Cyngor i Dorset Fire & Rescue
Yn ôl i'r rhestrYmholiad
- Oddiwrth
- Dorset Fire & Rescue
- Y dyddiad y rhoddwyd y cyngor
- 17 Hydref 2011
- Math o ymholiad
- Phone
Is it possible to extend the deadline for comments that form part of IPC's scoping opinon?
Cyngor a roddwyd
Unfortunately, we are unable to amend the deadline for our scoping consultation. The 28 day deadline for consultees to respond to consultation is set out in Regulation 8 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2009. Therefore, for comments to be included in the Navitus Bay Scoping Opinion they must be received by the IPC by 21 October 2011.
The IPC will forward any replies received after this date to the developer, but these comments will not be incorporated into the Scoping Opinion.