12 April 2024

In accordance with Schedule 18 Part 1 of the East Anglia ONE North Offshore Wind Farm Order 2022 and the East Anglia TWO Offshore Wind Farm Order 2022, the Secretary of State has invited the Marine Management Organisation, Natural England, East Suffolk Council, Great Yarmouth Borough Council, the Royal Society for the Protection of Birds, Norfolk Boreas Limited and Norfolk Vanguard Limited, to comment on the Kittiwake Implementation Plan.

The deadline for responses is 23.59 on 12 May 2024.

14 November 2023

Decision Letter (PDF, 216KB) have been issued by the Department of Energy Security and Net Zero for the Kittiwake Implementation and Monitoring Plan; and the responses received to the Secretary of State's consultation letter dated 6 October 2023 have now been published.

6 October 2023

In accordance with Schedule 18 Part 2 of the East Anglia ONE North Offshore Wind Farm Order 2022 and the East Anglia TWO Offshore Wind Farm Order 2022, the Secretary of State has invited (PDF,163KB) the Marine Management Organisation, Natural England, East Suffolk Council, the Royal Society for the Protection of Birds, Norfolk Boreas Limited and Norfolk Vanguard Limited, to comment on the Lesser black-backed gull Implementation & Monitoring Plan. View the documents here. Deadline for responses is 23.59 on 6 November 2023.

6 September 2023

The responses received to the Secretary of State’s consultation letter dated 11 July 2023 have now been published.

11 July 2023

In accordance with Schedule 18 Part 1 of the East Anglia ONE North Offshore Wind Farm Order 2022 and the East Anglia TWO Offshore Wind Farm Order 2022, the Secretary of State has invited (PDF, 147KB) the Marine Management Organisation, Natural England, East Suffolk Council, Great Yarmouth Borough Council, the Royal Society for the Protection of Birds, Norfolk Boreas Limited and Norfolk Vanguard Limited, to comment on the Kittiwake Implementation Plan (PDF, 2MB).

11 May 2023

The Secretary of State has issued an Approval Letter (PDF, 89KB) on 11 May 2023 for the Lesser Black-Backed Gull Plan of Works, pursuant to Schedule 18, Part 2 of the East Anglia ONE North Offshore Wind Farm Order 2022.

16 January 2023

The Secretary of State has issued an Approval Letter on 16 January 2023 (PDF, 91KB) for the Kittiwake Plan of Works, pursuant to Schedule 18, Part 1 of the East Anglia ONE North Offshore Wind Farm Order 2022.

22 December 2022

A Correction Order (PDF, 180 KB) for the East Anglia ONE North Offshore Windfarm  Order 2022 has been published. The Correction Order came into force on 22 December 2022.

31 March 2022

The Secretary of State has today granted development consent for this application. For further information please refer to the following decision documentation:

Secretary of State’s Decision Letter (PDF, 1MB)
Planning Inspectorate Notification of Decision Cover Letter (PDF, 140KB)
Development Consent Order as Made (PDF, 1MB)
Examining Authority’s Recommendation Report Volume 1 (PDF, 5MB)
Examining Authority’s Recommendation Report Volume 2 (PDF, 15MB)
Examining Authority’s Recommendation Report Volume 3 (PDF, 5MB)
Habitats Regulations Assessment (PDF, 3MB)
Regulation 31 Notice (PDF, 109KB)
Post Examination Submissions (PDF, 54MB)

Additional responses received by the Secretary of State since the close of the consultation period have also now been published.

31 March 2022

Decision made by the Secretary of State

18 March 2022

The Applicant has submitted a clarification letter (PDF, 136KB) in relation to the letter submitted by Natural England.

14 March 2022

The Secretary of State for Business Energy and Industrial Strategy has received clarifications from the Applicant in relation to red-throated diver in the Outer Thames Estuary Special Protection Area and has requested the advice of Natural England upon these clarifications. (PDF,415KB)

2 February 2022

The responses received to the Secretary of State’s Consultation Letter of 20 December 2021 have now been published.

20 December 2021

The Secretary of State (SoS) for Business, Energy and Industrial Strategy has requested information (PDF, 161KB) from the Applicant, Suffolk County Council, Natural England, the Marine Management Organisation and all other Interested Parties. The deadline for responses to this second round of consultation and comments on responses to the SoS first round of consultation is 23.59 pm on 31 January 2022.

The SoS has set a new deadline for the Decision to be made on this application which is 31 March 2022.

