A1 in Northumberland - Morpeth to Ellingham Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 5 January 2021

The examination closed on 5 July 2021

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

10 December 2020 - Procedural Deadline A

Closed

Procedural Deadline A

Deadline for receipt by the ExA of:

• Written submissions on Examination procedure; and • requests to be heard orally at the Preliminary Meeting Part 1.

15 December 2020 - Preliminary Meeting (Part 1)

Closed

Preliminary Meeting (Part 1)

15 December 2020 - Preliminary Meeting Part 1

Closed

Preliminary Meeting Part 1

22 December 2020 - Procedural Deadline B

Closed

Procedural Deadline B

Deadline for receipt by the ExA of:

• Written submissions on Examination procedure including submissions responding to matters raised orally in the Preliminary Meeting Part 1; and • requests to be heard orally at the Preliminary Meeting Part 2.

5 January 2021 - Preliminary Meeting (Part 2)

Closed

Preliminary Meeting (Part 2)

5 January 2021 - Preliminary Meeting Part 2

Closed

Preliminary Meeting Part 2

6 January 2021 - Publication by the ExA of 1

Closed

Publication by the ExA of:

• Examination Timetable • ExA’s Written Questions (ExQ1) (as originally issued 19 November 2020)

12 January 2021 - Deadline 1

Closed

Deadline 1

Deadline for receipt by ExA of:

  • Responses to The ExA’s Written Questions (ExQ1) issued on 19 November 2020
  • Local Impact Reports (LIR) from Local Authorities
  • Comments on Relevant Representations
  • Notification by Statutory Parties of their wish to be considered as an Interested Party (IP) by the ExA
  • Statements of Common Ground (SoCG) requested by the ExA
  • Statement of Commonality for SoCG
  • The Compulsory Acquisition Schedule
  • Notification of wish to participate in Open Floor Hearings
  • Notification of wish to participate in Issue Specific Hearings
  • Notification of wish to participate in Compulsory Acquisition Hearings
  • Notification of wish to attend Accompanied Site Inspection (ASI)

29 January 2021 - Deadline 2

Closed

Deadline 2

Deadline for receipt by ExA of:

  • Comments on responses for Deadline 1
  • Comments on responses to ExQ1
  • Written Representations (WRs) including summaries of all WRs exceeding 1500 words
  • Progressed SoCG
  • Progressed Statement of Commonality for SoCG
  • An updated Guide to the Application
  • An updated version of the draft Development Consent Order (dDCO) in clean and tracked versions
  • Schedule of changes to dDCO
  • An updated Compulsory Acquisition Schedule in clean and tracked versions
  • Submission by Applicant of proposed locations of ASI
  • Any further information requested by the ExA under Rule 17 of the Examination Rules

12 February 2021 - Deadline 3

Closed

Deadline 3

Deadline for receipt by ExA of:

  • Comments on responses submitted for Deadline 2
  • Comments on LIR(s)
  • Comments on WRs
  • An updated Guide to the Application
  • An updated Compulsory Acquisition Schedule in clean and tracked versions
  • Progressed Statement of Common Ground
  • Progressed Statement of Commonality for SoCG
  • Any further information requested by the ExA under Rule 17 of the Examination Rules
  • Responses to any further information requested by the ExA under Rule 17 of the Examination Rules (if required)

22 February 2021 - Open Floor Hearing 1

Closed

Open Floor Hearing (OFH1)

22 February 2021 - Open Floor Hearing 2

Closed

Open Floor Hearing (OFH2)

23 February 2021 - Issue Specific Hearing 1

Closed

Issue Specific Hearing into the dDCO (ISH1)

24 February 2021 - Compulsory Acquisition Hearing 1

Closed

Compulsory Acquisition Hearing 1 (CAH1)

25 February 2021 - Issue Specific Hearing 2 (Part 1)

Closed

Issue Specific Hearing 2 (ISH2) - Part 1

26 February 2021 - Issue Specific Hearing 2 (Part 2)

Closed

Issue Specific Hearing 2 (ISH2) - Part 2

2 March 2021 - Hearings 1

Closed

Date reserved for any: • Issue Specific Hearing (if required)

12 March 2021 - Deadline 4

Closed

Deadline 4

Deadline for receipt by ExA of:

  • Comments on responses submitted for Deadline 3
  • Written summaries of oral submissions to Hearings held during the week 22 February 2021
  • Any post-Hearing notes requested at the Hearings
  • An updated Guide to the Application
  • An updated version of the dDCO in clean and tracked versions
  • An updated Schedule of changes to the dDCO
  • Comments on the Applicant’s draft ASI arrangements and itinerary
  • An updated Compulsory Acquisition Schedule in clean and tracked versions
  • Progressed SoCG
  • Progressed Statement of Commonality for SoCG
  • Any further information requested by the ExA under Rule 17 of the Examination Rules
  • Responses to any further information requested by the ExA under Rule 17 of the Examination Rules (if required)

19 March 2021 - Publication by the ExA of 2

Closed

Publication by the ExA of:

• Further Written Questions (ExQ2) (if required) • Report on the Implications for European Sites (RIES) (if required)

29 March 2021 - Accompanied Site Inspections

Closed

Accompanied Site Inspections

1 April 2021 - Deadline 5

Closed

Deadline 5

Deadline for receipt by ExA of:

  • Responses to ExQ2 (if required)
  • Comments on responses submitted for Deadline 4
  • An updated Guide to the Application
  • An updated version of the dDCO in clean and tracked versions
  • An updated Schedule of changes to dDCO
  • An updated Compulsory Acquisition Schedule in clean and tracked versions
  • Progressed SoCG
  • Progressed Statement of Commonality for SoCG
  • Any further information requested by the ExA under Rule 17 of the Examination Rules
  • Responses to any further information requested by the ExA under Rule 17 of the Examination Rules (if required)

