Past deadlines and events

6 September 2021 - Procedural Deadline A

Closed

Procedural Deadline A

Deadline for receipt by the ExA of:

  • Written submissions on the Examination procedure including any submissions about the use of virtual procedures
  • Any changes that are considered necessary to the draft Examination Timetable
  • Requests to be heard orally at the Preliminary Meeting

13 September 2021 - Preliminary Meeting Part 1

Closed

Preliminary Meeting Part 1

17 September 2021 - Procedural Deadline B

Closed

Procedural Deadline B

Deadline for receipt by the ExA of:

  • Written submissions on Examination procedure including responses to matters raised orally at the Preliminary Meeting Part 1
  • Requests to be heard orally at the Preliminary Meeting Part 2

23 September 2021 - Preliminary Meeting Part 2

Closed

Preliminary Meeting Part 2 (if required)

13 October 2021 - Deadline 1

Closed

Deadline 1

Deadline for receipt by ExA of:

  • Comments on Relevant Representations
  • Summaries of all RRs exceeding 1500 words
  • Local Impact Reports (LIR) from Local Authorities
  • Written Representations (WRs)
  • Summaries of all WRs exceeding 1500 words
  • Statements of Common Ground (SoCGs)
  • Statement of Commonality for SoCG
  • Compulsory Acquisition Schedule
  • Guide to the Application
  • Notification by Statutory Parties of their wish to be considered as an Interested Party (IP)
  • Notification of wish to speak at an Issue Specific Hearing
  • Notification from any Affected Person of wish to speak at Compulsory Acquisition Hearing
  • Notification of wish to speak at an Open Floor Hearing
  • Nominations of suggested locations and justifications for site inspections for consideration by the ExA
  • Any further information requested by the ExA under Rule 17 of the Examination Procedure Rules (EPR)

26 October 2021 - Deadline 2

Closed

Deadline 2

Deadline for receipt by ExA of:

  • Responses to the ExA’s Written Questions (ExQ1)
  • Comments on LIR(s)
  • Comments on WRs
  • The Applicant’s revised draft Development Consent Order (draft DCO)
  • Schedule of changes to the draft DCO
  • Comments on any additional information/submissions received by Deadline 1
  • Any further information requested by the ExA under Rule 17 of the EPR

16 November 2021 - Open Floor Hearing 1 (OFH1)

Closed

For any Interested Parties to make representations on the merits of the Proposed Development.

17 November 2021 - Issue Specific Hearing 1 (ISH 1)

Closed

Issue Specific Hearing dealing with environmental matters

18 November 2021 - Draft DCO Hearing 1

Closed

Draft DCO Hearing 1 (DCO 1)

23 November 2021 - Deadline 3

Closed

Deadline 3

Deadline for receipt by ExA of:

  • Comments on responses to ExQ1
  • Post hearing submissions including written summaries of oral case
  • The Applicant’s revised draft DCO
  • Schedule of changes to the draft DCO
  • Updated Compulsory Acquisition Schedule
  • Progressed SoCGs
  • Progressed Statement of Commonality for SoCG
  • Comments on any additional information/submissions received by Deadline 2
  • Any further information requested by the ExA under Rule 17 of the EPR

23 November 2021 - Unaccompanied and Access Required Site Inspection

Closed

Unaccompanied and Access Required Site Inspection

30 November 2021 - Publication by the ExA 1

Closed

Publication by the ExA of:

• Further Written Questions (ExQ2) (if required) • Notice to hold an Accompanied Site Inspection in the week commencing Monday 17 January 2022 (in the event the ExA considers it necessary)

6 December 2021 - Deadline 4

Closed

Deadline 4

Deadline for receipt by ExA of:

  • An updated Guide to the Application
  • Comments on any additional information/submissions received by Deadline 3
  • Any further information requested by the ExA under Rule 17 of the EPR

20 December 2021 - Deadline 5

Closed

Deadline 5

Deadline for receipt by ExA of:

  • Responses to ExQ2 (if required)
  • The Applicant’s revised draft DCO
  • Schedule of changes to the draft DCO
  • Updated Compulsory Acquisition Schedule
  • Progressed SoCGs
  • Progressed Statement of Commonality for SoCG
  • Applicant’s suggested draft Itinerary for an ASI (if required)
  • Comments on any additional information/submissions received by Deadline 4
  • Any further information requested by the ExA under Rule 17 of the EPR

17 January 2022 - Accompanied Site Inspection

Closed

Accompanied Site Inspection (only if deemed to be required by ExA)

18 January 2022 - Deadline 6

Closed

Deadline 6

Deadline for receipt by the ExA of:

  • Comments on responses to the ExQ2 (if required)
  • An updated Guide to the Application
  • The Applicant’s revised draft DCO
  • Schedule of changes to the draft DCO
  • Updated Compulsory Acquisition Schedule
  • Comments on any additional information/submissions received by Deadline 5
  • Any further information requested by the ExA under Rule 17 of the EPR

31 January 2022 - Hearings 2

Closed

Hearings 2

Date reserved to hold any: • Open Floor Hearing (OFH) (if required) • Compulsory Acquisition Hearing(s)(CAHs) (if required) • Issue Specific Hearing(s) (ISHs) (if required)

10 February 2022 - Deadline 7

Closed

Deadline 7

Deadline for receipt by the ExA of:

  • Post hearing submissions including written summaries of oral case
  • Updated Compulsory Acquisition Schedule
  • The Applicant’s revised draft DCO
  • Schedule of changes to the draft DCO
  • Progressed SoCGs
  • Progressed Statement of Commonality for SoCG
  • Comments on any additional information/submissions received by Deadline 6
  • Any further information requested by the ExA under Rule 17 of the EPR

21 February 2022 - Publication by the ExA 2

Closed

Publication by the ExA of:

• The Report on the Implications for European Sites (RIES) (if required) • The ExA’s proposed schedule of changes to the draft DCO/Commentary on the draft DCO (if required)

28 February 2022 - Hearings 3

Closed

Date reserved to hold any:

• Open Floor Hearing (OFH) (if required) • Compulsory Acquisition Hearing(s)(CAHs) (if required) • Issue Specific Hearing(s) (ISHs) (if required)

1 March 2022 - Open Floor Hearing 2 (OFH2)

Closed

For any Interested Parties to make representations on the merits of the Proposed Development.

2 March 2022 - Compulsory Acquisition Hearing 1 (CAH1)

Closed

Compulsory Acquisition Hearing

3 March 2022 - Deadline 8

Closed

Deadline 8

Deadline for receipt by the ExA of:

  • Comments on the ExA’s proposed schedule of changes to the draft DCO/Commentary on the draft DCO (if issued)
  • An updated Guide to the Application
  • Comments on any additional information/submissions received by Deadline 7
  • Any further information requested by the ExA under Rule 17 of the EPR

3 March 2022 - Issue Specific Hearing 2 (ISH2)

Closed

Issue Specific Hearing 2 (ISH 2) on Environmental Matters and Draft DCO

14 March 2022 - Deadline 9

Closed

Deadline 9

Deadline for receipt by the ExA of:

  • Comments on the RIES (if issued)
  • Post hearing submissions including written summaries of oral case
  • Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report
  • Final Explanatory Memorandum
  • Final Compulsory Acquisition Schedule (identifying any unresolved objections)
  • Final SoCGs
  • Final Statement of Commonality also listing matters not agreed (in circumstances where a SoCG could not be finalised)
  • Comments on any additional information/submissions received by Deadline 8
  • Any further information requested by the ExA under Rule 17 of the EPR

18 March 2022 - Deadline 10

Closed

Deadline 10

Deadline for receipt by the ExA of:

  • Final Guide to the Application
  • Comments on any additional information/submissions received by Deadline 9
  • Any further information requested by the ExA under Rule 17 of the EPR

23 March 2022 - End of Examination

Closed

End of Examination:

The ExA is under duty to complete the examination of the application by the end of the period of six months