Drax Re-power Examination timetable

The examination timetable shows the dates of events and deadlines for submissions.

If you have registered to have your say, you can do this in the examination stage.

The examination stage

The examination opened on 4 October 2018

The examination closed on 4 April 2019

Upcoming deadlines and events

There are no deadlines and events

Past deadlines and events

4 October 2018 - Preliminary Meeting

Closed

Preliminary Meeting

4 October 2018 - Open Floor Hearing

Closed

Open Floor Hearing

11 October 2018 - Issue by ExA of

Closed

• Examination Timetable • ExA’ Written Questions

18 October 2018 - Deadline 1

Closed

DEADLINE 1

Deadline for receipt of: • Comments on updated application documents • Comments on Relevant Representations (RR) • Summaries of all RRs exceeding 1500 words • Statements of Common Ground (SoCG) requested by the ExA • Post hearing submissions including written submissions of oral case • Notification by Statutory Parties of their wish to be considered as an IP by the ExA • Notification of wish to make oral representations at an Issue Specific Hearing (ISH) • Notification of wish to speak at any Open Floor Hearing (OFH) • Notification of wish to speak at any Compulsory Acquisition Hearing (CAH) • Notification of wish to attend an Accompanied Site Inspection (ASI) including suggested locations and justifications • Notification of wish to have future correspondence received electronically • Comments on any additional information/submissions received • Responses to any further information requested by the ExA for this Deadline

8 November 2018 - Deadline 2

Closed

DEADLINE 2

Deadline for receipt of: • Written Representations (WR’s) • Summaries of all WR’s exceeding 1500 words • Comments on SoCG’s • Local Impact Reports (LIR) from any local authorities • Responses to ExA’s Written Questions • Updated Compulsory Acquisition Schedule (Annex to Written Questions) • Draft itinerary for Accompanied Site Inspection • Comments on any additional information/submissions received by D1 • Responses to any further information requested by the ExA for this Deadline

22 November 2018 - Deadline 3

Closed

DEADLINE 3

Deadline for receipt of: • Comments on WR’s • Comments on LIR’s • Comments on responses to the ExA’s Written Questions • Any revised/updated SoCG (if any) • The Applicant’s revised draft Development Consent Order (dDCO) • Requests to attend Accompanied Site Inspection • Comments on any additional information/submissions received by D2 • Responses to any further information requested by the ExA for this Deadline

4 December 2018 - Accompanied Site Inspection

Closed

Accompanied Site Inspection

4 December 2018 - Open Floor Hearing 2 (OFH2)

Closed

Date reserved to hold OFH2

5 December 2018 - Issue Specific Hearing 1 (ISH1)

Closed

Date reserved to hold ISH1

6 December 2018 - Issue Specific Hearing 2 (ISH2)

Closed

Date reserved to hold ISH2 on the dDCO (morning)

6 December 2018 - Compulsory Acquisition Hearing 1 (CAH1)

Closed

Date reserved to hold CAH1(afternoon)

13 December 2018 - Deadline 4

Closed

DEADLINE 4

Deadline for receipt of: • Post hearing submissions including written submissions of oral case • Comments on any revised/updated SoCG (if any) • Comments on the Applicant’s revised dDCO • Comments on any additional information/submissions received by D3 • Responses to any further information requested by the ExA for this Deadline

9 January 2019 - Deadline 5

Closed

DEADLINE 5

Deadline for receipt of: • Any revised/updated SoCG (if any) • The Applicant’s revised dDCO • Comments on any additional information/submissions received by D4 • Responses to any further information requested by the ExA for this Deadline

15 January 2019 - Publication by ExA of -

Closed

• The ExA’s further Written Questions (if required)

30 January 2019 - Deadline 6

Closed

DEADLINE 6

Deadline for receipt of: • Responses to the ExA’s further Written Quetsions (if required) • Comments on any revised/updated SoCG (if any) • Comments on the Applicant’s revised dDCO • Comments on any additional information/submissions received by D5 • Responses to any further information requested by the ExA for this Deadline

12 February 2019 - Compulsory Acquisition Hearing (CAH2), Open Floor Hearing (OFH3) & Issue Specific Hearing (ISH3)

Closed

Date reserved to hold CAH2, OFH3 and ISH3

20 February 2019 - Deadline 7

Closed

DEADLINE 7

Deadline for receipt of: • Post hearing submissions including written submissions of oral case (if required) • Comments on the ExA’s further Written Questions (if required) • Any revised/updated SoCG (if any) • The Applicant’s revised dDCO • Comments on any additional information/submissions received by D6 • Responses to any further information requested by the ExA for this Deadline

28 February 2019 - Publication by ExA of -

Closed

• Report on the Implications for European Sites (RIES) • ExA’s proposed schedule of changes to the dDCO (if required)

21 March 2019 - Deadline 8

Closed

DEADLINE 8

Deadline for receipt of: • Comments on the RIES • Comments on the ExA’s proposed schedule of changes to the dDCO (if required) • Final SoCGs • Applicant’s final Compulsory Acquisition Schedule • Final updated Book of Reference • Comments on any additional information/submissions received by D7 • Responses to any further information requested by the ExA for this Deadline

28 March 2019 - Deadline 9

Closed

DEADLINE 9

Deadline for receipt of: • Applicant’s final DCO to be submitted in the SI template with the SI template validation report • Final updated Guide to the Application • Comments on any additional information/submissions received by D8 • Responses to any further information requested by the ExA for this Deadline

4 April 2019 - Close of the Examination

Closed

The ExA is under a duty to complete the examination of the application by the end of the period of 6 months beginning with the day after the close of the Preliminary Meeting