

2 Hydref 2019 - Issue Specific Hearing 6

Caeedig

Issue Specific Hearing on: Environmental matters

11 Hydref 2019 - Deadline 6 (D6)

Caeedig

Deadline 6 Deadline for the receipt of:

•Comments on the draft DCO, submitted on D5 • Responses to the Panel’s Third Written Questions • Post hearing submissions including written submissions of oral cases, arising from Hearings on 1-3 October 2019 • Environmental Appraisals and Consultation Report on the Proposed changes to the application • Responses to any further information requested by the Panel • Comments on any additional information or submissions received by previous deadline

22 Hydref 2019 - Compulsory Acquisition Hearing 2

Caeedig

Compulsory Acquisition Hearing (CAH 2) Further consideration of Compulsory Acquisition (CA) and Temporary Possession (TP)

23 Hydref 2019 - Issue Specific Hearing 7

Caeedig

Issue Specific Hearing on: Revised content of the draft Development Consent Order (DCO 4)

28 Hydref 2019 - Deadline 7 (D7)

Caeedig

Deadline 7 Deadline for receipt of: • Comments on responses to the Panel’s Third Written Questions • Responses to any further information requested by the Panel • Comments on any additional information or submissions received by previous deadline • Post hearing submissions including written submissions of oral cases, arising from Hearings

5 Tachwedd 2019 - Deadline 8 (D8)

Caeedig

Deadline 8 Deadline for receipt of: • Responses to any further information requested by the Panel • Comments on any additional information or submissions received by previous deadline

8 Tachwedd 2019 - Publication of Panel's preferred dDCO or dDCO commentary

Caeedig

Publication by the Panel of: • The Panel’s preferred dDCO or dDCO commentary (if required)

15 Tachwedd 2019 - Deadline 9 (D9)

Caeedig

Deadline 9 Deadline for receipt of: • Comments on the Panel’s preferred dDCO or dDCO commentary • Final draft DCO to be submitted by the Applicant in the statutory instrument (SI) template with the SI template validation report, together with a revised version of the Explanatory Memorandum • Responses to any further information requested by the Panel

20 Tachwedd 2019 - Deadline 10 (D10)

Caeedig

Deadline 10 Deadline for receipt of: • Responses to any further information requested by the Panel (if required) • Comments on any additional information or submissions received by previous deadline