Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Caeodd yr archwiliad ar 9 October 2019
9 Ebrill 2019 - Preliminary Meeting
CaeedigPreliminary Meeting
9 Ebrill 2019 - Open Floor Hearing
CaeedigOpen Floor Hearing (OFH1)
16 Ebrill 2019 - Issue by the ExA of
Caeedig• Examination Timetable • The ExA’s Written Questions
26 Ebrill 2019 - Deadline 1
CaeedigDEADLINE 1 (D1)
Deadline for receipt by the ExA of: • Comments on updated application documents • Comments on Relevant Representations (RRs) • Summaries of all RRs exceeding 1500 words • Post Hearing submissions including written submissions of oral case made at OFH1 • Notification by Statutory Parties of their wish to be considered as an IP by the ExA • Applicant’s draft itinerary for Accompanied Site Inspection (ASI) • Suggested locations for site inspections, and justification, for consideration by the ExA • Notification of wish to speak at any subsequent Open Floor Hearing (OFH) • Notification of wish to make oral representations at an Issue Specific Hearing (ISH) • Notification of wish to speak at a Compulsory Acquisition Hearing (CAH) • Notification of wish to have future correspondence received electronically • Comments on any additional information/ submissions received • Responses to any further information requested by the ExA for this deadline
17 Mai 2019 - Deadline 2
CaeedigDEADLINE 2 (D2)
Deadline for receipt by the ExA of: • Written Representations (WRs) • Summaries of all WRs exceeding 1500 words • Local Impact Reports from any local authorities • Statements of Common Ground (SoCG) requested by the ExA • Responses to the ExA’s Written Questions • Applicant’s first revised draft DCO • Responses to comments on RRs • Comments on draft itinerary for ASI and suggested locations for site inspections • Notification of wish to attend an ASI • Comments on any additional information/ submissions received by D1 • Responses to any further information requested by the ExA for this deadline
31 Mai 2019 - Deadline 3
CaeedigDEADLINE 3 (D3)
Deadline for receipt by the ExA of: • Comments on WRs • Comments on Local Impact Reports • Comments on SoCG • Comments on responses to the ExA’s Written Questions • Comments on Applicant’s first revised draft DCO • Comments on any additional information/ submissions received by D2 • Responses to any further information requested by the ExA for this deadline
4 Mehefin 2019 - Notification of Hearings and ASI
CaeedigNOTIFICATION OF HEARINGS AND SITE INSPECTION
Time reserved for issue by the ExA of: • Notification of date, time and meeting place for ASI • Notification of Hearings
2 Gorffennaf 2019 - Accompanied Site Inspection
CaeedigAccompanied Site Inspection (ASI)
3 Gorffennaf 2019 - Issue Specific Hearing 1 (ISH1)
CaeedigIssue Specific Hearing on the draft DCO (ISH1)
3 Gorffennaf 2019 - Compulsory Acquisition Hearing
CaeedigCompulsory Acquisition Hearing(CAH1)
3 Gorffennaf 2019 - Open Floor Hearing 2
CaeedigOpen Floor Hearing (OFH2)
12 Gorffennaf 2019 - Deadline 4
CaeedigDEADLINE 4 (D4)
Deadline for receipt by the ExA of: • Post Hearing submissions including written submissions of oral case • Any revised/ updated SoCG (if any) • Comments on any additional information/ submissions received by D3 • Responses to any further information requested by the ExA for this deadline
23 Gorffennaf 2019 - Publication by ExA of -
Caeedig• The ExA’s Further Written Questions (if required)
9 Awst 2019 - Deadline 5
CaeedigDEADLINE 5 (D5)
Deadline for receipt by the ExA of: • Responses to the ExA’s further Written Questions (if required) • Applicant’s revised draft DCO • Comments on any revised/ updated SoCG • Comments on any additional information/ submissions received by D4 • Responses to any further information requested by the ExA for this deadline
13 Awst 2019 - Notification of Hearings
CaeedigTime reserved for issue by the ExA of: • Any notification of Hearings – NOT REQUIRED
19 Awst 2019 - Publication of
Caeedig• The ExA’s Further Written Questions
21 Awst 2019 - Deadline 6 (D6)
CaeedigDeadline 6 (D6) Deadline for receipt by the ExA of: • Comments on responses to the ExA’s further Written Questions (issued on Tuesday 23 July 2019) • Comments on Applicant’s revised draft DCO • Comments on any additional information/ submissions received by D5 • Responses to any further information requested by the ExA for this deadline
27 Awst 2019 - Publication of
Caeedig• Report on the Implications for European Sites (RIES)
2 Medi 2019 - Deadline 6a (D6a)
CaeedigDeadline 6a (D6a) Deadline for receipt by the ExA of: • Responses to the ExA’s Additional Written Questions (issued on Monday 19 August 2019) • Responses to any further information requested by the ExA for this deadline
10 Medi 2019 - Hearings
CaeedigNOT REQUIRED
10 Medi 2019 - Publication of
CaeedigThe ExA’s proposed schedule of changes to the draft DCO (if required)
20 Medi 2019 - Deadline 7 (D7)
CaeedigDeadline 7 (D7) Deadline for receipt by the ExA of: • Comments on the ExA’s proposed schedule of changes to the draft DCO • Comments on the RIES • Comments on any responses to the ExA’s Additional Written Questions (issued on Monday 19 August 2019) • Comments on any additional information/ submissions received by D6 • Responses to any further information requested by the ExA for this deadline
1 Hydref 2019 - Deadline 8 (D8)
CaeedigDeadline 8 (D8) Deadline for receipt by the ExA of: • Response to comments on the RIES • Responses to comments on the ExA’s proposed schedule of changes to the draft DCO • Final DCO to be submitted by the Applicant in the SI template with the SI template validation report • Final updated Book of Reference • Final SoCG • Final Compulsory Acquisition Schedule • Final updated Guide to the Application • Comments on any additional information/ submissions received by D7 • Responses to any further information requested by the ExA for this deadline
7 Hydref 2019 - Deadline 9 - midday
CaeedigDeadline 9 (D9) - midday Deadline for receipt by the ExA of: • Comments on any additional information/ submissions received by D8 • Responses to any further information requested by the ExA for this deadline
9 Hydref 2019 - Close of Examination
CaeedigResponses to any further information requested by the ExA for this deadline.
The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.