18 August 2020

The Secretary of State for Business, Energy and Industrial Strategy has issued a Correction Order. For further information please refer to the following decision documentation:

Correction Order;
Correction Notice;
Applicant’s request for Correction Order;
Applicant’s list of corrections; and
Applicant’s DCO comparison

4 October 2019

The Secretary of State has granted development consent for this application. For further information, please refer to the following decision documentation:

Notification of Decision Letter
Secretary of State Decision Letter
Development Consent Order as made by the Secretary of State
Recommendation Report
Post-Examination Submissions
Regulation 31 Notice
Habitats Regulations Assessment

4 October 2019

Decision made by the Secretary of State

4 July 2019

Recommendations given by the Planning Inspectorate

4 April 2019

The deadline for close of examination is midnight 4 April 2019.

29 March 2019

The Submissions for Deadline 9 have now been published.

22 March 2019

The Submissions for Deadline 8 have now been published.

21 February 2019

The Submissions for Deadline 7 have now been published.

20 February 2019

The Action Points from Issue Specific Hearing 3 have now been published.

13 February 2019

The Audio recordings for Compulsory Acquisition Hearing 2, Open Floor Hearing 3, and Issue Specific Hearing 3 have now been published.

6 February 2019

The agenda for Issue Specific Hearing 2 (ISH2) has now been published.

6 February 2019

The Deadline 6 Submissions have now been published.

15 January 2019

A procedural decision has been issued relating to the Applicant’s proposed changes to the application.

The Notification letter for the hearings taking place on the 12 of February 2019 has been published.

The Examination Authority’s Further Written Questions have also been published.

10 January 2019

The Deadline 5 Submissions have now been published.

14 December 2018

The documents for deadline 4 have now been published.

3 December 2018

The Examining Authority has issued a procedural decision regarding an application for additional land.

The Examining Authority has issued a procedural decision regarding the Site Reconfiguration Works and a request for further information.

An additional submission (Letter from North Yorkshire County Council) has been accepted at the discretion of the Examining Authority.

19 November 2018

An additional submission (6.2.9.10 Appendix 9.10 - Biodiversity Net Gain Assessment - Appendix 3 - Maps) has been accepted at the discretion of the Examining Authority.

 

12 November 2018

The preliminary meeting note and the submissions for deadline 2 have been published.

6 November 2018

The notification letter for the Accompanied Site Inspection (4 December 2018) and  Hearings (4 December 2018 - 6 December 2018) has been published.

19 October 2018

The submissions for deadline 1 have now been published.

11 October 2018

The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.

Procedural decision following Preliminary Meeting.

4 October 2018

Preliminary Meeting takes place

4 October 2018

Examination begins

24 September 2018

The agenda for the forthcoming open floor hearing has been published.

11 September 2018

6 September 2018

The notification of Preliminary Meeting (Rule 6 letter) has been sent.

The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.

4 September 2018

Relevant representations published on the website

29 August 2018

Registration of interested parties closes

20 July 2018

Registration of interested parties begins

26 June 2018

The application has been accepted for examination

29 May 2018

Application received by the Planning Inspectorate