Y cam archwilio
Agorodd yr archwiliad ar 27 February 2019
Caeodd yr archwiliad ar 27 August 2019
27 Chwefror 2019 - Preliminary Meeting
CaeedigPreliminary Meeting
27 Chwefror 2019 - Open Floor Hearing 1
CaeedigFirst Open Floor Hearing
27 Chwefror 2019 - Open Floor Hearing 2
CaeedigSecond Open Floor Hearing
28 Chwefror 2019 - Issue Specific Hearing 1 on the Draft DCO
CaeedigFirst Issue Specific Hearing, on the Draft Development Consent Order
13 Mawrth 2019 - Deadline 1
CaeedigDeadline 1, for receipt of: • Post-Hearing submissions and written submissions of oral case
5 Ebrill 2019 - Deadline 2
CaeedigDeadline 2, for receipt of: • Comments on Relevant Representations (RRs) • Summaries of all RRs exceeding 1500 words • Written Representations (WRs) • Summaries of all WRs exceeding 1500 words • Local Impact Reports from any local authorities • Statements of Common Ground (SoCG) requested by the ExA • Responses to the ExA’s Written Questions Comments on updated application documents • Responses to further information requested by the ExA • Applicant’s proposed itinerary for an Accompanied Site Inspection • Proposals from other IPs for Accompanied Site Inspection Viewpoints • Notification of wish to speak at a Compulsory Acquisition Hearing or an Open Floor Hearing • Comments on Submissions Made at Deadline 1
24 Ebrill 2019 - Deadline 3
CaeedigDeadline 3, for receipt by the ExA of: • Comments on submissions for deadline 2. • Revised draft DCO from Applicant • Responses to further information requested by the ExA
3 Mehefin 2019 - Time period reserved for hearings
CaeedigTime period reserved for hearings (Week of 3 June 2019)
5 Mehefin 2019 - Compulsory Acquisition Hearing
CaeedigCompulsory Acquisition Hearing
5 Mehefin 2019 - Issue Specific Hearing on Accessibility and Transport
CaeedigIssue Specific Hearing on Accessibility and Transport
6 Mehefin 2019 - Issue Specific Hearing on Environmental Effects
CaeedigIssue Specific Hearing on Environmental Effects
6 Mehefin 2019 - Issue Specific Hearing on the Draft DCO
CaeedigIssue Specific Hearing on the Draft DCO
14 Mehefin 2019 - Deadline 4
CaeedigDeadline 4, for receipt of: • Post hearing submissions including written submissions of oral case
5 Gorffennaf 2019 - Deadline 5
CaeedigDeadline 5, for receipt of: • Responses to the ExA’s Further Written Questions (if required) • Responses to further information requested by the ExA • Applicant’s revised draft DCO and revised/updated Explanatory Memorandum
10 Gorffennaf 2019 - Issue Specific Hearing 5 - Achieving SRFI Objectives
CaeedigAchieving SRFI Objectives: scale, viability, commitment to rail and policy compliance
11 Gorffennaf 2019 - Issue Specific Hearing 6 on the Draft DCO
CaeedigIssue Specific Hearing on the Draft DCO
19 Gorffennaf 2019 - Deadline 6
CaeedigDeadline 6, for receipt of: • Comments on responses to the ExA’s Further Written Questions (if required) • Responses to further information requested by the ExA • Post hearing submissions including written submissions of oral case • Applicant’s final draft DCO and revised/updated Explanatory Memorandum
7 Awst 2019 - Deadline 7
CaeedigDeadline 7, for receipt of: • Comments on the ExA’s schedule of changes to the draft (if required) • Comments on the RIES (if required) • Responses to further information requested by the ExA • Comments on applicant’s final draft DCO
21 Awst 2019 - Deadline 8
CaeedigDeadline 8, for receipt of: • Responses to comments on the ExA’s schedule of changes to the draft DCO (if required) • Responses to comments on the RIES (if required) • Responses to further information requested by the ExA • Final DCO to be submitted by the Applicant in the SI template with the SI template validation report