All project updates
10 May 2024
A Decision Letter (PDF, 205KB) and Amendment Order (PDF, 153KB) have been issued by the Department of Energy Security and Net Zero to make a change that is not material to the Hornsea Three Offshore Wind Farm Order 2020.
15 March 2024
The Secretary of State for Energy Security and Net Zero has made a decision (PDF, 187KB) to approve the Kittiwake Implementation and Management Plan, as required by Part 2 of Schedule 14 to the Development Consent Order.
14 February 2024
Natural England’s response to the Non-Material Change Consultation (PDF, 113KB) in response to the application for a non-material change to the Made Hornsea Project Three Offshore Wind Farm Development Consent Order has been published.
16 January 2024
The deadline for receipt of representations is 12 February 2024.
If you wish to make a representation, this should be emailed to hornseaprojectthree@planninginspectorate.gov.uk or posted to:
National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol BS1 6PN
17 April 2023
6 March 2023
3 March 2023
The Consultation and Publicity Statement (PDF, 58 MB) for the non-material change application has been published.
20 February 2023
2 February 2023
In accordance with Schedule 14 Part 1 of the Hornsea Three Offshore Wind Farm Order 2020 the Secretary of State has invited the Marine Management Organisation, Natural England, Hartlepool Borough Council, Durham County Council, and East Suffolk Council, to comment on the KIMP.
The deadline for responses is 23.59 on 3 March 2023.
12 January 2023
An application for a non-material change to the Hornsea Project Three Offshore Wind Farm Development Consent Order has been made by Orsted Hornsea Project Three (UK) Ltd.
If you wish to make a representation, this should be emailed to HornseaProjectThree@planninginspectorate.gov.uk or posted to:
National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol BS1 6PN
The deadline for receipt of representations is 11:59pm on Thursday 16 February 2023
21 December 2022
13 April 2022
7 April 2022
25 January 2022
10 December 2021
3 December 2021
8 September 2021
24 May 2021
- Correction Notice (PDF, 145KB)
- Correction Order (PDF, 102KB)
31 December 2020
- Secretary of State’s Decision Letter (PDF, 541 KB);
- Planning Inspectorate Decision Cover Letter (PDF, 125 KB);
- Development Consent Order as Made (PDF, 3MB);
- Examining Authority’s Recommendation Report (PDF, 6MB);
- Habitats Regulations Assessment (PDF, 2MB);
- Regulation 23 Notice (PDF, 65KB);
- Post Examination correspondence bundle (PDF, 7MB).
31 December 2020
10 November 2020
2 October 2020
7 September 2020
1 July 2020
- Draft Development Consent Order
- Draft Habitats Regulation Assessment
- Examining Authority's Recommendation Report
To allow time for the Applicant to submit further information by 30 September 2020 and to allow for consultation on the further information with Interested Parties, the Secretary of State has set a new deadline of 31 December 2020 for his decision on this application. The Secretary of State has asked the Planning Inspectorate to facilitate the consultation process via the project page of the National Infrastructure Planning website.
1 June 2020
24 April 2020
3 April 2020
2 March 2020
6 February 2020
19 December 2019
31 October 2019
17 October 2019
27 September 2019
25 July 2019
10 July 2019
2 July 2019
3 April 2019
29 March 2019
28 March 2019
Recording of Open Floor Hearing 3 - 25 March 2019
Recording of Further Issue Specific Hearing - 26 March 2019
Recording of Further Compulsory Acquisition Hearing - 26 March 2019
Deadline 9 Submissions have also been published.
27 March 2019
22 March 2019
19 March 2019
Ørsted Hornsea Project Three (UK) Ltd
Norfolk County Council
Natural England
15 March 2019
Agenda for Open Floor Hearing 3
Agenda for Further Issue Specific Hearing
Agenda for Further Compulsory Acquisition Hearing
Deadline 7 Submissions have also been published.
7 March 2019
Please note that the Issue Specific Hearing on Friday 8th March 2019 will commence at 9am (doors open at 8:30am) and not at 9.30.
6 March 2019
27 February 2019
Agenda for Issue Specific Hearing 7: Offshore ecology
Agenda for Issue Specific Hearing 8: Aviation, shipping and effects on oil and gas operations
Agenda for Issue Specific Hearing 9: Part 1 – Cumulative traffic impacts and related mitigation measures and Part 2 – The draft DCO
26 February 2019
21 February 2019
20 February 2019
13 February 2019
8 February 2019
6 February 2019
24 January 2019
The Examination Authority has issued a procedural decision regarding the Applicant’s proposed design changes to the original application.
The Examination Authority has issued a procedural decision to accept the proposed provision for the compulsory acquisition of additional land as part of the application.
23 January 2019
21 January 2019
Open Floor Hearing - Monday 28 January 2019
Issue Specific Hearing 5: Offshore ecology - Tuesday 29 January 2019
Issue Specific Hearing 6: The draft Development Consent Order - Wednesday 30 January
Compulsory Acquisition Hearing - Thursday 31 January 2019
The Itinerary for the Accompanied Site Inspection on 28 January 2019 has also been published.
20 December 2018
20 December 2018
19 December 2018
18 December 2018
27 November 2018
Hearing agendas have now been published.
27 November 2018
23 November 2018
9 November 2018
7 November 2018
5 November 2018
25 October 2018
9 October 2018
Procedural decision following Preliminary Meeting.
3 October 2018
2 October 2018
4 September 2018
The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.
3 September 2018
27 July 2018
The relevant representations received up until 22 July 2018 have been published and any relevant representations received from those parties set out in the letter above, will be published when the further deadline has passed.