Cyngor i Wendy Englestone

Yn ôl i'r rhestr

Ymholiad

Oddiwrth
Wendy Englestone
Y dyddiad y rhoddwyd y cyngor
8 Mawrth 2018
Math o ymholiad
Email

What policing has gone on regarding Vattenfall in Norfolk during consultation in which they did not behave correctly? Project still going ahead revised plans a no relay Stations HDVC , please can you provide information

Cyngor a roddwyd

The Applicant is required to produce a consultation report detailing how they have complied with the consultation requirements of sections 42, 47 and 48 of the Planning Act 2008. This should be submitted with the application and will be checked, along with the other application documents, as part of the Acceptance process.