Advice to Jackie Baxter
Back to listEnquiry
- From
- Jackie Baxter
- Date advice given
- 25 September 2013
- Enquiry type
Enquiry from the North East Lincolnshire Council regarding its Interested Party status for North Killingholme Power Project.
Advice given
It was explained that under s.43 of the Planning Act 2008 (as amended) North East Lincolnshire Council has been identified as an 'A' authority. This is an authority that shares a boundary with a local authority in which the proposed development is situated; in this instance North Lincolnshire Council.
The appointed Examining Authority must notify each person as defined in s.43 of the 2008 Act about procedural decisions made in relation to the above application. As a result of this it is required that North East Lincolnshire Council authority is contacted with regard to the above Nationally Significant Infrastructure Project.
It was noted that, in future, the local authority will only be contacted about changes to the examination timetable in relation to the above application. The authority was advised that should they wish to participate in the examination they will need to notify the Examining Authority by Friday 4 October 2013.