21 October 2020

The Secretary of State for Business, Energy and Industrial Strategy has today granted development consent for the project. For further information please refer to the following documents:

21 October 2020

Decision made by the Secretary of State

21 July 2020

Recommendations given by the Planning Inspectorate

15 April 2020

The Deadline 7 Submissions have now been published.

2 April 2020

Deadline 6 submissions have now been published.

9 March 2020

The Rule 17 – Request for further information has now been Published.

25 February 2020

Deadline 5 submissions have now been published and the Examination Library has been updated.

10 February 2020

The Examining Authority has exercised its discretion to accept an Additional Submission from the Canal & Rivers Trust. This has been added to the Examination Library.

3 February 2020

Deadline 4 submissions have now been published and the Examination Library has been updated.

21 January 2020

The Examining Authority has exercised its discretion to accept an Additional Submission from the Applicant in the form of a Statement of Common Ground with Bassetlaw District Council. This has been added to the Examination Library.

13 January 2020

The Itinerary for the Accompanied Site Inspection and agendas for the Open Floor Hearing and Issue Specific Hearing have been published and added to the Examination Library.

23 December 2019

 

The Deadline 3 submissions and the updated Examination Library have now been published.

10 December 2019

The Deadline 2 submissions and the updated Examination Library have now been published.

22 November 2019

The Deadline 1 submissions have been published.

6 November 2019

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.

Procedural decision following Preliminary Meeting.

5 November 2019

The Examining Authority carried out an Unaccompanied Site Inspection on 29 October 2019. A note of the inspection has been added to the Examination Library.

1 November 2019

The Examining Authority has exercised its discretion to accept an Additional Submission from ESP Utilities Group Ltd. This has been added to the Examination Library.

31 October 2019

Recording of the Preliminary Meeting - 30 October 2019 has been published.

30 October 2019

Preliminary Meeting takes place

30 October 2019

Examination begins

30 September 2019

The Examining Authority undertook an Unaccompanied Site Inspection on Wednesday 25 September 2019. A note of the visit has been published and added to the Examination Library.

26 September 2019

The notification of Preliminary Meeting (Rule 6 letter) has been sent.

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

25 September 2019

The Examining Authority has exercised its discretion to accept an Additional Submission from the Environment Agency. This has been added to the Examination Library.

16 September 2019

The Examining Authority has exercised its discretion to accept Additional Submissions from Highways England and Harlaxton Gas Networks Limited. These have been added to the Examination Library.

3 September 2019

Relevant representations published on the website

30 August 2019

Registration of interested parties closes

26 June 2019

Registration of interested parties begins

23 May 2019

The application has been accepted for examination

1 May 2019

This application was received by the Planning Inspectorate on 30 April 2019.

The application documents will be made available if the application is accepted for examination.

It is for the applicant to decide whether or not application documents can be published upon submission (see DCLG pre-application guidance).

30 April 2019

Application received by the Planning Inspectorate