York Potash Harbour Facilities Order Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 21 July 2015

The examination closed on 21 January 2016

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

21 July 2015 - Preliminary Meeting

Closed

Preliminary Meeting

27 July 2015 - Deadline 1

Closed

Publication by ExA of: · Examination timetable · ExA first written questions

21 August 2015 - Deadline 2

Closed

Deadline 1

Deadline for receipt by the ExA of: · Comments on relevant representations (RRs) and submissions accepted at the preliminary meeting · Summaries of all RRs exceeding 1500 words · Written representations (WRs) by all interested parties · Summaries of all WRs exceeding 1500 words · Local Impact Report from any local authorities · Any statements of Common Ground requested by ExA · Responses to ExA’s first written questions · Notification of wish to speak at a Compulsory Acquisition or Open Floor hearing · Notification of wish to make oral representations at the issue specific hearing on the draft Development Consent Order (DCO) · Notification of wish to attend an accompanied site visit, or submission on the itinerary for such a visit.

7 September 2015 - Deadline 3

Closed

Deadline 2

Deadline for receipt by the ExA of: · Comments on WRs and responses to comments on RRs · Comments on Local Impact Reports · Comments on responses to ExA’s first written questions · Any revised draft DCO from applicant · Any draft Development Consent Obligation from the applicant.

23 September 2015 - Site Visit (Accompanied)

Closed

Accompanied Site Visit

24 September 2015 - Open Floor Hearing 1

Closed

Open Floor Hearing

24 September 2015 - Compulsory Acquisition Hearing 1

Closed

Compulsory Acquisition Hearing

24 September 2015 - Open Floor Hearing 2

Closed

Open Floor Hearing

25 September 2015 - Issue Specific Hearing 1

Closed

Hearing on the Draft Development Consent Order

2 October 2015 - Deadline 4

Closed

Deadline 3

Submissions following hearings in the week of commencing 21 September 2015: · Written submissions made in lieu of oral submissions at hearings · Summaries of oral submissions to the hearings · Written responses to any questions put to the parties orally by the ExA at the hearings · Any revised draft DCO from applicant

16 October 2015 - Deadline 5

Closed

Publication by ExA of: · Second written questions

6 November 2015 - Deadline 6

Closed

Deadline 4

Deadline for receipt by the ExA of: · Responses to ExA’s second written questions · Comments on written submissions from hearings · Any revised draft DCO from applicant

20 November 2015 - Deadline 7

Closed

Deadline 5

Deadline for receipt by the ExA of: · Comments on responses to ExA’s second written questions

24 November 2015 - Compulsory Acquisition Hearing 2

Closed

Compulsory Acquisition Hearing

24 November 2015 - Issue Specific Hearing 2

Closed

Hearing on the Draft Development Consent Order

25 November 2015 - Deadline 8

Closed

Publication by ExA of: · Report on the Implications for European Sites (RIES) · Draft Development Consent Order

16 December 2015 - Deadline 9

Closed

Deadline 6

Deadline for receipt by the ExA of: · Comments on the RIES · Comments on draft DCO · Any outstanding comments on submissions to the examination before this date

30 December 2015 - Deadline 10

Closed

Deadline 7

Deadline for receipt by the ExA of: · Comments on responses to the draft DCO · Comments on responses to the RIES · Any further submissions in relation to comments