Nid oes unrhyw derfynau amser neu ddigwyddiadau
Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Agorodd yr archwiliad ar 18 April 2013
Caeodd yr archwiliad ar 14 October 2013
18 Ebrill 2013 - Preliminary Meeting
CaeedigPreliminary meeting
30 Ebrill 2013 - Deadline 1
CaeedigIssue of: • Procedural timetable • Examining Authority’s (ExA) first written questions
15 Mai 2013 - Deadline 2
CaeedigDeadline for receipt by ExA of: • Notification by interested parties of wish to speak at an open floor hearing • Notification by affected parties of wish to speak at a compulsory acquisition hearing • Notification by interested parties of wish to make oral representations at a specific issue hearing on the draft Development Consent Order (DCO)
17 Mai 2013 - Deadline 3
CaeedigFinal notification by ExA of the date, time and place for: • Open floor hearing(s) • Accompanied site visit • Issue specific hearing on the DCO
29 Mai 2013 - Deadline 4
CaeedigDeadline for receipt by ExA of: • Written representations (WR) by all interested parties • Summaries of all WRs exceeding 1500 words • Responses to ExA’s first written questions
12 Mehefin 2013 - Deadline 5
CaeedigDeadline for receipt by ExA of: • Statements of common ground • Comments on WRs and comments on RRs • Local impact reports (LIR) from the local authorities • Comments on responses to ExA’s first written questions • Any proposed amendments to the draft DCO
19 Mehefin 2013 - Site Visit (Accompanied)
CaeedigASV - all day
19 Mehefin 2013 - Open Floor Hearing
CaeedigEvening open floor hearing
20 Mehefin 2013 - Issue Specific Hearing 1
Caeedighearing on draft DCO
21 Mehefin 2013 - Deadline 6
CaeedigNotification by ExA of date, time and place of: • Compulsory acquisition hearing(s) • Any issue specific hearings (in the event that the ExA decides during the progress of the examination that they are needed)
26 Mehefin 2013 - Deadline 7
CaeedigIssue of ExA’s request for further information in the letter to IPs dated 26 June 2013
3 Gorffennaf 2013 - Deadline 8
CaeedigDeadline for receipt by ExA of: • Comments on LIRs • Any written summary of the oral cases put at the DCO hearing • Submissions as to whether there should be oral questioning by another person at any compulsory acquisition or issue specific hearings (if these are to be held)
17 Gorffennaf 2013 - Deadline 9
CaeedigDeadline for receipt by the ExA of any further proposed amendments by the applicant to the draft DCO
23 Gorffennaf 2013 - Compulsory Acquisition Hearing
CaeedigCA hearing
24 Gorffennaf 2013 - Issue Specific Hearing 2
CaeedigLandscape and Ecology ISH
31 Gorffennaf 2013 - Deadline 10
CaeedigDeadline for receipt by the ExA of responses to the ExA’s request for further information issued on 26 June 2013
7 Awst 2013 - Deadline 11
CaeedigDeadline for receipt by the ExA of: • Any written summary of the oral cases put at the compulsory acquisition hearing • Any written summary of the oral cases put at the open floor hearing
8 Awst 2013 - Deadline 12
CaeedigIssue by the ExA of any further written questions and the matrices to inform the Report on the Implications for European Sites (RIES)
14 Awst 2013 - Deadline 13
CaeedigDeadline for receipt by the ExA of comments on responses to the ExA’s request for further information issued on 26 June 2013 (please note that the deadline for the response to the request in 31 July 2013)
29 Awst 2013 - Deadline 14
CaeedigDeadline for receipt by the ExA of responses to the matrices to inform the RIES
4 Medi 2013 - Deadline 15
CaeedigDeadline for receipt by the ExA of: • Final draft DCO • Responses to any further written questions issued by the ExA
11 Medi 2013 - Issue Specific Hearing 3
Caeedig2nd DCO hearing
18 Medi 2013 - Deadline 16
CaeedigDeadline for receipt by ExA of: • Comments on responses to any further written questions • Any written summary of the oral cases put at the second DCO hearing
25 Medi 2013 - Deadline 17
CaeedigDeadline for receipt by ExA of: • Final comments on draft DCO of 4 September 2013 • A revised version of the final draft DCO
2 Hydref 2013 - Deadline 18
CaeedigDeadline for receipt by the ExA of: • Comments on the revised version of the final draft DCO
4 Hydref 2013 - Deadline 19
CaeedigIssue of ExA’s request for further information in the letter to the parties dated 04 October 2013.
10 Hydref 2013 - Deadline 20
CaeedigDeadline for receipt by the ExA of: • Responses to the ExA’s request for further information (dated 04 October 2013).