During a break of the issue specific hearing, case manager Nicholas Coombes discussed discrepancies between the project co-ordinates in the draft Development Consent Order and the Order Limits plan with the applicant's project team.
Advice given
Nicholas Coombes pointed out the anomalous co-ordinates identified in the ExA's Comments on DCO4 using the hard copy application documents.