Back to list East Anglia ONE North Offshore Windfarm

Representation by Richard Gardiner

Date submitted
21 January 2020
Submitted by
Members of the public/businesses

The connecting cables from Thorpeness and the substation at Friston will cause temporary and permanent damage and loss of amenity. This is unnecessary and/or the possible alternative siting at or near Sizewell, which would involve reduced need for connecting cable and cause less damage and loss of amenity, has not been properly investigated and considered.