1. Section 51 advice
  2. Advice in detail

Advice to LNG Portable Pipeline Services

Back to list

Enquiry

From
LNG Portable Pipeline Services
Date advice given
15 April 2015
Enquiry type
Email

We recently took over a copy that receives letters from yourselves, however we would like to unsubscribe from this.

Company Name ?

LNG Portable Pipeline Services Ltd Cadarache Bere Court Pangbourne Reading RG8 8HT

Please let me know if you require any more information.

Advice given

Thank you for your email in relation to the above project.

LNG Portable Pipeline Services Ltd is listed as a prescribed consultee for this project. This means that we have a statutory duty to consult you in accordance with Section 42 of the Planning Act 2008 (the 2008 Act) and Schedule 1 of The Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009 (as amended) (the APFP Regulations).

Now you have received the Rule 8 letter (detailing how the application is to be examined), you should only receive one further letter from us, the Section 99 letter which confirms the closing of the examination period. If there is a change to the timetable as set out in the Rule 8 letter, you will also receive this letter.

Further information on the applicable planning legislation can be found on our website, please see the attached link: http://infrastructure.planningportal.gov.uk/legislation-and-advice/legislation/

Please note this reply will be published as section 51 advice under the Planning Act 2008 on the project page of the Planning Portal. I hope this response has been helpful.

Kind Regards