Galloper Offshore Wind Farm

Section 51 advice

The list below includes a record of advice we have provided for this project.

There is a statutory duty, under section 51 of the Planning Act 2008, around an application or potential application. This includes recording the name of the person who requested advice and the advice given. This information has to be made publicly available.

Search advice

Search by key words or the name of person the advice was given to.

Showing 1 to 22 of 22 documents, newest first.

Results per page 25 | View 50 results per page | View 100 results per page

  • View advice to RSPB

    Will the Examining Authority for Galloper Wind Farm accept and take into consideration our letter of 30 November 2012, submitted to PINS after the close of examination?

  • View meeting with Galloper Wind Farm Ltd (GWFL)

    Discussion on procedures under the Planning Act 2008 (PA2008) following acceptance of an application for examination.

  • View advice to Galloper Wind Farm Limited

    IPC advice to Galloper Wind Farm Ltd (?GWFL?) in respect of the application for development consent for the proposed project.

  • View advice to SSE Renewables

    During a final engineering review of the proposed development, it has become clear that in order to construct the onshore works, there is a requirement (which was not previously identified) for a... Read more

  • View advice to Royal Haskoning

    Request for IPC advice regarding the draft Habitats Regulations Assessment Report for Galloper Wind Farm.

  • View meeting with Kate Tibble

    Project update and discussion regarding the draft Development Consent Order (DCO)

  • View advice to Galloper Wind Farm Ltd

    Galloper Wind Farm Ltd requested comments on draft DCO.

  • View advice to Kate Tibble

    When submitting the application, who should the accompanying cheque be made out to?

  • View advice to Galloper Wind Farm

    Submission of a draft Habitats Regulations Assessment screening report for the Galloper Wind Farm project - for IPC general comment.

  • View advice to RWE Npower Renewables Ltd

    Request for advice in respect of the draft section 48 notice for the proposed Galloper Wind Farm project.

  • View advice to RWE Npower Renewables Ltd

    Does the IPC see any difficulty with a single application for development consent including two Nationally Significant Infrastructure Projects?

  • View meeting with GWF

    Please refer to meeting note, attached

  • View meeting with Galloper Wind Farm (GWF)

    A meeting was held to update the IPC on the project and explain GWFs proposed approach to the Rochdale Envelope and assessing cumulative impacts as part of the Environmental Impact Assessment (EIA).

  • View meeting with Galloper Wind Farm

    Update meeting with the applicant to discuss Galloper Wind Farm (GWF) project. Discussion regarding the applicant?s initial draft development consent order, consent flexibility and the Rochdale... Read more

  • View meeting with RWEnpower

    Meeting with Galloper Windfarm for update on the project and discussion of future progression.

  • View meeting with RWE npower renewables

    Details of meeting held on 23rd November 2010 between the IPC and RWE npower renewables to discuss progress to date.

  • View meeting with RWE

    Meeting held on 23 November 2010 between the IPC and promoter for an update on the project.

  • View meeting with SSE Renewables

    Meeting with RWE and SSE Renewables to discuss offshore wind farm matters the Rochdale Envelope.

  • View advice to RWE

    What information is required to make a s.53 PA 2008 request for authorisation to the Commission? Are there any other statutory timeframes apart from the 14 days notice required where the land is... Read more

  • View meeting with SSE Renewables

    Discussions on the progress of the project and further detail on the new Planning Process (e.g Fee Structure)

  • View meeting with SSE Renewables and RWE Npower

    Discussions on the progress of the project and further detail on the new Planning Process (e.g Fee Structure)

  • View meeting with SSE Renewables & RWE Npower Rene

    A general introduction to the project and its team members.