7 December 2021

The responses received to the Secretary of State’s Consultation Letter of 2 November 2021 (and subsequent related letters) have now been published. The Secretary of State will be issuing a letter detailing the next steps in due course.

24 November 2021

The Secretary of State has issued a letter (PDF,425 KB) containing details of flood events provided by Substation Action Save East Suffolk (SASES) to the Environment Agency that should be considered for its consultation response.

17 November 2021

The Secretary of State has issued a letter of clarification (PDF, 110KB) to the Environment Agency regarding flood events that should be considered for its consultation response.

2 November 2021

The Secretary of State for Business, Energy and Industrial Strategy has requested information (PDF, 159KB) from the Applicant, Natural England, the RSPB, East Suffolk Council and Suffolk County Council on the following areas: badgers, offshore ornithology, key documents to be certified and flood risk.

All Interested Parties are requested to comment on specific issues regarding flood risk and the Offshore Ornithology Cumulative and In Combination Collision Risk and Displacement Update submitted by the Applicant at the end of the examination.

The deadline for responses 11.59 pm on 30 November 2021.

6 October 2021

Recommendations given by the Planning Inspectorate

7 July 2021

The Deadline 13 submissions have now been published.

The Examining Authority has issued a Notification to confirm the completion of the Examination (PDF, 106KB).

The Examination closed at 23:59 on Tuesday 6 July 2021.

6 July 2021

The Examination closes at 23:59 on Tuesday 06 July 2021.

30 June 2021

The Deadline 12 submissions have now been published.

22 June 2021

The Examining Authority has accepted additional submissions from the Applicant at their discretion on 22 June 2021. These are a covering letter (PDF, 108KB) and updated versions of the Applicants Deadline 11 submissions, which had information missing, namely:

AS-133 and AS-134 (to replace REP11-047)
AS-135 and AS-136 (to replace REP11-083)

The Examining Authority has also issued a Rule 17 request for further information (PDF, 230 KB) from the Applicant and eight specific Interested Parties (IPs) requiring a response by Deadline 12, Monday 28 June 2021, however other IPs can also provide responses thereto if they wish. IPs may wish to comment on any of these responses by Deadline 13, Monday 5 July 2021.

18 June 2021

The Examining Authority (ExA) has issued a Rule 17 request for further information (PDF, 230 KB) from the Applicant and eight specific Interested Parties (IPs) requiring a response by Deadline 12, Monday 28 June 2021. However, other IPs may also wish to respond to these requests by Deadline 13, Monday 5 July 2021.

16 June 2021

The Examining Authority has published the Updated Report on the Implications for European Sites [PDF, 972KB]. Comments are requested by Deadline 12 (28 June 2021).

The authority has also publish a Rule 9 Letter [PDF, 271KB] accepting a proposal by the Applicant to exclude land near Ness House, Thorpeness from the Order as a non-material change.

14 June 2021

The ExA has accepted and published submissions from the Applicant made on 11 June 2021, updating the Outline Operational Drainage Management Plan (OODMP) and the Outline Landscape and Ecological Management Strategy (OLEMS). Comments on these documents should be made by Deadline 12.

11 June 2021

The Deadline 11 submissions have now been published.

1 June 2021

The Action points for ISH16 into the proposed substation site (PDF, 150KB), and ISH17 into the dDCO and other matters (PDF, 146KB) have been published. The recordings and transcripts for these events have also been published.

27 May 2021

The Action Points for ISH16 into the proposed substation site (PDF, 150KB), have been published. The recordings and transcripts for this event have also been published.

The Livestream for events running w/c 24 May 2021 is available for those wishing to observe in real time.

Please refer to the Agenda for Issue Specific Hearing 17 (ISH17) (PDF, 219KB) into the draft Development Consent Order.

The Applicant has submitted a draft response to Examining Authorities Rule 17 request for information (R17QE), (PDF, 143KB) to be used in ISH16 and ISH17.

24 May 2021

The Applicant has submitted a draft response to Examining Authorities Rule 17 request for information (R17QE), (PDF, 143KB) to be used in ISH16 and ISH17.

The Livestream for events running w/c 24 May 2021 is available for those wishing to observe in real time.

Agenda for Issue Specific Hearing 16 (ISH16) (PDF, 206KB) into the proposed substation site; and
Agenda for Issue Specific Hearing 17 (ISH17) (PDF, 219KB) into the draft Development Consent Order.

20 May 2021

The Examining Authority Commentaries on the draft Development Consent Order (PDF, 411KB) and further written questions (ExQ3) (PDF, 533KB) have been published.

The Livestream for events running w/c 24 May 2021 is available for those wishing to observe in real time.

