5 April 2019

Decision made by the Secretary of State

18 March 2019

Sembcorp Utilities (UK) Limited (Applicant) has responded to The Secretary of State for Business, Energy and Industrial Strategy’s request for further comments.

25 February 2019

The  Environment Agency and Sembcorp Utilities (UK) Limited (Applicant) have responded to The Secretary of State for Business, Energy and Industrial Strategy’s request for further comments.

10 January 2019

Recommendations given by the Planning Inspectorate

11 October 2018

An Additional submission from the Applicant has been accepted at the discretion of the Examining Authority on Wednesday 10 October 2018.

10 October 2018

An additional submission from the National Grid has been accepted at the discretion of the Examining Authority.

8 October 2018

An additional submission from the Applicant has been accepted at the discretion of the Examination Authority.

5 October 2018

28 September 2018

The Examining Authority has accepted two late submissions from the applicant for deadline 7.

27 September 2018

14 September 2018

An additional submission from the Environment Agency has been accepted at the discretion of the Examination Authority.

31 August 2018

An additional submission from the Environment Agency has been accepted at the discretion of the Examination Authority.

23 August 2018

21 August 2018

The Examining Authority has accepted a late submission from Natural England for deadline 5.

10 August 2018

The submissions for deadline 5 have been published.

24 July 2018

10 July 2018

The responses received for Deadline 4 (6 July 2018) have now been published.

29 June 2018

The Examination Authority has accepted the non-material change consultation report as an additional submission from the applicant.

18 June 2018

8 June 2018

The Examination Authority has issued a Rule 17 Letter requesting comments on the Deadline 2 Submission from the Applicant that was omitted from publication on 29 May 2018.

5 June 2018

The Accompanied Site Inspection Itinerary and Agendas for Hearings in June 2018 have been published. Please note that the date reserved for the Open Floor Hearing on the evening of 13 June 2018 is not taking place as we have received no requests for one to be held.

31 May 2018

The responses received for Deadline 3 (29 May 2018) have now been published.

22 May 2018

1 May 2018

18 April 2018

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.

Procedural decision following Preliminary Meeting.

10 April 2018

Preliminary Meeting takes place

10 April 2018

Examination begins

9 March 2018

The notification of Preliminary Meeting (Rule 6 letter) has been sent.

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

14 February 2018

Relevant representations published on the website

9 February 2018

Registration of interested parties closes

11 January 2018

Registration of interested parties begins

18 December 2017

The application has been accepted for examination

23 November 2017

This application was received by the Planning Inspectorate on 22 November 2017.

The application documents will be made available if the application is accepted for examination.

It is for the applicant to decide whether or not application documents can be published upon submission (see DCLG pre-application https://www.gov.uk/government/publications/guidance-on-the-pre-application-process-for-major-infrastructure-projects)

22 November 2017

Application received by the Planning Inspectorate