20 December 2024

An application for a non-material change to The Ferrybridge Multifuel 2 Power Station Order 2015 (as Corrected and Amended) has been made by Enfinium Limited.

The deadline for receipt of representations is 23:59 on Friday 21 February 2024.

If you wish to make a representation, this should be emailed to fm2@planninginspectorate.gov.uk or posted to:

National Infrastructure

The Planning Inspectorate

Temple Quay House

2 The Square

Bristol

BS1 6PN

20 November 2024

2 March 2021

The Examination documents relating to this project have been archived and are no longer available on this site. The >Secretary of State's decision and Development Consent Order can be viewed on the Documents tab.

To find out where to view the Certified Documents please refer to the contact details set out in the Explanatory Note of the Development Consent Order.

28 October 2015

Decision made by the Secretary of State

29 July 2015

Recommendations given by the Planning Inspectorate

4 December 2014

Examination begins

22 October 2014

Relevant representations published on the website

16 October 2014

Registration of interested parties closes

4 September 2014

Registration of interested parties begins

31 July 2014

Application received by the Planning Inspectorate