Nid oes unrhyw derfynau amser neu ddigwyddiadau
Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Agorodd yr archwiliad ar 20 February 2024
Caeodd yr archwiliad ar 20 August 2024
6 Chwefror 2024 - Procedural Deadline A
CaeedigProcedural Deadline A For receipt by the Examining Authority of:
- Request to change from postal to email notifications for parties who receive notifications by post
- Proposed Familiarisation Site Inspection (FSI) itinerary from the Applicant
- Any written submissions about how the application is to be Examined
- Receipt of additional application material from the Applicant
6 Chwefror 2024 - Registration for the events week commencing 19 February 2024
CaeedigRegistration for the events week commencing 19 February 2024
20 Chwefror 2024 - Preliminary Meeting
CaeedigPreliminary Meeting (PM)
20 Chwefror 2024 - Issue Specific hearing 1 (ISH1)
CaeedigIssue Specific hearing 1 (ISH1)
21 Chwefror 2024 - Issue Specific hearing 2 (ISH2)
CaeedigIssue Specific hearing 2 (ISH2)
22 Chwefror 2024 - Issue Specific hearing 3 (ISH3)
CaeedigIssue Specific hearing 3 (ISH3)
23 Chwefror 2024 - Familiarisation Site Inspection
CaeedigFamiliarisation Site Inspection
13 Mawrth 2024 - Deadline 1 (D1)
CaeedigDeadline 1 For receipt by the Examining Authority of:
- Responses to Relevant Representations
- Written Representations (WR), including summaries of all WRs exceeding 1500 words
- Responses to the Examining Authority’s First Written Questions
- Applicant’s Land Rights Tracker
- Applicant’s Statutory Undertakers Schedule
- Statements of Common Ground
- Applicant’s Statement of Commonality
- Local Impact Reports from relevant Local Authorities
- Notification by Statutory Parties of their wish to be considered as an Interested Party by the Examining Authority
- Requests for Open Floor Hearing
- Requests for Compulsory Acquisition Hearing
- Nominations for locations to be included in Examining Authority’s site inspections
- Any other information requested by the Examining Authority under Rule 17 of the Examination Procedure Rules
Updates from the Applicant
- Guide to the Application
- Draft Development Consent Order, including consolidated tracked changed version
- Explanatory Memorandum
- Schedule of changes to Draft Development Consent Order
26 Mawrth 2024 - Deadline 2 (D2)
CaeedigDeadline 2 For receipt by the Examining Authority of:
- Comments on responses to Relevant Representation
- Comments on Written Representations
- Comments on responses to the Examining Authority’s First Written Questions
- Comments on the Local Impact Reports
- Comments from Affected Persons on Applicant’s Compulsory Acquisition Schedule
- Applicant’s proposed Accompanied Site Inspection itinerary (if requested by the Examining Authority)
- Comments on any other information and submissions received at Deadline 1
- Confirmation of wish to attend and speak at the Hearings w/c 8 April 2024 and w/c 15 April, including details of topics of discussion
- Any other information requested by the Examining Authority under Rule 17 of the Examination Procedure Rules
3 Ebrill 2024 - Registration for the events week commencing 8 and 15 April 2024
CaeedigRegistration for the events week commencing 8 and 15 April 2024
19 Ebrill 2024 - Dates reserved for Hearings and Site Inspection
CaeedigDates reserved for Hearings and Site Inspection
Weeks commencing 8 April and 15 April 2024
- Accompanied Site Inspection
- Compulsory Acquisition Hearing
- Issue Specific Hearing
- Open Floor Hearing
3 Mai 2024 - Deadline 3 (D3)
CaeedigDeadline 3 (D3) For receipt by the Examining Authority of:
- Post-Hearing submissions including written submissions of oral case as requested by Examining Authority
- Comments on any other information and submissions received at Deadline 2
- Any further information requested by the Examining Authority under Rule 17 of the Examination Procedure Rules
Updates from the applicant
- Guide to the Application
- Statements of Common Ground
- Statement of Commonality
- Draft Development Consent Order, including consolidated tracked changed version
- Explanatory Memorandum
- Schedule of Changes to Draft Development Consent Order
- Land Rights Tracker
17 Mai 2024 - Publication by the Examining Authority of
CaeedigPublication by the Examining Authority of:
- Second Written Questions (if issued)
4 Mehefin 2024 - Deadline 4 (D4)
CaeedigDeadline 4 (D4) For receipt by the Examining Authority of:
