Thames Tideway Tunnel Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 12 September 2013

The examination closed on 12 March 2014

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

12 September 2013 - Preliminary Meeting

Closed

Meeting to discuss the procedure for examining the application

23 September 2013 - Deadline 1

Closed

Deadline for receipt by the ExA of: Submission by the Applicant of the proposed changes. Such submissions to include all consequential changes of for example: Land Plans; the Book of Reference; Statement of Reasons and environmental information Submission by Applicant of all documents relating to the Applicant’s proposed corrections and omissions to the application including all environmental information and other supporting information Statutory Parties (SP) written confirmation that they wish to be considered as an Interested Party (IP) Persons in certain categories with interests in land written request to the ExA to become an IP (using the prescribed form)39 Submission by any SP or IP of corrections and omissions in relation to a Relevant Representation or for a SP who wishes to be considered as an IP an initial submission about the application. This includes the initial submission details by IPs who advised in their Relevant Representation that additional information would be provided Any representations relating to locations to view at or near the site and in the surrounding area that IPs consider are important and relevant for the ExA to better understand representations made or to see land and interests where there is no other opportunity to gain public access. Notification of wish by IPs to make oral representations on the specific issue or issues being examined at an Issue Specific (IS) hearing, relating to the rationale for the selection of work sites and drive strategies Notification of wish to be heard at an open floor (OF) hearing by IPs and any representation about the potential location of such hearings Notification of wish to be heard at a Compulsory Acquisition (CA) hearing by Affected Persons (APs) Notification of wish by IPs to make oral representations on the specific issue or issues being examined at identified IS hearings, relating to the draft development consent order (DCO), requirements,any s106 undertaking and related LIR matters

26 September 2013 - Deadline 2

Closed

Issue by the ExA of: Procedural timetable First written questions First request for Statements of Common Ground (SoCG) Note of preliminary meeting Publication by the Planning Inspectorate of the Applicant’s proposed changes

3 October 2013 - Deadline 3

Closed

Availability of Applicant’s proposed corrections/omissions and other IP or SP submissions for public inspection at notified locations

7 October 2013 - Deadline 4

Closed

Deadline for any written submissions on whether the Applicant’s changes as submitted are substantial and whether they would amount to a different application. Any submissions should set out the reasoning for any response

15 October 2013 - Deadline 5

Closed

The ExA’s decision on whether the Applicant’s proposed changes will be accepted will be notified to Parties by publication on the Planning Inspectorate, National Infrastructure, Thames Tideway Tunnel project page of the Planning Portal website Issue of final notification by the ExA of date, time and place for: OF hearings Three IS hearings relating to the draft development consent order (DCO), requirements, any s106 undertaking and related LIR matters CA hearings and Statutory Undertaker and special category land hearings IS hearing relating to the rationale for the selection of work sites and drive strategies matters Accompanied site visit to limited access sites

29 October 2013 - Site Visit (Accompanied) 1

Closed

Accompanied site visit on 29 October 2013

4 November 2013 - Deadline 6

Closed

Deadline for receipt by the ExA of: Comments on Relevant Representations (RRs) For any RRs or initial submissions that exceeded 1500 words a summary should be provided Comments on any omissions, errata or supplementary information submitted for the September deadline Written Representations (WRs) by all IPs Any summaries of WRs, for WRs that exceed 1500 words Local Impact Report (LIR) by all local authorities Responses to ExA’s first written questions SoCG requested on or before Thursday 26 September 2013 Any draft s106 agreements or other agreements or programmes Any submissions in relation to Statutory Undertakers’ land (s127 pa 2008) and extinguishment of rights, and removal of apparatus, of Statutory Undertakers etc. (s138 pa 2008) Any written confirmation required from the Crown in relation to s135 PA 2008 providing documentary confirmation that no interests are engaged and/or the Crown authority consents

11 November 2013 - Issue Specific Hearing 1

Closed

Introductory Session Carnwarth Road Riverside and alternative drive strategy, followed by Barn Elms and Putney

