Hornsea Offshore Wind Farm (Zone 4) - Project One Amserlen yr archwiliad

Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.

Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.

Y cam archwilio

Agorodd yr archwiliad ar 10 December 2013

Caeodd yr archwiliad ar 10 June 2014

Terfynau amser a digwyddiadau i ddod

Nid oes unrhyw derfynau amser neu ddigwyddiadau

Terfynau amser a digwyddiadau blaenorol

10 Rhagfyr 2013 - Preliminary Meeting

Caeedig

Preliminary Meeting to discuss how the examination will be conducted

13 Ionawr 2014 - Deadline 1

Caeedig

Notification of wish by an interested party to be heard at an open floor hearing

Notification by an affected person of wish for compulsory acquisition hearing to be held

Notification of wish to make oral representations at the issue-specific hearing on the draft Development Consent Order (DCO)

20 Ionawr 2014 - Deadline 2

Caeedig

Deadline II for receipt of:

Comments on relevant representations (RRs)

Summaries of all RRs exceeding 1500 words

Written representations (WRs) by all interested parties

Summaries of all WRs exceeding 1500 words

Local Impact Report from any local authorities

Statements of Common Ground requested by ExA – see Annex G

Responses to ExA’s first round of written questions

Completion by applicant of HRA matrices

11 Chwefror 2014 - Open Floor Hearing

Caeedig

OFH

12 Chwefror 2014 - Site Visit (Accompanied)

Caeedig

x

13 Chwefror 2014 - Issue Specific Hearing 1

Caeedig

ISH

24 Chwefror 2014 - Deadline 3

Caeedig

Deadline III for receipt by the ExA of:

Comments on WRs and responses to comments on RRs

Comments on Local Impact Reports

Comments on responses to ExA’s first round of written questions

Revised draft DCO from applicant

Comments on Environmental Clarification Notes

Written submissions of oral cases given at hearings week commencing 10 February 2014

11 Mawrth 2014 - Deadline 4

Caeedig

Dates for issue-specific hearings on:

HRA - methodology and impacts on birds and marine mammals

Impacts on fishing and navigation

Construction impacts and socio-economic matters

Monitoring, management and mitigation plans and provisions

11 Mawrth 2014 - Issue Specific Hearing 2

Caeedig

ISH

12 Mawrth 2014 - Deadline 5

Caeedig

Dates for issue-specific hearings on:

HRA - methodology and impacts on birds and marine mammals

Impacts on fishing and navigation

Construction impacts and socio-economic matters

Monitoring, management and mitigation plans and provisions

13 Mawrth 2014 - Deadline 6

Caeedig

Dates reserved for compulsory acquisition hearing (including, if required, s127 of the Planning Act 2008 issues)

13 Mawrth 2014 - Compulsory Acquisition Hearing

Caeedig

CAH

20 Mawrth 2014 - Deadline 7

Caeedig

Date for issue of possible second round of written questions

22 Ebrill 2014 - Deadline 8

Caeedig

Deadline IV for receipt of:

Responses to ExA’s second round of written questions

Written submissions of oral cases given at hearings week commencing 10 March 2014

29 Ebrill 2014 - Deadline 9

Caeedig

Dates reserved for:

Any other issue-specific or compulsory acquisition hearings

29 Ebrill 2014 - Issue Specific Hearing 3

Caeedig

ISH

30 Ebrill 2014 - Deadline 10

Caeedig

Dates reserved for:

Any other issue-specific or compulsory acquisition hearings

1 Mai 2014 - Deadline 11

Caeedig

Dates reserved for:

Any other issue-specific or compulsory acquisition hearings

13 Mai 2014 - Deadline 12

Caeedig

Date reserved for second accompanied site visit

14 Mai 2014 - Deadline 13

Caeedig

Deadline V for receipt of:

Comments on responses to ExA’s second round of written questions

And final deadline for:

All documents post all hearings

All written proofs of oral cases

Issue of:

The Report on the Implications on European Sites

21 Mai 2014 - Deadline 14

Caeedig

Deadline VI for reciept of:

The applicant’s final draft DCO

28 Mai 2014 - Deadline 15

Caeedig

Deadline VII for reciept of: Comments on the Report on the Implications on European Sites

6 Mehefin 2014 - Deadline 16

Caeedig

Deadline VII for reciept of:

Response to Rule 17 issued 3 June 2014.

Comments on documents submitted by the applicant on 3 June 2014.

9 Mehefin 2014 - Deadline 17

Caeedig

Deadline VIII for reciept of:

Comments on all responses recieved for deadline VII.

This is the final deadline of the examination

10 Mehefin 2014 - Deadline 18

Caeedig

The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.