Agorodd yr archwiliad ar 9 October 2018
Caeodd yr archwiliad ar 9 April 2019
9 Hydref 2018 - Preliminary Meeting
CaeedigPreliminary Meeting
9 Hydref 2018 - Issue Specific Hearing 1 (ISH1)
CaeedigISH1 on the draft Development Consent Order (dDCO)
10 Hydref 2018 - Open Floor Hearing (OFH)
CaeedigOpen Floor Hearing (OFH)
17 Hydref 2018 - Issue by the Examining Authority (ExA)
CaeedigIssue by the ExA of: - Examination Timetable - The ExA’s Written Questions
6 Tachwedd 2018 - Deadline 1
CaeedigDeadline for receipt of: - Local Impact Reports from any local authorities - Statements of Common Ground (SoCG) requested by the ExA (except those requested for submission by Deadline 3) - Draft s.106 Agreements and any similar Agreements and allied documents - Responses to the ExA’s Written Questions - Written Representations (WRs) - Summaries of all WRs exceeding 1500 words - Comments on Relevant Representations (RRs) - Summaries of all RRs exceeding 1500 words - Comments on updated application documents submitted by the Applicant before the PM – See Annex E of Rule 8 letter - Post-hearing submissions including written submissions of oral cases - Responses to any further information requested by the ExA for this deadline - Nominations of suggested locations and justifications for site inspections for consideration by the ExA - Notification of wish to attend an Accompanied Site Inspection (ASI) - Draft Itinerary to be provided by the Applicant for an ASI - Notification from any Affected Person of wish to speak at a Compulsory Acquisition Hearing - Notification of wish to speak at any subsequent Issue Specific Hearings (ISH) - Notification of wish to speak at a subsequent Open Floor Hearing (OFH) - Notification by Statutory Parties of their wish to be considered as an Interested Party (IP) by the ExA - Notification of wish to have future correspondence received electronically
20 Tachwedd 2018 - Deadline 2
CaeedigDeadline for receipt by the ExA of: - Revised dDCO from Applicant - Comments on Local Impact Reports - Comments on any SoCG submitted at Deadline 1 - Comments on WRs - Responses to comments on RRs - Comments on responses to the ExA’s Written Questions - Comments on any additional information/ submissions received by Deadline 1 - Responses to any further information requested by the ExA for this deadline
23 Tachwedd 2018 - Issue by the ExA
CaeedigIssue by the ExA of: - Notification of ASI (if required)
30 Tachwedd 2018 - Deadline 3
CaeedigDeadline for receipt by the ExA of: - Statements of Common Ground (SoCG) between: o Applicant and Ashfield Land and Gazeley GLP o Applicant, Ashfield Land and Gazeley GLP and Network Rail – see Procedural Decision (1) Annex B of Rule 8 letter - Comments on the Applicant’s revised dDCO - Comments on any additional information/ submissions received by Deadline 2 - Responses to any further information requested by the ExA for this deadline
18 Rhagfyr 2018 - Accompanied Site Inspection (ASI)
CaeedigDate reserved to hold an ASI (if required)
19 Rhagfyr 2018 - Issue Specific Hearing (ISH2)
CaeedigIssue Specific Hearing (ISH2) ISH2 on Environmental matters including Transport, Landscape & Visual, Ecology, Air Quality and Other matters
20 Rhagfyr 2018 - Issue Specific Hearing (ISH3)
CaeedigIssue Specific Hearing (ISH3) ISH3 on the dDCO
20 Rhagfyr 2018 - Compulsory Acquisition Hearing (CAH)
CaeedigCompulsory Acquisition Hearing
8 Ionawr 2019 - Deadline 4
CaeedigDeadline for receipt of: - Comments on SoCG submitted for D3 - Any revised dDCO from the Applicant - Post-hearing submissions including written submissions of oral cases - Comments on any additional information/ submissions received by Deadline 3 - Responses to any further information requested by the ExA for this deadline
5 Chwefror 2019 - Publication by ExA
CaeedigPublication by ExA of: - The ExA’s Further Written Questions (if required) - The ExA’s preferred dDCO or dDCO commentary (if required) - Report on the Implications for European Sites (RIES) (if required)
26 Chwefror 2019 - Deadline 5
CaeedigDeadline for receipt of: - Responses to Further Written Questions (if issued) - Comments on the ExA’s preferred dDCO or dDCO commentary (if issued) - Comments on the RIES (if issued) - Comments on any additional information/ submissions received by Deadline 4 - Responses to any further information requested by the ExA for this deadline
12 Mawrth 2019 - Issue Specific Hearing (ISH4)
CaeedigIssue Specific Hearing (ISH4) Date reserved to hold ISH4 on Cumulative Impact and interaction Issues
13 Mawrth 2019 - Issue Specific Hearing (ISH5)
CaeedigIssue Specific Hearing (ISH5) Date reserved to hold ISH5 on the dDCO (if required)
13 Mawrth 2019 - Compulsory Acquisition Hearing 2
CaeedigCompulsory Acquisition Hearing 2 Date reserved to hold CAH2 (if required)
14 Mawrth 2019 - Open floor Hearing 2 (OFH2)
CaeedigDate reserved to hold OFH2
19 Mawrth 2019 - Deadline 6
CaeedigDeadline for receipt of: - Final draft DCO to be submitted by the Applicant in the SI template with the SI template validation report - Final s.106 Agreements and any similar Agreements and allied documents - Final SoCG - Post-hearing submissions including written submissions of oral cases - Comments on responses to the ExA’s Further Written Questions (if required) - Comments on any additional information/ submissions received by Deadline 5 - Responses to any further information requested by the ExA for this deadline
26 Mawrth 2019 - Deadline 7
CaeedigDeadline for receipt of: - Comments on the Applicant’s final dDCO - Comments on final s.106 Agreements and any similar Agreements and allied documents - Comments on final SoCG - Comments on any additional information/ submissions received by Deadline 6 - Responses to any further information requested by the ExA for this deadline
3 Ebrill 2019 - Deadline 8
CaeedigDeadline for receipt of: - Responses to any further information requested by the ExA for this deadline
5 Ebrill 2019 - Deadline 9
CaeedigDeadline for receipt of: - Comments on any additional information/ submissions received by Deadline 8
9 Ebrill 2019 - Close of Examination
CaeedigThe ExA is under a duty to complete the examination of the application by the end of the period of six months beginning with the day after the close of the Preliminary Meeting.