A46 Newark Bypass Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 8 October 2024

The examination is expected to close on 8 April 2025

Have your say

Upcoming deadlines and events

14 January 2025 - The ExA’s Written Questions (ExQ2)

Publication by the ExA of:

  • ExA’s Second Written Questions (ExQ2), if required
  • Report on the Implications for European Sites (RIES) and any associated questions, if required

4 February 2025 - Deadline 5

Open

Deadline 5

For receipt by the ExA of:

  • Responses to ExQ2, if required
  • Responses on the (RIES) and any associated questions, if required
  • Comments on any submissions received at the previous deadline
  • Responses to any further information requested by the ExA for this deadline

From the Applicant

  • Updated NPS accordance table
  • Updated application documents tracker
  • Updated BoR
  • Updated Schedule of Changes to the BoR
  • Updated Land Rights Tracker
  • Updated dDCO
  • Updated Schedule of Changes to the dDCO
  • Updated EM
  • Updated SoCG and SoC
  • Updated legal agreements, if identified

17 February 2025 - Week reserved for Hearings (if required)

Week reserved for Hearings, if required for:

  • Further Issue Specific Hearing(s)
  • Further Compulsory Acquisition Hearing(s)
  • Further Open Floor Hearing(s)

25 February 2025 - Deadline 6

Deadline 6

For receipt by the ExA of:

  • Written summaries of oral submissions made at the Hearings
  • Comments on any submissions received at the previous deadline
  • Responses to any further information requested by ExA

From the Applicant

  • Updated application documents tracker
  • Updated Land Rights Tracker
  • Updated dDCO
  • Updated Schedule of Changes to the dDCO
  • Updated EM
  • Updated SoCG and SOC
  • Updated legal agreements, if identified

12 March 2025 - The ExA’s Written Questions (ExQ3)

Publication by the ExA of:

  • ExQ3, if required
  • ExA’s commentary on, or schedule of changes to, the dDCO

25 March 2025 - Dradline 7

Deadline 7

For receipt by the ExA of:

  • Responses to ExQ3, if required
  • Comments on the ExA’s schedule of changes to the dDCO, if issued
  • Comments on any submissions received at the previous deadline
  • Responses to any further information requested by the ExA

3 April 2025 - Deadline 8

Deadline 8

For receipt by the ExA of:

  • Comments on any submissions received at the previous deadline
  • Responses to any further information requested by ExA

From the Applicant:

  • Final application document tracker
  • Final updated BoR
  • Final BoR (with full land registry refresh) and schedule of changes to BoR
  • Final Land Rights Tracker
  • Final dDCO, in clean and tracked versions in both MS Word and PDF
  • Final draft DCO to be submitted in the SI template with the SI template validation report.
  • Final Schedule of Changes to the dDCO
  • Final EM
  • Final SoCGs
  • List of matters not agreed where SoCG could not be finalised
  • Final SOC
  • Final NPS accordance table
  • Final signed and dated legal agreements, if any identified

7 April 2025 - Deadline 9

Deadline 9:

For receipt by the ExA of:

  • Parties’ closing statements of final position on outstanding matters not resolved by end of examination
  • Responses to any further information requested by ExA

8 April 2025 - End of Examination

The ExA is under a duty to complete the Examination of the application by the end of the period of six months

Past deadlines and events

24 September 2024 - Procedural Deadline A

Closed

Procedural Deadline A

Deadline for receipt by the ExA of:

  • Written submissions on the Examination Procedure, including any submissions about the use of virtual methods
  • Requests to be heard orally at the Preliminary Meeting
  • Requests to attend the Preliminary Meeting or any Hearings
  • Suggested locations for site inspections (accompanied or unaccompanied), including justification, for consideration by the ExA

8 October 2024 - Preliminary Meeting (PM)

Closed

Preliminary Meeting (PM)

8 October 2024 - Open Floor Hearing (OFH) 1

Closed

Open Floor Hearing (OFH) 1

9 October 2024 - Compulsory Acquisition (CAH) 1

Closed

Compulsory Acquisition (CAH) 1

22 October 2024 - Deadline 1

Closed

Deadline 1:

Deadline 1 For receipt by the ExA of:

  • Comments on Relevant Representations (RR)
  • Written summaries of oral submissions made at the PM or Hearings
  • Requests to be heard at notified hearings, see Annex E of the Rule 6 letter
  • Requests to be heard at an OFH
  • Requests by Affected Persons (defined in section 59(4) of the Planning Act 2008) to be heard at a CAH
  • Notification by any Statutory Parties who have not submitted a RR of their wish to be considered as an Interested Party
  • Responses to any further information requested by ExA From Local Authorities
  • Local Impact Report (LIR) From the Applicant
  • Suggested Accompanied Site Inspection (ASI) itinerary
  • Land Rights Tracker
  • Initial Statements of Common Ground (SoCG) and Statement of Commonality (SoC) If changes have been made:
  • Updated application documents tracker
  • Updated Book of Reference (BoR)
  • Updated Schedule of Changes to the BoR
  • Updated draft Development Consent Order (dDCO)
  • Updated Schedule of Changes to the dDCO
  • Updated Explanatory Memorandum (EM)
  • Updated legal agreements, if identified

12 November 2024 - Deadline 2

Closed

Deadline 2

For receipt by the ExA of:

  • Written Representations (WR), including summaries of any WR exceeding 1500 words
  • Responses to ExQ1
  • Comments on SoCG and SoC
  • Comments on the Applicant’s suggested itinerary for an ASI1, if required
  • Comments on LIR
  • Comments on any other submissions received at the previous deadline
  • Responses to any further information requested by ExA

From the Applicant If changes have been made:

  • Updated application documents tracker
  • Updated Land Rights Tracker
  • Updated dDCO
  • Updated Schedule of Changes to the dDCO
  • Updated EM
  • Updated SoCG and SoC
  • Updated legal agreements, if identified

26 November 2024 - Deadline 3

Closed

Deadline 3

For receipt by the ExA of:

  • Comments on WR
  • Responses to comments on RR
  • Comments on responses to ExQ1
  • Updated BoR (full land registry refresh)
  • Comments on any submissions received at the previous deadline
  • Responses to any further information requested by ExA

2 December 2024 - Dates Rerved for Hearings and ASI if required

Closed

Week reserved for any (if required)

  • Issue Specific Hearing(s)
  • Compulsory Acquisition Hearing(s)
  • Further Open Floor Hearing(s)
  • ASI

13 December 2024 - Deadline 4

Closed

Deadline 4

For receipt by the ExA of:

  • Written summaries of oral submissions made at the previous Hearings
  • Comments on any submissions received at the previous deadline
  • Responses to any further information requested by ExA From the Applicant
  • Updated application documents tracker
  • Updated Land Rights Tracker
  • Updated dDCO
  • Updated Schedule of Changes to the dDCO
  • Updated EM
  • Updated SoCG and SoC
  • Updated legal agreements, if identified