All project updates
10 Mai 2024
A Decision Letter (PDF, 205KB) and Amendment Order (PDF, 153KB) have been issued by the Department of Energy Security and Net Zero to make a change that is not material to the Hornsea Three Offshore Wind Farm Order 2020.
15 Mawrth 2024
The Secretary of State for Energy Security and Net Zero has made a decision (PDF, 187KB) to approve the Kittiwake Implementation and Management Plan, as required by Part 2 of Schedule 14 to the Development Consent Order.
14 Chwefror 2024
Natural England’s response to the Non-Material Change Consultation (PDF, 113KB) in response to the application for a non-material change to the Made Hornsea Project Three Offshore Wind Farm Development Consent Order has been published.
16 Ionawr 2024
The deadline for receipt of representations is 12 February 2024.
If you wish to make a representation, this should be emailed to hornseaprojectthree@planninginspectorate.gov.uk or posted to:
National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol BS1 6PN
17 Ebrill 2023
6 Mawrth 2023
3 Mawrth 2023
The Consultation and Publicity Statement (PDF, 58 MB) for the non-material change application has been published.
20 Chwefror 2023
2 Chwefror 2023
In accordance with Schedule 14 Part 1 of the Hornsea Three Offshore Wind Farm Order 2020 the Secretary of State has invited the Marine Management Organisation, Natural England, Hartlepool Borough Council, Durham County Council, and East Suffolk Council, to comment on the KIMP.
The deadline for responses is 23.59 on 3 March 2023.
12 Ionawr 2023
An application for a non-material change to the Hornsea Project Three Offshore Wind Farm Development Consent Order has been made by Orsted Hornsea Project Three (UK) Ltd.
If you wish to make a representation, this should be emailed to HornseaProjectThree@planninginspectorate.gov.uk or posted to:
National Infrastructure
The Planning Inspectorate
Temple Quay House
2 The Square
Bristol BS1 6PN
The deadline for receipt of representations is 11:59pm on Thursday 16 February 2023
21 Rhagfyr 2022
13 Ebrill 2022
7 Ebrill 2022
25 Ionawr 2022
10 Rhagfyr 2021
3 Rhagfyr 2021
8 Medi 2021
24 Mai 2021
- Correction Notice (PDF, 145KB)
- Correction Order (PDF, 102KB)
31 Rhagfyr 2020
- Secretary of State’s Decision Letter (PDF, 541 KB);
- Planning Inspectorate Decision Cover Letter (PDF, 125 KB);
- Development Consent Order as Made (PDF, 3MB);
- Examining Authority’s Recommendation Report (PDF, 6MB);
- Habitats Regulations Assessment (PDF, 2MB);
- Regulation 23 Notice (PDF, 65KB);
- Post Examination correspondence bundle (PDF, 7MB).
31 Rhagfyr 2020
10 Tachwedd 2020
2 Hydref 2020
7 Medi 2020
1 Gorffennaf 2020
- Draft Development Consent Order
- Draft Habitats Regulation Assessment
- Examining Authority's Recommendation Report
To allow time for the Applicant to submit further information by 30 September 2020 and to allow for consultation on the further information with Interested Parties, the Secretary of State has set a new deadline of 31 December 2020 for his decision on this application. The Secretary of State has asked the Planning Inspectorate to facilitate the consultation process via the project page of the National Infrastructure Planning website.
1 Mehefin 2020
24 Ebrill 2020
3 Ebrill 2020
2 Mawrth 2020
6 Chwefror 2020
19 Rhagfyr 2019
31 Hydref 2019
17 Hydref 2019
27 Medi 2019
25 Gorffennaf 2019
10 Gorffennaf 2019
2 Gorffennaf 2019
3 Ebrill 2019
29 Mawrth 2019
28 Mawrth 2019
Recording of Open Floor Hearing 3 - 25 March 2019
Recording of Further Issue Specific Hearing - 26 March 2019
Recording of Further Compulsory Acquisition Hearing - 26 March 2019
Deadline 9 Submissions have also been published.
27 Mawrth 2019
22 Mawrth 2019
19 Mawrth 2019
Ørsted Hornsea Project Three (UK) Ltd
Norfolk County Council
Natural England
15 Mawrth 2019
Agenda for Open Floor Hearing 3
Agenda for Further Issue Specific Hearing
Agenda for Further Compulsory Acquisition Hearing
Deadline 7 Submissions have also been published.
7 Mawrth 2019
Please note that the Issue Specific Hearing on Friday 8th March 2019 will commence at 9am (doors open at 8:30am) and not at 9.30.
6 Mawrth 2019
27 Chwefror 2019
Agenda for Issue Specific Hearing 7: Offshore ecology
Agenda for Issue Specific Hearing 8: Aviation, shipping and effects on oil and gas operations
Agenda for Issue Specific Hearing 9: Part 1 – Cumulative traffic impacts and related mitigation measures and Part 2 – The draft DCO
26 Chwefror 2019
21 Chwefror 2019
20 Chwefror 2019
13 Chwefror 2019
8 Chwefror 2019
6 Chwefror 2019
24 Ionawr 2019
The Examination Authority has issued a procedural decision regarding the Applicant’s proposed design changes to the original application.
The Examination Authority has issued a procedural decision to accept the proposed provision for the compulsory acquisition of additional land as part of the application.
23 Ionawr 2019
21 Ionawr 2019
Open Floor Hearing - Monday 28 January 2019
Issue Specific Hearing 5: Offshore ecology - Tuesday 29 January 2019
Issue Specific Hearing 6: The draft Development Consent Order - Wednesday 30 January
Compulsory Acquisition Hearing - Thursday 31 January 2019
The Itinerary for the Accompanied Site Inspection on 28 January 2019 has also been published.
20 Rhagfyr 2018
20 Rhagfyr 2018
19 Rhagfyr 2018
18 Rhagfyr 2018
27 Tachwedd 2018
Hearing agendas have now been published.
27 Tachwedd 2018
23 Tachwedd 2018
9 Tachwedd 2018
7 Tachwedd 2018
5 Tachwedd 2018
25 Hydref 2018
9 Hydref 2018
Procedural decision following Preliminary Meeting.
3 Hydref 2018
2 Hydref 2018
4 Medi 2018
The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.
3 Medi 2018
27 Gorffennaf 2018
The relevant representations received up until 22 July 2018 have been published and any relevant representations received from those parties set out in the letter above, will be published when the further deadline has passed.