Amserlen yr archwiliad
Mae amserlen yr archwiliad yn dangos dyddiadau digwyddiadau a therfynau amser ar gyfer cyflwyniadau.
Os ydych wedi cofrestru i leisio'ch barn, gallwch wneud hyn yn ystod y cam archwilio.
Y cam archwilio
Agorodd yr archwiliad ar 10 December 2013
Caeodd yr archwiliad ar 10 June 2014
10 Rhagfyr 2013 - Preliminary Meeting
CaeedigPreliminary Meeting to discuss how the examination will be conducted
13 Ionawr 2014 - Deadline 1
CaeedigNotification of wish by an interested party to be heard at an open floor hearing
Notification by an affected person of wish for compulsory acquisition hearing to be held
Notification of wish to make oral representations at the issue-specific hearing on the draft Development Consent Order (DCO)
20 Ionawr 2014 - Deadline 2
CaeedigDeadline II for receipt of:
Comments on relevant representations (RRs)
Summaries of all RRs exceeding 1500 words
Written representations (WRs) by all interested parties
Summaries of all WRs exceeding 1500 words
Local Impact Report from any local authorities
Statements of Common Ground requested by ExA – see Annex G
Responses to ExA’s first round of written questions
Completion by applicant of HRA matrices
11 Chwefror 2014 - Open Floor Hearing
CaeedigOFH
12 Chwefror 2014 - Site Visit (Accompanied)
Caeedigx
13 Chwefror 2014 - Issue Specific Hearing 1
CaeedigISH
24 Chwefror 2014 - Deadline 3
CaeedigDeadline III for receipt by the ExA of:
Comments on WRs and responses to comments on RRs
Comments on Local Impact Reports
Comments on responses to ExA’s first round of written questions
Revised draft DCO from applicant
Comments on Environmental Clarification Notes
Written submissions of oral cases given at hearings week commencing 10 February 2014
11 Mawrth 2014 - Deadline 4
CaeedigDates for issue-specific hearings on:
HRA - methodology and impacts on birds and marine mammals
Impacts on fishing and navigation
Construction impacts and socio-economic matters
Monitoring, management and mitigation plans and provisions
11 Mawrth 2014 - Issue Specific Hearing 2
CaeedigISH
12 Mawrth 2014 - Deadline 5
CaeedigDates for issue-specific hearings on:
HRA - methodology and impacts on birds and marine mammals
Impacts on fishing and navigation
Construction impacts and socio-economic matters
Monitoring, management and mitigation plans and provisions
13 Mawrth 2014 - Deadline 6
CaeedigDates reserved for compulsory acquisition hearing (including, if required, s127 of the Planning Act 2008 issues)
13 Mawrth 2014 - Compulsory Acquisition Hearing
CaeedigCAH
20 Mawrth 2014 - Deadline 7
CaeedigDate for issue of possible second round of written questions
22 Ebrill 2014 - Deadline 8
CaeedigDeadline IV for receipt of:
Responses to ExA’s second round of written questions
Written submissions of oral cases given at hearings week commencing 10 March 2014
29 Ebrill 2014 - Deadline 9
CaeedigDates reserved for:
Any other issue-specific or compulsory acquisition hearings
29 Ebrill 2014 - Issue Specific Hearing 3
CaeedigISH
30 Ebrill 2014 - Deadline 10
CaeedigDates reserved for:
Any other issue-specific or compulsory acquisition hearings
1 Mai 2014 - Deadline 11
CaeedigDates reserved for:
Any other issue-specific or compulsory acquisition hearings
13 Mai 2014 - Deadline 12
CaeedigDate reserved for second accompanied site visit
14 Mai 2014 - Deadline 13
CaeedigDeadline V for receipt of:
Comments on responses to ExA’s second round of written questions
And final deadline for:
All documents post all hearings
All written proofs of oral cases
Issue of:
The Report on the Implications on European Sites
21 Mai 2014 - Deadline 14
CaeedigDeadline VI for reciept of:
The applicant’s final draft DCO
28 Mai 2014 - Deadline 15
CaeedigDeadline VII for reciept of: Comments on the Report on the Implications on European Sites
6 Mehefin 2014 - Deadline 16
CaeedigDeadline VII for reciept of:
Response to Rule 17 issued 3 June 2014.
Comments on documents submitted by the applicant on 3 June 2014.
9 Mehefin 2014 - Deadline 17
CaeedigDeadline VIII for reciept of:
Comments on all responses recieved for deadline VII.
This is the final deadline of the examination
10 Mehefin 2014 - Deadline 18
CaeedigThe ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting.