18 August 2020
The Secretary of State for Business, Energy and Industrial Strategy has issued a Correction Order. For further information please refer to the following decision documentation:
Correction Order;
Correction Notice;
Applicant’s request for Correction Order;
Applicant’s list of corrections; and
Applicant’s DCO comparison
Correction Order;
Correction Notice;
Applicant’s request for Correction Order;
Applicant’s list of corrections; and
Applicant’s DCO comparison
4 October 2019
The Secretary of State has granted development consent for this application. For further information, please refer to the following decision documentation:
Notification of Decision Letter
Secretary of State Decision Letter
Development Consent Order as made by the Secretary of State
Recommendation Report
Post-Examination Submissions
Regulation 31 Notice
Habitats Regulations Assessment
Notification of Decision Letter
Secretary of State Decision Letter
Development Consent Order as made by the Secretary of State
Recommendation Report
Post-Examination Submissions
Regulation 31 Notice
Habitats Regulations Assessment
4 October 2019
Decision made by the Secretary of State
4 July 2019
Recommendations given by the Planning Inspectorate
5 April 2019
4 April 2019
The deadline for close of examination is midnight 4 April 2019.
29 March 2019
The Submissions for Deadline 9 have now been published.
22 March 2019
The Submissions for Deadline 8 have now been published.
28 February 2019
The Report on the Implications for European Sites and the Examining Authority’s schedule of changes to the draft Development Consent Order have been published.
21 February 2019
The Submissions for Deadline 7 have now been published.
20 February 2019
The Action Points from Issue Specific Hearing 3 have now been published.
13 February 2019
The Audio recordings for Compulsory Acquisition Hearing 2, Open Floor Hearing 3, and Issue Specific Hearing 3 have now been published.
6 February 2019
The agenda for Issue Specific Hearing 2 (ISH2) has now been published.
6 February 2019
The Deadline 6 Submissions have now been published.
15 January 2019
A procedural decision has been issued relating to the Applicant’s proposed changes to the application.
The Notification letter for the hearings taking place on the 12 of February 2019 has been published.
The Examination Authority’s Further Written Questions have also been published.
The Notification letter for the hearings taking place on the 12 of February 2019 has been published.
The Examination Authority’s Further Written Questions have also been published.
10 January 2019
The Deadline 5 Submissions have now been published.
14 December 2018
The documents for deadline 4 have now been published.
13 December 2018
The Recordings of Open Floor Hearing 2, Issue Specific Hearings 1 and 2 and the Compulsory Acquisition Hearing have now been published.
7 December 2018
The Examining Authority have issued a notification letter about their procedural decision to accept the Additional Land Application for examination. They have also accepted the proposed provision for the compulsory acquisition of additional land.
3 December 2018
The Examining Authority has issued a procedural decision regarding an application for additional land.
The Examining Authority has issued a procedural decision regarding the Site Reconfiguration Works and a request for further information.
An additional submission (Letter from North Yorkshire County Council) has been accepted at the discretion of the Examining Authority.
The Examining Authority has issued a procedural decision regarding the Site Reconfiguration Works and a request for further information.
An additional submission (Letter from North Yorkshire County Council) has been accepted at the discretion of the Examining Authority.
28 November 2018
The Agenda for the Open Floor Hearing 2 and the Agenda for the Issue Specific Hearing and Compulsory Acquisition Hearing have now been published.
19 November 2018
An additional submission (6.2.9.10 Appendix 9.10 - Biodiversity Net Gain Assessment - Appendix 3 - Maps) has been accepted at the discretion of the Examining Authority.
15 November 2018
The Examining Authority has accepted a joint late deadline 2 submission from North Yorkshire County Council and Selby District Council.
12 November 2018
The preliminary meeting note and the submissions for deadline 2 have been published.
6 November 2018
The notification letter for the Accompanied Site Inspection (4 December 2018) and Hearings (4 December 2018 - 6 December 2018) has been published.
2 November 2018
19 October 2018
The submissions for deadline 1 have now been published.
11 October 2018
The Examination Timetable (Rule 8 letter) has been sent to Interested Parties.
Procedural decision following Preliminary Meeting.
4 October 2018
Preliminary Meeting takes place
4 October 2018
Examination begins
24 September 2018
The agenda for the forthcoming open floor hearing has been published.
13 September 2018
Additional Submissions accepted at the discretion of the Examining Authority have been published.
11 September 2018
Procedural Decision by the Examining Authority has been published.
6 September 2018
The notification of Preliminary Meeting (Rule 6 letter) has been sent.
The letter also includes the draft Examination Timetable and Initial Assessment of Principal Issues.
4 September 2018
Relevant representations published on the website
29 August 2018
Registration of interested parties closes
20 July 2018
Registration of interested parties begins
16 July 2018
Additional Submissions accepted by the Examining Authority have been published.
26 June 2018
The application has been accepted for examination
29 May 2018
Application received by the Planning Inspectorate