12 November 2013 - Issue Specific Hearing 2

Closed

Chambers Wharf and Alternative Drive Strategy

13 November 2013 - Issue Specific Hearing 3

Closed

Deptford Church Street

14 November 2013 - Issue Specific Hearing 4

Closed

King Edward Memorial Park

15 November 2013 - Issue Specific Hearing 5

Closed

Other submissions on alternative sites proposed by interested parties

19 November 2013 - Open Floor Hearing 1

Closed

Open Floor Hearing

20 November 2013 - Open Floor Hearing 2

Closed

Open Floor Hearing

21 November 2013 - Open Floor Hearing 3

Closed

Open Floor Hearing

22 November 2013 - Open Floor Hearing 4

Closed

Open Floor Hearing

23 November 2013 - Open Floor Hearing 5

Closed

Open Floor Hearing

26 November 2013 - Deadline 7

Closed

Deadline for receipt by the ExA of: Written summaries of the cases put orally at the hearings held on and between Monday 11 and Saturday 23 November 2013

26 November 2013 - Issue Specific Hearing 6

Closed

First hearing on the DCO requirements, any s106 undertakings and related LIR matters

27 November 2013 - Issue Specific Hearing 7

Closed

Issue Specific Hearings

28 November 2013 - Compulsory Acquisition Hearing 1

Closed

Compulsory Acquisition Hearing

29 November 2013 - Compulsory Acquisition Hearing 2

Closed

Compulsory Acquisition Hearings

2 December 2013 - Deadline 8

Closed

Deadline for receipt by the ExA of: Written summaries of the cases put orally at the hearings held on and between Tuesday 26 and Wednesday 27 November 2013 Comments on WRs and responses to comments on RRs Comments on LIRs Comments on responses to first written questions and initial requested and first requested SoCG Comments on any submissions in relation to Statutory Undertakers’ land (s127 pa 2008) and extinguishment of rights, and removal of apparatus of Statutory Undertakers etc. (s138 pa 2008)

3 December 2013 - Compulsory Acquisition Hearing 3

Closed

Compulsory Acquisition Hearing

4 December 2013 - Compulsory Acquisition Hearing 4

Closed

Compulsory Acquistion Hearing

5 December 2013 - Compulsory Acquisition Hearing 5

Closed

Compulsory Acquisition Hearing

6 December 2013 - Compulsory Acquisition Hearing 6

Closed

Compulsory Acquisition Hearings

10 December 2013 - Compulsory Acquisition Hearing 7

Closed

Compulsory Acquisition Hearing

11 December 2013 - Compulsory Acquisition Hearing 8

Closed

Compusory Acquisition Hearings

12 December 2013 - Compulsory Acquisition Hearing 9

Closed

Compulsory Acquisition Hearing

13 December 2013 - Compulsory Acquisition Hearing 10

Closed

Compulsory Acquisition Hearings

17 December 2013 - Compulsory Acquisition Hearing 11

Closed

Compulsory Acquisition Hearings

18 December 2013 - Compulsory Acquisition Hearing 12

Closed

Compulsory Acquisition Hearings

19 December 2013 - Deadline 9

Closed

Issue by the ExA of: Second written questions Second requested SoCG Issue of final notification by the ExA of date, time and place for: The accompanied site visit In the event that the ExA decides during the progress of the examination that they are needed, any other: OF hearings IS hearings CA hearings and Statutory Undertaker and special category land hearings

19 December 2013 - Compulsory Acquisition Hearing 13

Closed

Compulsory Acquisition Hearings

20 December 2013 - Compulsory Acquisition Hearing 14

Closed

Compulsory Acquisition Hearings

23 December 2013 - Deadline 10

Closed

Deadline for receipt by the ExA of: Written summaries of the cases put orally at the hearings held on and between Thursday 28 November and Friday 20 December 2013

13 January 2014 - Deadline 11

Closed

Deadline for receipt by the ExA of: Responses to ExA’s second written questions Second requested SoCG Any draft s106 agreements or other agreements or programmes