Please refer to the appropriate Agendas for each day:

Agenda for Issue Specific Hearing 16 (ISH16) (PDF, 206KB) into the proposed substation site; and
Agenda for Issue Specific Hearing 17 (ISH17) (PDF, 219KB) into the draft Development Consent Order.

13 May 2021

The Examining Authority has issued a Rule 17 letter (PDF, 143KB) requesting further information from the Applicant.

The agendas for the following hearings have been published:

Agenda for Issue Specific Hearing 16 (ISH16) (PDF, 206KB) into the proposed substation site; and

Agenda for Issue Specific Hearing 17 (ISH17) (PDF, 219KB) into the draft Development Consent Order.

12 May 2021

The Examining Authority has published the following documents:

The note from the Unaccompanied Site Inspections (PDF, 321KB) undertaken on 22 & 23 April 2021;

Agenda for Issue Specific Hearing 16 (ISH16) (PDF, 206KB) into the proposed substation site; and

Agenda for Issue Specific Hearing 17 (ISH17) (PDF, 219KB) into the draft Development Consent Order.

6 May 2021

The Examining Authority has issued a Rule 17 letter (PDF, 139KB) requesting further information from the Nuclear Decommissioning Authority.

29 April 2021

The Examining Authority has issued a letter confirming their Procedural Decision (PDF, 342KB) to accept the Applicants non-material change request. The letter also notifies all Interested Parties for ISH16 and ISH17 commencing the week of 24 May 2021.

The Examining Authority has issued a Rule 17 letter (PDF, 173KB) requesting further information from the Applicant.

19 April 2021

Deadline 9 submissions have now been published.

6 April 2021

The Secretary of State has issued a letter extending the Examination from 6 April 2021 until no later than 6 July 2021 (PDF, 96KB)

The Examining Authority has issued their Rule 8(3) Letter amending the Examination timetable. (PDF, 175KB)

Deadline 9 has now changed. All submissions must now be received by Thursday 15 April 2021.

29 March 2021

The Deadline 8 submissions have now been published.

26 March 2021

The Examining Authority has issued a Procedural Decision to accept the Applicant’s proposed changes to the scheme, which were submitted at Deadline 7.

The Procedural Decision (PDF, 259KB) has been added to the Examination Library (PDF, 2MB).

22 March 2021

The Examining Authority have published a Rule 17 letter, requesting further information from Natural England dated 17 March 2021, the deadline for a response is D8, 25 March 2021.

The Action Points for ISH10 into Health and Wellbeing Assessment (PDF, 112KB), ISH11 into Flood Risk and Drainage (PDF, 83KB), ISH12 into Noise (PDF, 102KB), ISH13 into Traffic and Transport (PDF, 156KB), ISH14 into Biodiversity and Habitats Regulations Assessment (PDF, 163KB), ISH15 into the draft Development Consent Order (DCO) (PDF, 150KB ) and CAH3 (PDF, 131KB) have been published. The recordings and transcripts for these events have also been published.

The time reserved for ISH10A, ISH11A, ISH12A, ISH13A, CAH3A, ISH14A, and ISH15A in w/c 23 March 2021 will no longer be required and have therefore been cancelled.

15 March 2021

The Livestream for events running w/c 15 March 2021 is available for those wishing to observe in real time.

Please refer to the appropriate Agendas for each day:

The Action Points for ISH10 into Health and Wellbeing Assessment (PDF, 112KB), ISH11 into Flood Risk and Drainage (PDF, 83KB), ISH12 into Noise (PDF, 102KB) and ISH13 into Traffic and Transport (PDF, 156KB) have been published. The recordings and transcripts for these events have also been published.

The time reserved for ISH10A, ISH11A, ISH12A and ISH13A in w/c 22 March 2021 will no longer be required and these events have been cancelled.

9 March 2021

The Livestream for events running w/c 8 March 2021 is available for those wishing to observe in real time.

Please refer to the appropriate Agendas for each day:

Agendas for hearings during the week of 15th March (ISH14 into Biodiversity and HRA (PDF, 241KB), ISH15 into the dDCO (PDF, 214KB) and Compulsory Acquisition Hearings (CAH3) (PDF, 185KB)) have been published.

5 March 2021

Deadline 7 submissions have now been published.

The Examining Authority has published the Report on the Implications for European Sites (RIES) (PDF, 737KB)

As no additional Affected Persons have requested to be heard at an Open Floor Hearing, OFH8 has been cancelled.

