1. Section 51 advice
  2. Advice in detail

Advice to Caryl Walter

Back to list

Enquiry

From
Caryl Walter
Date advice given
19 January 2014
Enquiry type
Email

The enquiry received from the applicant regarding deadline for submission of Certificates of Compliance with s56 of the Planning Act (as amended)

The applicant enquired whether certificates must be submitted within 10 working days following the initial deadline given for receipt of relevant representations, or the extended deadline that was provided by the applicant to 3 parties.

Advice given

Following advice was given:

Our understanding is that the applicant has carried out the following in respect of section 56 of the Planning Act (2008) as amended:

? s56 (2) Notifying persons of accepted application, and Regulation 8 of the Infrastructure Planning (Applications: Prescribed Forms and Procedures) Regulations 2009 (as amended) - Notice of accepted application. The notice that was served by the applicant to persons under s56(2) included the period of 14 November ? 6 January 2014 for receipt of relevant representations.

? Legislation as above. A re-issued notice was served by the applicant to Mr and Mrs Howson, identified as new tenants, and South Milford Parish Council on the basis of returned correspondence, and was served on 24 December 2013 and included the period of 14 November ? 28 January 2014 for receipt by the SoS of relevant representations.