Stafford Area Improvements - Norton Bridge Railway Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 18 April 2013

Caeodd yr archwiliad ar 14 October 2013

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

18 Ebrill 2013 - Preliminary Meeting

Caeedig

Preliminary meeting

30 Ebrill 2013 - Deadline 1

Caeedig

Issue of: • Procedural timetable • Examining Authority’s (ExA) first written questions

15 Mai 2013 - Deadline 2

Caeedig

Deadline for receipt by ExA of: • Notification by interested parties of wish to speak at an open floor hearing • Notification by affected parties of wish to speak at a compulsory acquisition hearing • Notification by interested parties of wish to make oral representations at a specific issue hearing on the draft Development Consent Order (DCO)

17 Mai 2013 - Deadline 3

Caeedig

Final notification by ExA of the date, time and place for: • Open floor hearing(s) • Accompanied site visit • Issue specific hearing on the DCO

29 Mai 2013 - Deadline 4

Caeedig

Deadline for receipt by ExA of: • Written representations (WR) by all interested parties • Summaries of all WRs exceeding 1500 words • Responses to ExA’s first written questions

12 Mehefin 2013 - Deadline 5

Caeedig

Deadline for receipt by ExA of: • Statements of common ground • Comments on WRs and comments on RRs • Local impact reports (LIR) from the local authorities • Comments on responses to ExA’s first written questions • Any proposed amendments to the draft DCO

19 Mehefin 2013 - Site Visit (Accompanied)

Caeedig

ASV - all day

19 Mehefin 2013 - Open Floor Hearing

Caeedig

Evening open floor hearing

20 Mehefin 2013 - Issue Specific Hearing 1

Caeedig

hearing on draft DCO

21 Mehefin 2013 - Deadline 6

Caeedig

Notification by ExA of date, time and place of: • Compulsory acquisition hearing(s) • Any issue specific hearings (in the event that the ExA decides during the progress of the examination that they are needed)

26 Mehefin 2013 - Deadline 7

Caeedig

Issue of ExA’s request for further information in the letter to IPs dated 26 June 2013

3 Gorffennaf 2013 - Deadline 8

Caeedig

Deadline for receipt by ExA of: • Comments on LIRs • Any written summary of the oral cases put at the DCO hearing • Submissions as to whether there should be oral questioning by another person at any compulsory acquisition or issue specific hearings (if these are to be held)

17 Gorffennaf 2013 - Deadline 9

Caeedig

Deadline for receipt by the ExA of any further proposed amendments by the applicant to the draft DCO

23 Gorffennaf 2013 - Compulsory Acquisition Hearing

Caeedig

CA hearing

24 Gorffennaf 2013 - Issue Specific Hearing 2

Caeedig

Landscape and Ecology ISH

31 Gorffennaf 2013 - Deadline 10

Caeedig

Deadline for receipt by the ExA of responses to the ExA’s request for further information issued on 26 June 2013

7 Awst 2013 - Deadline 11

Caeedig

Deadline for receipt by the ExA of: • Any written summary of the oral cases put at the compulsory acquisition hearing • Any written summary of the oral cases put at the open floor hearing

8 Awst 2013 - Deadline 12

Caeedig

Issue by the ExA of any further written questions and the matrices to inform the Report on the Implications for European Sites (RIES)

14 Awst 2013 - Deadline 13

Caeedig

Deadline for receipt by the ExA of comments on responses to the ExA’s request for further information issued on 26 June 2013 (please note that the deadline for the response to the request in 31 July 2013)

29 Awst 2013 - Deadline 14

Caeedig

Deadline for receipt by the ExA of responses to the matrices to inform the RIES

4 Medi 2013 - Deadline 15

Caeedig

Deadline for receipt by the ExA of: • Final draft DCO • Responses to any further written questions issued by the ExA

11 Medi 2013 - Issue Specific Hearing 3

Caeedig

2nd DCO hearing

18 Medi 2013 - Deadline 16

Caeedig

Deadline for receipt by ExA of: • Comments on responses to any further written questions • Any written summary of the oral cases put at the second DCO hearing

25 Medi 2013 - Deadline 17

Caeedig

Deadline for receipt by ExA of: • Final comments on draft DCO of 4 September 2013 • A revised version of the final draft DCO

2 Hydref 2013 - Deadline 18

Caeedig

Deadline for receipt by the ExA of: • Comments on the revised version of the final draft DCO

4 Hydref 2013 - Deadline 19

Caeedig

Issue of ExA’s request for further information in the letter to the parties dated 04 October 2013.

10 Hydref 2013 - Deadline 20

Caeedig

Deadline for receipt by the ExA of: • Responses to the ExA’s request for further information (dated 04 October 2013).