The Livestream for events running w/c 8 March 2021 is available for those wishing to observe in real time.

Please refer to the appropriate Agendas for each day:
Issue Specific Hearing 10 (ISH10) into Health and Wellbeing Assessment (PDF, 204KB)
Issue Specific Hearing 11 (ISH11) into Flood risk and drainage (PDF, 205KB)
Issue Specific Hearing 12 (ISH12) into Noise (PDF, 207KB)
Issue Specific Hearing 13 (ISH13) into Traffic and transport (PDF, 211KB)

Agendas for events commencing week of 15th March will be published 9th March 2021.

5 March 2021

As no additional Affected Persons have requested to be heard at an Open Floor Hearing, Open Floor Hearing 8 (OFH8) has been cancelled.

The Examining Authority has published the Report on the Implications for European Sites (RIES) (PDF, 737KB).

Agendas for hearings during the week of 8th March can be found here.

Agendas for events commencing week of 15th March will be published 9th March 2021.

4 March 2021

The Examining Authority has published the Report on the Implications for European Sites (RIES) (PDF, 737KB).

Information for forthcoming Hearings:

The Agendas for the following events have been published:
• Issue Specific Hearing 10 (ISH10) into Health and Wellbeing Assessment (PDF, 204KB)
• Issue Specific Hearing 11 (ISH11) into Flood risk and drainage (PDF, 205KB)
• Issue Specific Hearing 12 (ISH12) into Noise (PDF, 207KB)
• Issue Specific Hearing 13 (ISH13) into Traffic and transport (PDF, 211KB)

Agendas for events commencing week of 15th March will be published 9 March 2021.

Further Written Questions (ExQ3) were not published on this occasion.

2 March 2021

The Agendas for the following events have been published:
Issue Specific Hearing 10 (ISH10) into Health and Wellbeing Assessment (PDF, 204KB)
Issue Specific Hearing 11 (ISH11) into Flood risk and drainage (PDF, 205KB)
Issue Specific Hearing 12 (ISH12) into Noise (PDF, 207KB)
Issue Specific Hearing 13 (ISH13) into Traffic and transport (PDF, 211KB)

Agendas for events commencing week of 15th March will be published 9 March 2021.

22 February 2021

The Examining Authority have issued a Procedural Decision (PDF, 427KB) in relation to Issue Specific Hearing 9 Agenda Item 1a.

The Action Points for Compulsory Acquisition Hearings (CAH) 2, Issue Specific Hearings (ISH) 7 into Biodiversity, ISH8 into Seascape and ISH9 into the draft Development Consent Order (dDCO) have been published. The recordings and transcripts for these events have also been published.

The time reserved for CAH2A, ISH7A, ISH8A and ISH9A in w/c 23 March 2021 will no longer be required and have therefore been cancelled.

19 February 2021

The Action Points for CAH2, (PDF, 148 KB)  ISH7 into Biodiversity (PDF, 157 KB) and ISH8 into Seascape  (PDF, 141 KB) have been published. The recordings and transcripts for these events have also been published.

The time reserved for CAH2A, ISH7A, ISH8A and ISH9A in w/c 23 March 2021 will no longer be required and have therefore been cancelled.

12 February 2021

The Examining Authority further written questions (ExQ2) (PDF, 632KB) and Commentaries on the draft Development Consent Order (PDF, 573KB) have been published. The published Rule 8(3) Letter (PDF, 474 KB) dated 9 February 2021 confirms the deadline for receipt of responses.

The Livestream for events running w/c 15 February 2021 is available for those wishing to observe in real time.

Please refer to the appropriate Agendas for each day, being Compulsory Acquisition Hearing 2 (CAH2) (PDF, 134 KB) (Tuesday) ; ISH7 into Biodiversity (PDF, 132 KB) (Wednesday); ISH8 into Seascape (PDF, 124 KB) (Thursday) and ISH9 into the draft Development Consent Order (PDF, 132 KB) (Friday), which have been published.

9 February 2021

The Examining Authority Rule 8(3) Letter (PDF, 474KB) has been published, giving details of changes to the Examination Timetable and notification for events to be held in March 2021.

8 February 2021

The Agendas for the following events have been published:

8 February 2021

25 January 2021

The Examining Authority Rule 8(3) Letter (PDF, 258KB) has been published, giving details of changes to the Examination Timetable and notification for events to be held in February 2021. Please refer to the appropriate Actions Points for: ISH3 into Biodiversity and HRA (PDF, 99KB); ISH4 into Onshore Environment, Construction, Transport and Operational effects (PDF, 92KB); ISH5 into Social, Economic, Land and Sea Use effects (PDF, 93KB); and Open Floor Hearing 6 (PDF, 97KB), which have been published.

