All project updates
29 April 2021
A Decision Letter (PDF, 307KB) and Amendment Order (PDF, 53KB) have been issued by the Department for Business, Energy and Industrial Strategy to make a change that is not material to the Rampion (Offshore Wind Farm) Order 2014.
5 February 2021
The Secretary of State has requested further information from the Applicant and Vodafone (PDF, 139KB) by 19 February 2021
13 January 2021
The Applicant has responded to the consultation responses received from Openreach and Vodafone:
Applicant’s response to Openreach (PDF, 395KB)
Applicant’s response to Vodafone (PDF, 459KB)
Applicant’s response to Openreach (PDF, 395KB)
Applicant’s response to Vodafone (PDF, 459KB)
3 December 2020
Responses to the consultation by BEIS have been published.
21 October 2020
An application for a non-material change to the Rampion Offshore Wind Farm Order 2014 has been made by Rampion Offshore Wind Limited.
If you wish to make a representation this should be emailed to RampionOffshoreWindFarm@planninginspectorate.gov.uk. The deadline for receipt of representations is 27 November 2020.
If you wish to make a representation this should be emailed to RampionOffshoreWindFarm@planninginspectorate.gov.uk. The deadline for receipt of representations is 27 November 2020.
31 July 2019
The examination documents relating to this project have been archived and are no longer available on this site. The Secretary of State’s decision and Development Consent Order can be viewed on the Documents tab.
To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.
To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.
16 July 2014
Decision made by the Secretary of State
17 April 2014
Recommendations given by the Planning Inspectorate