- Responses to the Examining Authority’s Second Written Questions (WQ2) (if issued)
- Comments on any other information and submissions received at Deadline 3
- Confirmation of wish to attend and speak at the Hearings w/c 1 July 2024 including details of topics of discussion
- Any further information requested by the Examining Authority under Rule 17 of the Examination Procedure Rules
Updates from the Applicant:
- Guide to the Application
- Statements of Common Ground
- Statement of Commonality
- Draft Development Consent Order
- Explanatory Memorandum
- Schedule of Changes to Draft Development Consent Order
- Land Rights Tracker
2 Gorffennaf 2024 - Issue Specific Hearing 8 (ISH8)
CaeedigIssue Specific Hearing 8 (ISH8) on the Draft Development Consent Order and Environmental Matters
11 Gorffennaf 2024 - Deadline 5 (D5)
CaeedigDeadline 5 (D5) For receipt by the Examining Authority of:
- Post-Hearing submissions including written submissions of oral case as requested by Examining Authority (if the Hearings are held)
- Comments on responses to the Examining Authority’s Second Written Questions (WQ2) (if issued)
- Comments on any other information and submissions received at Deadline 4
- Any further information requested by the Examining Authority under Rule 17 of the Examination Rules
Updates from the Applicant:
- Guide to the Application
- Statements of Common Ground
- Statement of Commonality
- Draft Development Consent Order including consolidated tracked changed version
- Explanatory Memorandum
- Schedule of Changes to Draft Development Consent Order
- Land Rights Tracker
17 Gorffennaf 2024 - Publication by the Examining Authority of
CaeedigPublication by the Examining Authority of:
- The Report on Implications for European Sites and any associated questions (if required)
- Third Written Questions (if required)
- The ExA’s proposed schedule of changes to the draft Development Consent Order (if required)
2 Awst 2024 - Deadline 6 (D6)
CaeedigDeadline 6 (D6) For receipt by the Examining Authority of:
- Responses to the Examining Authority’s Third Written Questions (WQ3) (if issued)
- Comments on the Examining Authority’s proposed schedule of changes to the draft Development Consent Order (if issued)
- Comments on any other information and submissions received at Deadline 5
- Any further information requested by the Examining Authority under Rule 17 of the Examination Procedure Rules
15 Awst 2024 - Deadline 7 (D7)
CaeedigDeadline 7 (D7) For receipt by the Examining Authority of:
- Comments on the Report on Implications for European Sites (if issued)
- Comments on responses to Examining Authority’s Third Written Questions (WQ3) (if issued)
- Comments on responses to the Examining Authority’s proposed schedule of changes to the draft Development Consent Order (if issued)
- Comments on any other information and submissions received at Deadline 6
- Any further information requested by the Examining Authority under Rule 17 of the Examination Procedure Rules
Final Updates from the Applicant:
- Final Statements of Common Ground
- Final Statement of Commonality
- Final Guide to the Application
- Final draft Development Consent Order in the Statutory Instrument (SI) template in both word and PDF versions
- SI template validation report and
- Consolidated tracked changed version of the final draft Development Consent Order
- Final Explanatory Memorandum
- Final Schedule of changes to draft Development Consent Order
- Final Land Rights Tracker
- Final updated Book of Reference
20 Awst 2024 - Deadline 8 (D8)
CaeedigDeadline 8 (D8) For receipt by the Examining Authority of:
- Any further information requested by Examining Authority
20 Awst 2024 - Close of Examination by the Examining Authority
CaeedigClose of Examination by the Examining Authority
- The Examining Authority is under a duty to complete the examination of the application by the end of the period of six months.
6 Rhagfyr 2024 - SoS consultation 1
CaeedigSoS consultation 1
- Request for comments from all Interested Parties on the Applicant's letter dated 11 November 2024
16 Rhagfyr 2024 - SoS consultation 2
CaeedigSoS consultation 2
- Request for the Applicant to provide a further update on any matters that remain outstanding.
18 Rhagfyr 2024 - SoS consultation 3
CaeedigSoS consultation 3
- Request for comments from Marine Management Organisation and Natural England in relation to the strategic oversight of projects within the Humber Estuary