Redditch Branch Enhancement Scheme Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 7 January 2013

Caeodd yr archwiliad ar 30 May 2013

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

7 Ionawr 2013 - Preliminary Meeting

Caeedig

Held at Alvechurch village hall

15 Ionawr 2013 - Deadline 1

Caeedig

Issue of:

  • Procedural timetable
  • Examining Authority’s (ExA) first written questions

4 Chwefror 2013 - Deadline 2

Caeedig

Deadline for reciept by the ExA of:

  • Notification by interested parties of wish to speak at an open floor hearing -Notification by affected persons of wish to speak at a compulsory scquisition hearing -Notification by interested parties of wish to make oral representations at a specific issue hearing on the draft Development Consent Order (DCO

11 Chwefror 2013 - Deadline 3

Caeedig

Notification by the ExA of date, time and place for:

  • Open floor hearing (s)
  • Accompanied Site Visit
  • Issue specific hearings on the DCO

12 Chwefror 2013 - Deadline 4

Caeedig

Deadline for receipt by the ExA of:

  • Comments on Relevant Representations (RRs)
  • Summaries of all RRs exceeding 1500 words
  • Written Representations (WRs) by all interested parties
  • Summaries of all WRs exceeding 1500 words
  • Local Impact Reports (LIR) from any local authorities
  • Response to the ExA's first written questions
  • Comments on LIRs
  • Comments on responses to the ExA's first written questions

7 Mawrth 2013 - Deadline 5

Caeedig

Deadline for reciept by the ExA of:

  • Statements of Common Ground
  • Comments on WRs and responses to comments on RRs
  • Comments on LIRs
  • Comments on responses to ExA's first written questions
  • Any proposed amendments to the draft DCO

13 Mawrth 2013 - Site Visit (Accompanied)

Caeedig

accompanied site visit

13 Mawrth 2013 - Open Floor Hearing 1

Caeedig

Open floor hearing - afternoon and possibly evening

13 Mawrth 2013 - Open Floor Hearing 2

Caeedig

Open Floor Hearing

15 Mawrth 2013 - Issue Specific Hearing 1

Caeedig

DCO hearing

20 Mawrth 2013 - Deadline 6

Caeedig

Notification by the ExA of the date, time and place of:

  • Compulsory acquisition hearing(s)
  • Any issue specific hearings (in the event the ExA decides during the progress of examination that they are needed)

22 Mawrth 2013 - Deadline 7

Caeedig

Rule 17 request for: Network Rail and Barnt Green Parish Council to respond to questions asked in ExA's letter of 14 March 2013.

5 Ebrill 2013 - Deadline 8

Caeedig

Rule 17 request for: Network Rail to respond to Ramblers Association's submission

16 Ebrill 2013 - Compulsory Acquisition Hearing

Caeedig

CA hearing

17 Ebrill 2013 - Issue Specific Hearing 2

Caeedig

Reserved for ISH

18 Ebrill 2013 - Issue Specific Hearing 3

Caeedig

Reserved for ISH

2 Mai 2013 - Deadline 9

Caeedig

Issue by ExA of any further written questions

9 Mai 2013 - Deadline 10

Caeedig

Rule 17 request for: Submission by the applicant of the final revision of the draft Development Consent Order, Explanatory Memorandum, Book of Reference and responses to ExA's request for further information set out in Annex A to letter.

16 Mai 2013 - Deadline 11

Caeedig

Deadline for reciept by ExA of:

  • Responses to any further written questions issued by the ExA
  • Any proposed amendments by the applicant to the draft DCO

28 Mai 2013 - Deadline 12

Caeedig

Rule 17 request for:

  • Submission of comments by all interested parties on the documents submitted on 9 May 2013 only.

29 Mai 2013 - Deadline 13

Caeedig

Close of Examination (subject to the ExA's review of comments submitted)

10 Mehefin 2013 - Deadline 14

Caeedig

Deadline for reciept of ExA of:

  • Comments on responses to any further written questions

8 Gorffennaf 2013 - Deadline 15

Caeedig

Deadline for close of examination