Knottingley Power Project Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 13 March 2014

The examination closed on 13 September 2014

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

13 March 2014 - Preliminary Meeting

Closed

Preliminary Meeting

27 March 2014 - Deadline 1

Closed

Receipt of written notification of:

• Request for receipt of written notification by statutory parties of a wish to be considered as an interested party

• Request for receipt of notification (using the prescribed form) by persons with certain categories of interest in the land of a wish to become an interested party

11 April 2014 - Deadline 2

Closed

Deadline 1

Deadline for receipt by the ExA of:

• Comments on additional documents provided and listed as accepted in Annex D of this letter and published on the Knottingley Power Project webpage on Thursday 20 March 2014

• Comments by interested parties on relevant representations (RRs) already received

• Summaries of all RRs by interested parties whose RRs exceeded 1500 words

• Written representations (WRs) by interested parties

• Summaries of WRs by interested parties whose WRs exceeded 1500 words

• Responses to ExA’s first written questions

• Statements of Common Ground requested by the ExA

• Local Impact Report(s) (LIR) from local authorities defined under s56A of the Planning Act 2008 (as amended)

• Any documents/amendments requested by the ExA at the Preliminary Meeting

14 April 2014 - Deadline 3

Closed

Deadline 2

Deadline for notification by interested parties of their wish:

• to be heard at an open floor hearing (OFH)

• to make oral representations at any issue specific hearing (ISH), including compulsory acquisition, DCO and local environmental impact matters

• to attend any accompanied site visit and any representations to view at or near the site or the surrounding area

17 April 2014 - Deadline 4

Closed

Notification by the ExA of date, time and place for:

• Compulsory acquisition hearing (CAH) • Local environmental impact matters hearing • Any accompanied site visit(s) (ASV) • Any other issue specific hearing(s) • Any open floor hearing

6 May 2014 - Deadline 5

Closed

Deadline 3

Deadline for the receipt of:

• Comments on the written representations and responses to comments on relevant representations

• Comments on Statements of Common Grounds

• Comments on Local Impact Reports

• Comments on responses to ExA’s first written questions

9 May 2014 - Deadline 6

Closed

Deadline for receipt of comments regarding the Examining Authority's procedural decision in relation to changes to the application and comments on the closure of Kellingley Colleriery, made on 1 May 2014.

13 May 2014 - Deadline 7

Closed

Date reserved for any accompanied site visit

13 May 2014 - Site Visit (Accompanied)

Closed

Accompanied Site Visit

14 May 2014 - Deadline 8

Closed

Date reserved for environmental impacts hearing and evening open floor hearing

14 May 2014 - Issue Specific Hearing 1

Closed

Issue Specific Hearing relating to Environmental Impacts

14 May 2014 - Open Floor Hearing

Closed

Open Floor Hearing

15 May 2014 - Deadline 9

Closed

Date reserved for compulsory acqusition hearing

15 May 2014 - Compulsory Acquisition Hearing

Closed

Compulsory Acquisition Hearing

23 May 2014 - Deadline 10

Closed

Deadline 4

Deadline for the receipt of:

• Written summary of the oral case put at the environmental impacts hearing, compulsory acquisition and open floor hearing

• Any documents/amendments requested by the ExA including

• Any revised DCO

28 May 2014 - Deadline 11

Closed

Issue by the ExA of:

• Second round of written questions (if a second round is required)

• Any further request for SoCGs

20 June 2014 - Deadline 12

Closed

Deadline 5

Deadline for the receipt of:

• Responses to the ExA’s second round of questions and any further SoCGs

• Comments on written summaries of cases put at any issue specific or open floor hearings

• Comments on any submitted revised DCO

23 June 2014 - Deadline 13

Closed

Notification by ExA of the time, date and place for:

• DCO hearing

• Any other hearings deemed necessary by the ExA

11 July 2014 - Deadline 14

Closed

Deadline 6

Deadline for the receipt of:

• Comments on the responses to the ExA’s second round of questions and any further SoCGs

• Any documents/amendments requested by the ExA

16 July 2014 - Deadline 15

Closed

Issue Specific Hearing on the draft Development Consent Order and Water Resource issues

16 July 2014 - Issue Specific Hearing 2

Closed

Issue Specific Hearing on the draft Development Consent Order and Water Resource issues

24 July 2014 - Deadline 16

Closed

Deadline 7

Deadline for the receipt of:

• Written summaries of cases put orally at DCO/or other issue specific hearing on 16 and 17 July 2014 and;

• Any documents/amendments requested by the ExA at the hearings

• Final revised DCO

15 August 2014 - Deadline 17

Closed

Deadline 8

Deadline for the receipt of:

• Comments on the written summaries of cases put orally at DCO/and any issue specific hearing on 16 and 17 July 2014

• Comments on final revised DCO