Hinkley Point C New Nuclear Power Station

Section 51 advice

The list below includes a record of advice we have provided for this project.

There is a statutory duty, under section 51 of the Planning Act 2008, around an application or potential application. This includes recording the name of the person who requested advice and the advice given. This information has to be made publicly available.

Search advice

Search by key words or the name of person the advice was given to.

Showing 51 to 75 of 120 documents, newest first.

Results per page 25 | View 50 results per page | View 100 results per page

  • View advice to The Power Trust

    Correspondence dated ?November 2011? has been received from ?The Power Trust? without an address for return correspondence. The correspondence is titled ?Advance Briefing for IPC Commissioners and Ass... Read more

  • View advice to East Huntspill & Puriton PCs

    I wish to register my Parish Councils' interest in this project

  • View advice to Judith Finsland

    Comments were supplied regarding the scheme and EDF's consultation. It was also queried why the IPC was to consult Exmoor National Park Authority, but not Cannington Parish Council.

  • View advice to Daniel Viesnik

    I must say that I find it entirely unsatisfactory that you are unable to inform individuals when the registration process opens, and that one is required to scan all the national and local papers on a... Read more

  • View advice to BNP Paribas

    Query regarding the Royal Mail's status as a statutory consultee and the process relating to making an objection to the IPC regarding the Hinkley Point C scheme.

  • View advice to Clerk to Williton Parish Council

    Further to your joint letter from SCC, SDC and WSC dated 5th October regarding the above we would like to register our interest and be kept informed of developments. I have tried to register online on... Read more

  • View advice to Richard Oerton

    I wish to register and make representations in regard to the application for development at Hinkley Point. I appreciate that I cannot do this until the IPC has accepted the application but (assuming t... Read more

  • View advice to Daniel Viesnik

    It appears from the webpage below that the Hinkley C application has been accepted by the IPC for consideration. I would like to please be kept informed of the date from which one can register to make... Read more

  • View advice to Marion Orton

    The caller queried their inability to submit a relevant representation for the Hinkley Point C application via the IPC website.

  • View advice to Sheila Allen

    I have been asked by many residents who are not on line to seek clarification that, now that EDF have submitted their application and, if accepted by the IPC in the 28 day period, is it during this 2... Read more

  • View advice to Clerk to Durleigh PC

    Can you provide me with information on how to register Durleigh Parish Council's interest in this project?

  • View advice to Cannington Parish Council

    Ms Valerie Bannister of Cannington Parish Council telephoned; she asked whether the Parish Council and other interested parties could write directly to the IPC with regards to the adequacy of consulta... Read more

  • View advice to EDF

    Advice sought regarding EIA regulation 24 Transboundary Impacts

  • View advice to Sedgemoor District Council

    The Council would like to have a full copy of the application at the same time as it is submitted to the IPC, to enable it to make an adequacy statement. What would happen if the Council was not ab... Read more

  • View advice to Tim Jones

    I would like to register to be able to put my views when an application for Hinkley Point C is submitted or if it has already been submitted.

  • View advice to TLT Solicitors

    Mr Silk called to ask which part or parts of the book of reference a party with a very specific intrest in land would best be included in.

  • View advice to NNB Genco (EDF)

    Are developers required to submit a full copy of the application to a local authority at the same time as it is submitted to the IPC? Is it appropriate for local authorities to publish the applicat... Read more

  • View advice to Sheila Allen

    Will the time we can register/write to the IPC regarding Hinkley Point C be published in local newspapers for those without computers?

  • View advice to Nether Stowey Parish Council

    Mr Ensor telephoned the IPC to ask how representatives of Parish Councils can make relevant representations on behalf of their organisations. Our response was by telephone.

  • View advice to David Gillam

    Mr Gillam asked to be kept advised of the submission date of the forthcoming application for a generating station at Hinkley Point, and the period for making relevant representations.

  • View advice to D C W Johnson

    DCW Johnson commented on concerns about the development of Combwich Wharf during the proposed Hinkley Point C project.

  • View meeting with Nick Matthews

    Meeting held to discuss the proposed Hinkley Point 'C' project

  • View meeting with Stockland Bristol Parish Council

    meeting to provide advice about the process and making a representation.

  • View advice to Avon and Sommerset Police

    Mr Adieze, a legal adviser at Avon and Somerset Police,(ASP) called to ask whether any submissions on the detail of planning obligations accompanying any application for a generating station at Hinkle... Read more

  • View meeting with Alyn Jones

    Meeting with Somerset County Council, West Somerset District Council and sedgemoor District Council to disucss the proposed Hinkley Point 'C' project