Mr Phillips (representing DONG Energy regarding the Walney Extension offshore wind farm proposal) queried the actions to be taken by an applicant submitting an application after 25 June 2013 rearding section 132 of the Planning Act 2008.

Cyngor a roddwyd

The Planning Inspectorate informed Mr Phillips that the applicant would need to be satisfied that the relevant the test in section 132(3) to (5) of the Planning Act 2008 as amended would be satisfied. In addition, as stated in section 24(3) of the Growth and Infrastructure Act 2013, the relevant subsection in section 132 of the Planning Act 2008 should be recorded in the Order.