1. Section 51 advice
  2. Advice in detail

Advice to Leigh Redman

Back to list

Enquiry

From
Leigh Redman
Date advice given
27 November 2017
Enquiry type
Email

Hi thank you for the response, for clarity:-

The consultees to non material changes do not include interested or registered persons from the full formal process? Who are the required consultees? How do i register to receive or be made aware of any published item on the HPC inspectors page? Increasing the size of a building by some 50% to form one of the largest building on site and major changes to the sea wall are not seen as a material change?

Thank you for your time.

Advice given

Thank you for your email. I will attempt to answer your questions. The answers to questions 1 and 2 are found in regulation 7 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations (as amended).

http://www.legislation.gov.uk/uksi/2011/2055/contents/made

The copy on legislation.gov.uk does not include the amendments made in 2015:

https://www.legislation.gov.uk/uksi/2015/760/contents/made

  1. Parties who registered as interested parties are not automatically consulted on a proposed non-material change.

  2. The required consultees are each person for whose benefit the development consent order has effect; each person that was notified of the acceptance of the original application for a Development Consent Order by the applicant under S56 of the Planning Act 2008; and any other person who may be directly affected by the changes proposed in the application. This is subject to a provision that allows the Secretary of State to consent to a shorter list of consultees on a case-by-case basis. By way of an example, please see this letter here:

https://infrastructure.planninginspectorate.gov.uk/wp-content/ipc/uploads/projects/EN010001/EN010001-006521-1.BEIS%20Letter%20to%20EDF%20Energy.pdf

  1. There is no way to register to be informed directly every time a document is published on our website.

  2. This is a matter for the Secretary of State. The decision on the application will include a decision on whether or not the proposed change is material.

As I mentioned below, there is guidance on changes to development consent orders, which can be found here:

https://www.gov.uk/government/publications/changes-to-development-consent-orders