Agenda for Open Floor Hearing 7 (PDF, 106 KB) (Thursday 28 January) and the Agenda for ISH6 into the Draft DCO (PDF, 213KB) (Friday 29 January) has been published. You can access the livestream for these events here.

19 January 2021

The livestream for events w/c 18 January 2021 is available for those wishing to observe in real time.

Please refer to the appropriate Agendas for each day, being ISH3 into Biodiversity and HRA (PDF, 172 KB)  (Tuesday) ; ISH4 into Onshore Environment, Construction, Transport and Operational effects (PDF, 212 KB) (Tuesday and Wednesday); ISH5 into Social, Economic, Land and Sea Use effects (PDF, 206 KB)  (Thursday) and Open Floor Hearing 6 (PDF, 106 KB)  (Friday), which have been published.

The final updated Site Inspection Itinerary  ( PDF, 3MB)  (Tuesday 26 and Wednesday 27 January), Agenda for Open Floor Hearing 7 (PDF, 106 KB)  (Thursday 28 January) and the Agenda for ISH6 into the Draft DCO  (PDF , 213KB)  (Friday 29 January) for events commencing w/c 25 January 2021 has been published.

8 January 2021

The Agendas for the following events have been published:
Issue Specific Hearing 3 (ISH3) into Biodiversity and Habitats Regulations Assessment (PDF, 172 KB)
Issue Specific Hearing 4 (ISH4) into Onshore Environment, construction, transport and operational effects (PDF, 142 KB)
Issue Specific Hearing 5 into Social, economic, land and sea use effects (ISH5) (PDF, 133 KB) and
Open Floor Hearings 6 and 7 (OFH6 and OFH7) (PDF, 69 KB) has been updated 13 January 2021

The Agenda for Issue specific Hearing 6 (ISH6) and the Itineraries for Accompanied Site Inspection 1 and 2 (ASI1 and ASI2) will be published no later than 19 January 2021

17 December 2020

Deadline 3 submissions have now been published. A Rule 17 Request has been issued to the Applicant and other named Interested Parties. Any parties wishing to provide a response to any questions within this letter can do so by Deadline 4.

8 December 2020

The Examining Authority Rule 8(3) Letter (PDF, 496KB) has been published, giving details of changes to the Examination Timetable and notification for events to be held in January 2021.

The Frequently Asked Questions (PDF, 388KB) has been updated and published. The recordings and transcripts for Issue Specific Hearings and Compulsory Acquisition Hearings held w/c 30 November 2020 have been published, including ISH1 Action Points (PDF, 121KB), CAH1 Action Points (PDF, 167KB) and ISH2 Action Points (PDF, 212KB).

Following the Examining Authority’s (ExA) decision to accept the Additional Land Application (PDF, 172KB) for examination, comments are now invited on the Applicant’s proposed provision by Deadline 4 – 13 January 2021.

Please note that any comments must be made on the Registration and Relevant Representation Form and must relate to the Applicant’s application for Additional Land  (PDF, 4MB) only; any submissions that are not in relation to the application for Additional Land, or are not on the prescribed form, will not be seen by the ExA and will be disregarded. Comments submitted after the deadline will also be disregarded.

7 December 2020

Following the Examining Authority’s (ExA) decision to accept the Additional Land Application (PDF, 172KB) for examination, comments are now invited on the Applicant’s proposed provision by Deadline 4 – 13 January 2021.

Please note that any comments must be made on the Registration and Relevant Representation Form and must relate to the Applicant’s application for Additional Land  (PDF, 4MB) only; any submissions that are not in relation to the application for Additional Land, or are not on the prescribed form, will not be seen by the ExA and will be disregarded. Comments submitted after the deadline will also be disregarded.

4 December 2020

The action points for Compulsory Acquisition Hearing 1 (CAH1) (PDF, 167KB)
and Issue Specific Hearing 2 (ISH2) (PDF, 212KB) has now been published.

2 December 2020

The Applicant has submitted a revised dDCO and Schedule of Changes which has been accepted by the ExA as an additional submission on 01 December 2020, the ExA has also on 02 December 2020 accepted the additional submission made by Save our Sandlings regarding Cumulative Impact (PDF, 6MB).

Issue Specific Hearing 1 Action Points (PDF, 121KB) have now been published.

