Yn dangos 176 i 200 o 727 o gofnodion, gyda’r rhai mwyaf newydd yn gyntaf.
Canlyniadau fesul tudalen 25 | View 50 results per page | View 100 results per page
-
Gweld cyngor i Jamie Macnamara
What are the rules governing applicants in DCO processes in the following specific circumstances; · Application is at pre-application stage (Scoping Report submitted) and is currently progres... Darllen mwy
-
Gweld cyfarfod gyda Highways England
Project Update Meeting
-
Gweld cyfarfod gyda Norfolk County Council
To provide an overview of the Planning Act 2008 process to the A47 Alliance Steering Group Meeting
-
Gweld cyfarfod gyda Highways England
Project Update Meeting
-
Gweld cyfarfod gyda Heathrow Airport Ltd
Project update meeting.
-
Gweld cyngor i ATKINS
I understand that an application for a DCO makes provision for developers to detail other consents etc that are required under legislation other than the 2008 Act. Certain prescribed consents can be c... Darllen mwy
-
Gweld cyngor i Strutt & Parker LLP
I had a quick enquiry in respect of nationally significant infrastructure projects which I was hoping you may be able to assist with. I assume that in preparation of a planning application, a screenin... Darllen mwy
-
Gweld cyngor i Bean Residents Association
Can you tell us if the above Highways England project has been accepted as a NSIP? Ii is currently subject to ‘informal’ Public Consultation (18th Jan to 1st March 2017). HE Scheme Milestones show... Darllen mwy
-
Gweld cyngor i Pegasus Planning
Can solar farm applications in England and Scotland fall under the remit of the Planning Act 2008.
-
Gweld cyfarfod gyda Heathrow Strategic Planning Group
The Planning Inspectorate were invited to give a presentation to the HSPG about the Planning Act 2008 process.
-
Gweld cyngor i Gowling WLG
The enquirer requested to view the Book of Reference associated with The Daventry International Rail Freight Interchange Alteration Order 2014.
-
Gweld cyngor i Andrew Troupe
Planning permission has been granted for a new battery storage facility in South Oxfordshire with a capacity of more than 50MW - does this mean that battery storage is not regarded as a form of energy... Darllen mwy
-
Gweld cyfarfod gyda Heathrow Airport Ltd
Project update meeting.
-
Gweld cyfarfod gyda Highways England
A303 Amesbury to Berwick Down (Stonehenge) Project Update Meeting
-
Gweld cyfarfod gyda Highways England
A428 Black Cat to Caxton Gibbet - Introduction Meeting
-
Gweld cyfarfod gyda Storelectric
Meeting regarding a possible NSIP project
-
Gweld cyfarfod gyda Suffolk County Council
Lake Lothing Third Crossing Introduction Meeting
-
Gweld cyngor i Canal and River Trust
Since S160 of the Housing & Planning Act allowed for residential development to be included in NSIPs to an extent, have there been changes to your website content and any guidance around this at all? ... Darllen mwy
-
Gweld cyfarfod gyda Highways England
A2 Bean to Ebbsfleet project update meeting
-
Gweld cyfarfod gyda Statera Energy Ltd
Meeting regarding possible battery storage projects
-
Gweld cyfarfod gyda Suffolk County Council
Project introduction – Upper Orwell Crossings
-
Gweld cyngor i Natural Power
Dear Sir/Madam, I am enquiring who would determine an onshore wind project located in Wales with a capacity of 50 MW. Would this be an NSIP project and determined by Planning Inspectorate, as all ... Darllen mwy
-
Gweld cyngor i DJ Lee
Can I begin the process of applying for a Development Consent Order for the development of a Geological Disposal Facility for Higher Activity Radioactive Wastes from The UK's Civil Nuclear industry an... Darllen mwy
-
Gweld cyfarfod gyda Highways England
A47 Project Update Meeting
-
Gweld cyngor i Pegasus Group
I am looking for a timeline chart that shows the NSIP process stages, and the length of anticipated time to complete each one. I recall a thirty-odd page document setting out the details of the pr... Darllen mwy