26 October 2020

A Correction Order (PDF 131KB) and Correction Notice (PDF 122 KB) following the Applicant’s request (PDF 232KB) have been published.

21 May 2020

Decision made by the Secretary of State

24 April 2020

The Responses to the Secretary of State request for comments have now been published.

IMPORTANT: As a result of ongoing Government guidance relating to COVID-19 the Planning Inspectorate is seeking to ensure that all Parties are notified of key developments on projects, in a timely manner. In order to help achieve this, and to minimise any delays which could arise if the postal service is affected, it would be extremely helpful if registered Parties that have not already done so could supply us with a contact e-mail address as soon as possible (details in the contact information heading of the project page).

7 April 2020

The Secretary of State for Transport has requested comments from the Applicant and other Interested Parties by 21 April 2020.

IMPORTANT: As a result of ongoing Government guidance relating to COVID-19 the Planning Inspectorate is seeking to ensure that all Parties are notified of key developments on projects, in a timely manner. In order to help achieve this, and to minimise any delays which could arise if the postal service is affected, it would be extremely helpful if registered Parties that have not already done so could supply us with a contact e-mail address as soon as possible (details in the contact information heading of the project page).

21 February 2020

Recommendations given by the Planning Inspectorate

21 November 2019

The Deadline 10 Submissions have been published.

21 November 2019

The Examination closed at 23:59 on Thursday 21st November 2019.

19 November 2019

The Deadline 9 Submissions have been published.

6 November 2019

The Deadline 8 Submissions have been published.

30 October 2019

The Deadline 7 Submissions have been published.

28 October 2019

The Action Points from the Compulsory Acquisition Hearing (CAH2) and from the Issue Specific Hearing 7 (DCO 4) have been published.

16 October 2019

The Deadline 6 Submissions have been published.

2 October 2019

The Examining Authority covered all the Environmental Matters listed in the agenda during Issue Specific Hearing 6 on  2 October and have decided to cancel Issue Specific Hearing 7 on 3 October as it is no longer necessary.

 

17 September 2019

The Deadline 5 Submissions have been published.

5 September 2019

The Deadline 4 Submissions have been published.

16 August 2019

The Deadline 3A Submissions have been published.

The Applicant has made a request to make non-material changes to the Application.

17 July 2019

The Deadline 3 Submissions have been published.

4 July 2019

28 June 2019

The Deadline 2 Submissions have been published.

6 June 2019

The Deadline 1 Submissions have been published.

31 May 2019

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.

Procedural decision following Preliminary Meeting.

28 May 2019

The Rule 8 letter, which will set out the confirmed timetable, will be issued on or before Friday 31 May. The next deadline is deadline 1 on the 3 June.

Items for this deadline include:

  • Whether you would like us to hold a Compulsory Acquisition Hearing or Open Floor Hearing at the dates indicated in the timetable.

  • If you have any suggested locations for the Accompanied Site Inspection.

  • You can provide a ‘Written Representation’ - this is an email, letter or other document which sets out your views on the Application.

  • You may also wish to comment on Relevant Representations which were submitted to us earlier this year eg you might be interested to read the opinion of a person or organisation and make comments on their opinion.


Please send correspondence for Deadline 1 in writing to M42junction6@planninginspectorate.gov.uk.

22 May 2019

A draft ASI itinerary, which was received shortly before the Preliminary Meeting, has been published. During the meeting and at the later Open Floor Hearing we agreed to a second day to ensure a range of stops for the ASI could be accommodated and to some additional stops.

The audio recordings taken at the Preliminary Meeting, the Open Floor Hearing and the Issue Specific Hearing have also been published.

21 May 2019

Preliminary Meeting takes place

21 May 2019

Examination begins

15 May 2019

The agendas for the Open Floor Hearing and Issue Specific Hearing (ISH) are now available. Please also see the schedule of questions which are intended to be asked at the ISH.

The agenda for the Preliminary Meeting is available in the Rule 6 letter.

23 April 2019

The notification of Preliminary Meeting (Rule 6 letter) has been sent.

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

5 April 2019

Relevant representations published on the website

28 March 2019

Registration of interested parties closes

22 February 2019

Registration of interested parties begins

30 January 2019

The application has been accepted for examination

7 January 2019

This application was received by the Planning Inspectorate on 2 January 2019.

The applicant has agreed that all application documents can be published as
soon as practicable to help everyone become familiar with the detail of what
is being proposed in this application. The Planning Inspectorate will therefore
make the application documents available as soon as practicable.

This provision is solely for the purpose of allowing more time to all those who
wish to become familiar with the detail of what is being proposed ahead of
the relevant representation period without lengthening the overall time
required for the application process. There will be no opportunity at this
stage to make comments on the application. However, if the application is
accepted anyone interested in the application will be able to register and
express their views during the relevant representation stage and the
subsequent examination.

2 January 2019

Application received by the Planning Inspectorate