The Livestream for ISH2 is available for those wishing to observe in real time. Please refer to the Agenda for Issue Specific Hearing 2 (ISH2) into Onshore siting, design and construction (PDF, 144KB) to see when the event will start broadcasting ‘LIVE’.

The Applicant has provided a presentation to cover Agenda items 3b and 3c during ISH2 (PDF, 5MB), this has been accepted by the ExA as an additional submission on 26 November 2020 and published to the project page.

If the Livestream doesn’t initially work, it may be resolved by refreshing the page or if you can’t hear anything, it may be that your sound is turned off and therefore un-muting or increasing the sound volume may resolve the issue.

27 November 2020

Joining instructions have been sent to all invitees for events commencing week of 30 November 2020. The Livestream for Events w/c 30 November 2020. is available for those wishing to observe in real time. Please refer to the Agendas for Issue Specific Hearing 1 (ISH1) into Biodiversity and HRA (PDF 167KB), Compulsory Acquisition Hearing 1 (CAH1) (PDF , 148KB) and Issue Specific Hearing 2 (ISH2) into Onshore siting, design and construction (PDF, 144KB) to see when each event will start broadcasting 'LIVE'.

The Applicant has provided a presentation to cover Agenda items 3b and 3c during ISH2, this has been accepted by the ExA as an additional submission (PDF 5KB) on 26 November 2020 and published to the project page.

If the Livestream doesn’t initially work, it may be resolved by refreshing the page or if you can’t hear anything, it may be that your sound is turned off and therefore un-muting or increasing the sound volume may resolve the issue.

24 November 2020

The Agendas for Issue Specific Hearing 1 (ISH1) into Biodiversity and HRA, (PDF, 167KB) Compulsory Acquisition Hearing 1 (CAH1) (PDF, 148KB) and  Issue Specific Hearing 2 (ISH2) into Onshore siting, design and construction (PDF, 144KB) ; commencing week of 30 November 2020 have now been published.

The Examining Authority has used its discretion to accept the late submission made by SASES and these have now been published.

19 November 2020

The Examining Authority has issued a Procedural Decision in relation to the Applicant’s change application (PDF, 172KB) and published an updated Ongoing Procedural Decision Tracker, (PDF, 125KB) along with a Compulsory Acquisition (Regulation 2010) Regulation 6 – Proposed Provisions Checklist (PDF, 153KB).

Having considered the range of submissions received at Deadline 1, whilst also preparing for events to be held from 1 – 3 December 2020, the ExAs have decided that further Written Questions (ExQ2) will not be published on 26 November 2020.

5 November 2020

The OFH4A reserved to start at 2pm this afternoon (5 November 2020) will no longer be required and is therefore cancelled.

The Livestream of Open Floor Hearing 5 is available for those wishing to observe it this week in real time. Please refer to the updated Agenda for Open Floor Hearing 4 and 5 (PDF, 107 KB) to see when each event will start broadcasting ‘LIVE’ and the updated List of Speakers per event. If the Livestream doesn’t initially work, it may be resolved by refreshing the page or if you can’t hear anything, it may be that your sound is turned off and therefore un-muting or increasing the sound volume may resolve the issue.

19 October 2020

The Rule 8 Letter confirms the timetable and procedural decisions for the Examination. Read the letter

The Preliminary Meeting recordings and meeting note (PDF, 565KB) for both parts have now been published.

Open Floor Hearings 1-3 (OFH1-3) recordings and action list (PDF, 117KB) are also available.

The Examining Authority has carried out its fourth Unaccompanied Site Inspection (USI4) and the USI4 Site Note (PDF, 4MB) undertaken on 12-13 October 2020 has been published. Please review this note prior to making any site inspection nomination for Deadline 1.

16 October 2020

Recordings of both parts of the Preliminary Meetings and Open Floor Hearings 1, 2 and 3 (OFHs 1 – 3) have been published.

12 October 2020

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.

Procedural decision following Preliminary Meeting.

9 October 2020

The OFH3A reserved to start at 2pm this afternoon (9 October 2020) will no longer be required and is therefore cancelled. The Rule 8 Letter and the Examining Authority first written questions (ExQ1) will be published on Monday 12 October 2020.

8 October 2020

The OFH2AB reserved to start at 6pm this evening (8 October 2020) will no longer be required and is therefore cancelled.

Open Floor Hearing 3 (OFH3) will still commence at 10am on 9 October 2020 as notified within the Rule 6 Letter.

Those parties speaking at the Open Floor Hearings this week will be sent joining instructions on how to participate before each event.

