The list below includes a record of advice we have provided for this project.
There is a statutory duty, under section 51 of the Planning Act 2008, around an application or potential application. This includes recording the name of the person who requested advice and the advice given. This information has to be made publicly available.
Search by key words or the name of person the advice was given to.
Showing 51 to 80 of 80 documents, newest first.
Results per page View 25 results per page | 50 | View 100 results per page
Enquiry sent to the Secretary of State.
Enquiry sent to the Secretary of State
Please see attached letter from Chris Wheeler (dated 01 August 2018)
Planning Act 2008 process meeting with Scottish Power Renewables
Project update meeting with the representatives of Suffolk Coastal and Waveney District Councils (SC&WDCs) and Suffolk County Council (SCC).
Query regarding selection of Zone 7 Friston by Scottish Power for the onshore wind farm substation and grid connection.
Dear Sir Re: Scottish Power Substations for East Anglia2 and East Anglia1 North Substations We live in Friston Suffolk. We attended a presentation by Scottish Power on 24th May 2018 which outlined the... Read more
Query regarding consultation and selection of Zone 7 Friston by Scottish Power for the EA2 onshore wind farm substation and grid connection.
Project update meeting
Dear Mr White I am assuming that as Infrastructure Planning Lead, you have overall responsibility for Planning Inspectorate's supervision of the statutory processes being undertaken by ScottishPowe... Read more
Project Update Meeting
Query regarding the pre-application consultation
See attached query
Project update meeting 25 January 2018
Please see meeting note attached
Evidence Plan Steering Group Meeting
Inception meeting