14 January 2014 - Compulsory Acquisition Hearing 15

Closed

Compulsory Acquisition Hearings

15 January 2014 - Compulsory Acquisition Hearing 16

Closed

Compulsory Acquisition Hearing

16 January 2014 - Compulsory Acquisition Hearing 17

Closed

Compulsory Acquisition Hearing

17 January 2014 - Compulsory Acquisition Hearing 18

Closed

Compulsory Acquistion Hearing, Glaziers Hall

20 January 2014 - Deadline 12

Closed

Deadline for receipt by the ExA of: Any written summaries of the cases put orally at the hearings held on and between Tuesday 14 and Friday 17 January 2014

20 January 2014 - Issue Specific Hearing 8

Closed

Second hearing on the DCO requirements, any s106 undertakings and related LIR matters

21 January 2014 - Deadline 13

Closed

Publication by the ExA of any: Report on the Implications for European Sites (RIES) for consultation

21 January 2014 - Issue Specific Hearing 9

Closed

Issue Specific Hearing

22 January 2014 - Issue Specific Hearing 10

Closed

Issue specific hearing on site selection and drive strategy

23 January 2014 - Issue Specific Hearing 11

Closed

Issue Specific Hearing on site selection and drive strategy

24 January 2014 - Issue Specific Hearing 12

Closed

Issue Specific Hearing on Traffic and Transport

27 January 2014 - Compulsory Acquisition Hearing 19

Closed

Compulsory Acquisition Hearing

28 January 2014 - Compulsory Acquisition Hearing 20

Closed

Compulsory Acquistion Hearing

29 January 2014 - Open Floor Hearing 6

Closed

Open Floor Hearing

29 January 2014 - Site Visit (Accompanied) 2

Closed

Accompanied site visit on the 29 - 31 January

30 January 2014 - Open Floor Hearing 7

Closed

Open Floor Hearing

3 February 2014 - Deadline 14

Closed

Deadline for receipt by the ExA of: Comments on responses to second written questions and second requested SoCG Written summaries of the cases put orally at any hearings held on and between Monday 20 and Tuesday 28 January 2014

3 February 2014 - Open Floor Hearing 8

Closed

Open Floor Hearing

4 February 2014 - Issue Specific Hearing 13

Closed

Issue Specific Hearing on Noise and Vibration

5 February 2014 - Open Floor Hearing 9

Closed

Open Floor Hearing

5 February 2014 - Open Floor Hearing 10

Closed

Open Floor Hearing

6 February 2014 - Issue Specific Hearing 14

Closed

Third hearing on the DCO requirements, any s106 undertaking and related LIR matters

12 February 2014 - Deadline 15

Closed

Deadline for receipt by the ExA of: Written summaries of the cases put orally at any hearings held on and between Monday 3 and Friday 7 February 2014 Any outstanding SoCG Completed s106 and any other agreements or programmes to be taken into account by the ExA and Secretary of State Any final written confirmation required from the Crown in relation to s135 PA 2008 providing documentary confirmation that no interests are engaged and/or the Crown authority consents Updated draft DCO Consultation response to any RIES published by the ExA.

20 February 2014 - Deadline 16

Closed

Publication by the ExA of: Any outstanding submitted SoCG Completed s106 and any other agreements or programmes Updated draft DCO in the final form that the Applicant wishes it to be made Responses to any RIES consultation. Issue by the ExA of: Any request for additional information by the ExA Request for comments on the published documentation

20 February 2014 - Issue Specific Hearing 15

Closed

Resumption of adjourned IS hearing noise and vibration

21 February 2014 - Issue Specific Hearing 16

Closed

Resumption of adjourned third IS hearing on the draft DCO and related matters

27 February 2014 - Site Visit (Accompanied) 3

Closed

Accompanied site visit to St Paul's Church Deptford (rescheduled as the church and grounds were being used during the time of the previous accompanied site visit to Deptford)

3 March 2014 - Deadline 17

Closed

Deadline for receipt by the ExA of: Comments on any outstanding submitted SoCG Comments on any submitted completed s106 and any other agreements to be taken into account by the ExA and Secretary of State Comments on any updated draft DCO Comments on any responses to RIES consultation Any final written submissions by any IP or SP

11 March 2014 - Deadline 18

Closed

All final written responses from the Applicant, any Interested Party, Affected Person or Statutory Party

12 March 2014 - Deadline 19

Closed

The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the last day of the preliminary meeting