The Livestream of Open Floor Hearing 1-3 is available for those wishing to observe this week in real time. Please refer to the Agenda for OFH 1-3 (PDF, 227kb) to see when each event will start broadcasting ‘LIVE’. If the Livestream doesn’t initially work, it may be resolved by refreshing the page or if you can’t hear anything, it may be that your sound is turned off and therefore un-muting or increasing the sound volume may resolve the issue.

 

6 October 2020

Examination begins

5 October 2020

Responses submitted for Procedural Deadline C have been published. Additionally, the Examining Authority has published a detailed agenda for part 2 of the Preliminary Meeting, (PDF, 158kb) which will be held on Tuesday 6 October 2020. Procedural Deadline C submissions, and detailed agenda, have been added to the Examination Library (PDF, 854kb).

28 September 2020

The Examining Authority has now published the detailed Agendas for Open Floor Hearings (OFHs1 - 3) to be held 7-9 October 2020. Annex A to this Agenda provides a running order of speakers and starting time for each OFH event. Speakers have been notified via email today which OFH they are expected to speak at and are encouraged to review Annex B which provides further explanation and advice for speakers prior to attending the OFHs.

For those wishing to observe the OFHs via the internet on a computer or smart phone on Wednesday 7th, Thursday 8th and Friday 9th October 2020 (please refer to the Agenda for start times), this will be broadcast via Livestream. Please use the following link on the day:

Observe the EA1N and EA2 Offshore Windfarm Open Floor Hearings

18 September 2020

The recordings of the Preliminary Meeting (Part 1) Recording of the Preliminary Meeting (Part 1) (Session 1), Recording of the Preliminary Meeting (Part 1) (Session 2) and Recording of the Preliminary Meeting (Part 1) (Session 3) have been published and added to the Examination Library. Any responses to matters discussed during the PM must be submitted by Procedural Deadline C (Tuesday 29 September 2020).

The East Anglia ONE North (EA1N) and East Anglia TWO Case Teams will be running MS Teams Familiarisation Sessions w/c 28 September 2020, in advance of the Examination starting and the scheduled Open Floor Hearing events (7-9 October). If there are any Interested Parties wishing to attend these Familiarisation Sessions please contact either the EA1N and/ or EA2 case team to request your participation. Requests must be received no later than Wednesday 23 September 2020.

The Case Team would appreciate it if you could confirm your name, unique reference number for these project and your preferred time to attend being 10.00am to 11.00am OR 12.00pm to 1.00pm. The Case Team will confirm via a joining instruction email the date and time you will be expected to attend a dedicated Familiarisation Session. Please be advised that we may not be able to offer everyone a session, however, we will run a further Familiarisation Session for those that were not successful this time during the Examination and before the first round of Issue Specific Hearings.

16 September 2020

Preliminary Meeting takes place

11 September 2020

The Examining Authority has now published the detailed Agenda for Part 1 of the Preliminary Meeting (PM), (PDF, 146KB) which will open at 10.00 on Wednesday 16 September 2020.

The Examining Authority would like to thank those who provided written submissions by Procedural Deadline A. These have been very helpful ahead of the PM. For those that have indicated a wish to speak on specific agenda items, instructions on how to join the meeting will be issued by email on Tuesday 15 September 2020.

For those that would like to view the PM in real time, the link to the livestream will be published on this project web page on Tuesday 15 September 2020.

Those participating or observing the PM should familiarise themselves with the Rule 6 letter (PDF, 601kb), dated 16 July 2020. It is particularly important to read Annex B, which provides an introduction to the PM, as this will not be covered in detail in the meeting.

 

9 September 2020

The Examining Authority would like to thank those who provided written submissions by Procedural Deadline A. These have been very helpful ahead of the Preliminary Meeting (PM), which will open at 10.00 on Wednesday 16 September 2020.

For those that have indicated a wish to speak on specific agenda items, instructions on how to join the meeting will be issued by email on Tuesday 15 September 2020.

For those that would like to view the PM in real time, the link to the livestream will be published on this project web page on Tuesday 15 September 2020.

Those participating or observing the PM should familiarise themselves with the Rule 6 letter (PDF, 601kb), dated 16 July 2020. It is particularly important to read Annex B, which provides an introduction to the PM, as this will not be covered in detail in the meeting.

28 August 2020

The ExA has now published submissions made at Procedural Deadline A as two documents to assist preparations for the Preliminary Meeting: a Report of procedural submissions from persons attending the Preliminary Meeting (PDF 382kb) and a Report of procedural submissions from persons not attending the Preliminary Meeting (PDF 876kb).

