1. Section 51 advice
  2. Advice in detail

Advice to Vattenfall UK

Back to list

Enquiry

From
Vattenfall UK
Date advice given
11 October 2010
Enquiry type
Phone

Letter seeking to notify IPC under Reg 6 Infrastructure Planning (EIA) Regulations 2009 without some of the information prescribed to accompany a Reg 6 notification.

Advice given

Thank you for your letter seeking to notify us under Reg 6 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2009 that Vattenfall Wind Power ltd intend to apply for a development consent order for an extension to the existing 90MW Kentish flats off-shore wind farm. Unfortunately we cannot accept it as a Reg 6 notification as it doesn't provide us with all the information that Reg 6 requires for this purpose.

However, you can submit your Reg 6 notification together with your formal scoping request under Regulation 8(1) as the latter requires the same accompanying information.