16 April 2021 - Deadline 5a

Closed

Deadline 5a

Deadline for receipt by  ExA  of: 

  • Comments on responses submitted in response to the ExA’s Rule 17 letter of 30 March ([REP5-032] [REP5-044])

20 April 2021 - Compulsory Acquisition Hearing 2

Closed

Compulsory Acquisition Hearing 2 (CAH2)

21 April 2021 - Issue Specific Hearing 3 Part 1

Closed

Issue Specific Hearing 3 (ISH3) - Part 1

22 April 2021 - Issue Specific Hearing 3 Part 2

Closed

Issue Specific Hearing 3 (ISH3)- Part 2

23 April 2021 - Hearings 2

Closed

Hearings (Reserve Date)

27 April 2021 - Hearings 3

Closed

Date reserved for any:   •  Issue Specific Hearing (if required). 

4 May 2021 - Deadline 6

Closed

Deadline 6

Deadline for receipt by ExA of:

  • Comments on responses submitted for Deadline 5
  • Written summaries of oral submissions to Hearings held during the week commencing 19 April 2021 and if held 27 April 2021
  • Any post-Hearing notes requested at the Hearings
  • Comments on the RIES (if required)
  • An updated Guide to the Application
  • An updated version of the dDCO in clean and tracked versions
  • An updated Schedule of changes to dDCO
  • An updated Compulsory Acquisition Schedule in clean and tracked versions
  • Progressed SoCG
  • Progressed Statement of Commonality for SoCG
  • Any further information requested by the ExA under Rule 17 of the Examination Rules
  • Responses to any further information requested by the ExA under Rule 17 of the Examination Rules (if required)

11 May 2021 - Deadline 7

Closed

Deadline 7

Deadline for receipt by ExA of:

  • Responses to comments on the REIS (if required)
  • Comment on responses submitted for Deadline 6
  • Updated SoCG
  • Update Statement of Commonality for SoCG
  • Any further information requested by the ExA under Rule 17 of the Examination Rules
  • Responses to any further information requested by the ExA under Rule 17 of the Examination Rules (if required)
  • Documents and information requested by the ExA from the Applicant in the Procedural Decision dated 9 April 2021 following the Applicant’s submission of proposed changes at D4, namely hydraulic modelling and geomorphological information

11 May 2021 - Publication by the ExA of 3

Closed

Publication by the ExA of:

• Further Written Questions (ExQ3) (if required) • The ExA’s proposed schedule of changes to the dDCO (if required)

20 May 2021 - Deadline 7a

Closed

Deadline 7a

Deadline for receipt by ExA of: 

  • Representations on the Applicant’s changes to the application received at D4

24 May 2021 - Publication by the ExA of 4

Closed

Publication by the ExA of:

• Further Written Questions (ExQ4) (if required).

25 May 2021 - Deadline 8

Closed

Deadline  8 

Deadline for receipt by ExA of: 

  • Comments on responses submitted for Deadline 7
  • Responses to ExQ3 (if required)
  • Updated SoCG
  • Updated Statement of Commonality for SoCG
  • An updated Guide to the Application
  • An updated Book of Reference 
  • An updated Statement of Reasons
  • Signed and dated s106 Agreements (if required)
  • Comments on the ExA’s proposed schedule of changes to the dDCO (if issued)
  • An updated version of the dDCO in clean and tracked versions
  • An updated Schedule of changes to dDCO
  • Any further information requested by the ExA under Rule 17 of the Examination Rules (if required)
  • Responses to any further information requested by the ExA under Rule 17 of the EPR (if required)

4 June 2021 - Deadline 8a

Closed

Deadline 8a

Deadline for receipt by the ExA of:

  • Responses to ExQ4 (if required)

7 June 2021 - Hearings 4

Closed

Dates reserved for any: 

• Issue Specific Hearing(s) (if required)  • Open Floor Hearing(s) (if required)  • Compulsory Acquisition Hearing(s) (if required).

14 June 2021 - Hearings 5

Closed

Dates reserved for any: 

• Issue Specific Hearing(s) (if required) • Open Floor Hearing(s) (if required) • Compulsory Acquisition Hearing(s) (if required).

15 June 2021 - Deadline 9

Closed

Deadline 9

  • Comments on responses submitted for Deadline 8 and Deadline 8a
  • Any post-Hearing notes requested at the Hearings
  • Any further information requested by the ExA under Rule 17 of the Examination Rules (if required)
  • Responses to any further information requested by the ExA under Rule 17 of the EPR (if required)

29 June 2021 - Deadline 10

Closed

Deadline  10 

Deadline for receipt by ExA of:

  • Comments on responses submitted for Deadline 9
  • Written summaries of oral submissions to Hearings held during the week commencing 7 and  14 June  2021 
  • Any post-Hearing notes requested at the Hearings
  • Finalised SoCG
  • Finalised Statement of Commonality for SoCG 
  • Finalised Statement of Compulsory Acquisition Schedule in clean and tracked versions
  • A finalised Guide to the Application
  • A finalised version of the dDCO in clean and tracked versions
  • A finalised Schedule of changes to the dDCO
  • Any further information requested by the ExA  under Rule 17 of the Examination Rules (if required)
  • Responses to any further information requested by the ExA under Rule 17 of the EPR (if required)

2 July 2021 - Deadline 11

Closed

Deadline  11 

Deadline for receipt by ExA of: 

  • Comments on responses submitted for Deadline 10
  • Any further information requested by the  ExA (if required) under Rule 17 of the EPR (if required)