11 August 2020

The notification of the Preliminary Meeting (Rule 6 letter dated 16 July 2020 (PDF 601kb) refers to Annex B which introduces the Preliminary Meeting and how you can participate. The FAQs provide further information on the Preliminary Meeting (PDF 443kb) , the Examination and the Involvement form. Interested Parties wishing to participate must complete the Preliminary Meeting Involvement Form by Procedural Deadline A which is this Thursday 13 August 2020.

16 July 2020

The new Rule 6 Letter notifying you of the Preliminary Meeting has been issued, that includes the draft Examination timetable and replaces the Rule 6 letter of 21 February 2020. Once you have read the letter, please complete the Preliminary Meeting Involvement Form, which must be completed by Procedural Deadline A (13 August 2020). Further information relating to the Involvement Form, Preliminary Meeting and the Examination is contained in the updated Frequently Asked Questions document.

26 June 2020

The Examining Authority has exercised its discretion to accept Additional Submissions in direct response to questions and on procedural matters from:

These documents have been added to the Examination Library.

Please note that the Examination has not yet started so, whilst the ExA is interested in your views about how the Examination could be run, it cannot consider any submissions about the planning merits of the application. Those must be made later, during the Examination itself. As the ExA has not called for any written submissions other than responses to the questionnaire and procedural matters, it will not accept, consider or publish any written submissions that address the planning merits of the application.

8 June 2020

Please remember that there is a deadline this Thursday 11 June for the following:

• Responses to the questionnaire on how virtual hearings might be used to examine the application, to inform our thinking on the forthcoming examination to be submitted by 5pm

• Responses to procedural decisions for the submission of early drafts of Statements of Common Ground (7.1) and Comments on Relevant Representations (11).

21 May 2020

The Examining Authority has issued a Procedural Decision in respect of draft submissions and inviting representations on how hearings might be held: these representations should be provided as responses to the online questionnaire, by 5pm 11 June 2020.

Representations Questionnaire

 


 


Frequently Asked Questions (version 1.0) document has also now been published.

14 May 2020

Consistent with the Written Ministerial Statement of 13 May 2020, the Examining Authority is considering whether and how virtual events should proceed for this case, including the practical measures needed to ensure fair participation by all. An update will be provided as soon as one is available.

Meanwhile, in its letter postponing the Preliminary Meeting, the ExA urged the Applicant and Interested Parties to use time before the start of the Examination to press ahead with the work necessary to prepare Statements of Common Ground, using virtual working methods to replace meetings. It also encouraged the Applicant to prepare responses to Relevant Representations. This important work will assist the ExA greatly by making the Examination process clearer and simpler once a start is made.

4 May 2020

In its letter postponing the Preliminary Meeting, the ExA urged the Applicant and Interested Parties to use time before the start of the Examination to press ahead with the work necessary to prepare Statements of Common Ground, using virtual working methods to replace meetings. It also encouraged the Applicant to prepare responses to Relevant Representations. This important work will assist the ExA greatly by making the Examination process clearer and simpler once a start is made.

17 March 2020

Please note the Preliminary Meeting and Hearings due to be held 24 – 26 March 2020 have been postponed in light of the current public health situation surrounding coronavirus (COVID-19).

Please see the Examining Authority's (ExA's) procedural decision to postpone the Preliminary Meeting (PM) and Hearings for further information.

We are not yet in a position to identify a revised timeline. Updates will be announced shortly

11 March 2020

IMPORTANT: In the light of the current public health situation surrounding coronavirus (COVID-19), if you are planning to attend the Preliminary Meeting and Hearings w/c 23 March 2020 please check this website, and that of the venue (Snape Maltings), regularly and before travelling to the events. If there are any changes or cancellations required to the Preliminary Meeting or Hearings this page will be updated as soon as possible. Advice is available and you are requested to please take careful note of it.

4 March 2020

21 February 2020

The notification of Preliminary Meeting (Rule 6 letter) has been sent.

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

20 February 2020

Relevant representations published on the website

27 January 2020

Registration of interested parties closes

3 January 2020

You can now register as an Interested PartyRegister online
If you wish to have your say on East Anglia One North and East Anglia Two you must register for each application separately.
If you are unable to complete a registration form online and would like to register your interest, please call the helpline on: 0303 444 5000 to request a paper form. For further advice please see Advice Note 8.2: How to register to participate in an Examination.
Please see our Frequently Asked Questions for more information.

29 November 2019

Registration of interested parties begins

22 November 2019

The application has been accepted for examination

25 October 2019

Application received by the Planning Inspectorate